Job Safety Analysis (JSA)

ALWAYS ATTACHED WITH WORK SAFETY PERMIT


Contact
Project Title: Company: IPENET SOLUTION SDN BHD
number
Work Supervisor In
Description: Charge:
□ Hot Work □ Harmful material □ Excavation work □ Heavy material □ Confined space work □ General tasks □ Lifting operation □ Others:
Work Type: □ Piping work □ Working at height □ Maintenance work □ Electrical work □ Hazardous Material □ Housekeeping □ Delivery tasks
□ Explosion □ Electrocution □ Slip, trip & fall □ Toxic fumes □ Fracture □ Skin disease □ Amputation □ Asphyxiation
Anticipated □ Laser □ Fire □ Chemical contact □ Biological Potential □ Frostbite □ Vision disorder □ Abrasion □ Hearing disorder
Hazard: □ Hit against □ Rupture □ Thermal burn □ Other Injury: □ Burn □ Poisoning □ Concussion □ Others
□ Falling object □ Vibration □ Engulfment (flood) □ Contusion □ Cut & penetration □ Death

WORK TO BE ACCOMPLISHED JOB HAZARD ANALYSIS Control


# Sequence steps for completion of work Potential Hazard Safety measure & controls  
 all the material & toolbox are placed and organized to
Preparation of equipment’s (Toolbox &
1 Messy workplace & possibility to trip. avoid tripping hazard
Material)
 ensure the working area is organized
 Cordon off the work area
Slip, Trip and Fall.
 Need to do housekeeping after cable installation
 Implement buddy system
Ergonomics Awkward posture and
 Resting in between works
2 Cable installation Repetition
 Ensure all in good health before start work
 Inspect tool all in good condition before start work
Physical Hazard  Use tools accordingly to the recommended cutting
condition

 Cordon off the work area


Slip, Trip and Fall.  Need to do housekeeping after cable installation
3 Cable Trunk installation  Implement buddy system
Ergonomics Awkward posture and
 Resting in between works
Repetition
 Ensure all in good health before start work
Job Safety Analysis (JSA)
WORK TO BE ACCOMPLISHED JOB HAZARD ANALYSIS Control
# Sequence steps for completion of work Potential Hazard Safety measure & controls  
 Implement buddy system
Straining, stress on knees, wrist injury,  Resting in between works
4 Installation of Cable Trunk (work at height)
falling off from ladder/ scaffold  Ensure all in good health before start work

Network Termination  Inspect tools in good condition before start work.


5 Physical Hazard (Body Injuries)  Use accordingly to the recommended cutting
 Using general cutting tools condition

Network cable testing  Inspect tools in good condition before start work.
6 Physical Hazard (Body Injuries)  Use accordingly to the tool’s user manual
 Using testing tools

 Assure ladder/scaffolding is stable and have partner to


falling off from ladder/ scaffold keep balance.
7 Wall opening and make good (Plastering)
 Assure drill bit is properly engaged
Physical Hazard (Body Injuries)  Hold drill with both steady hands

 making sure that the work area is organized and


cleaned after work is completed
9 Housekeeping/clean the area Straining, possibility to trip and fall.  ensure that all tools and machineries aren’t left at the
work area.