F..No. J-17060/59/2019DDU-GKY-Part (1)
Government of India
Ministry of Rural Development
Department of Rural Development
(Rural Skills Division)
NDCC II Building, 7" Floor
Jai Singh Road, New Delhi- 110001
Dated: 17" Feb 2020
Cor m
Subject: Fund Release Conditions for Project Implementing
Agencies under DDU-GKY.
This is with reference to Notification No: 19/2019 dated 21% Oct 2019 of Rural
Skill Division on the subject mentioned above and to say that condition 2 of the
said notification be replaced with following words:
“If the PIA has got only first Installment and submitted relevant necessary
documents for the release of second Installment to SRLM/Nodal Agency
implementing DDU-GKY in the State/UT till the date of Notification (21st Oct 2019)
and those are found correct then all the remaining Installments to the PIA may be
released on the basis of Section 5.9, Table 6 of DDU-GKY Guidelines of 2016.
Further, States/UTs need to finalize and dispose all such cases within 2 months:
from the date of issue of this corrigendum".
All other terms and conditions of the said notification will remain as such.
6 [
Under Secretary to Govt. of India
This issues with the approval of the competent authority.
To
1. Director General, NIRD&PR, Hyderabad.
MD, NABCONS, Rajendra Place, New Delhi.
3. The Additional Chief Secretaries/ Principal Secretaries/ Commissioner &
Secretaries of the Nodal Departments of the States implementing DDU GKY
Copy to
1. CEOs/MDs of SRLMs/ SSDMs in States
PPS to Secretary (RD)
PPS to AS (RD)
PPS to JS (Skills)
Director (Skills)
Director (M& E), NIRDPR
All officials in DDU GKY, ICT- PMU team for uploading the notification &
necessary changes on DDU GKY Website489444(4)/2019/Strategic Project
F. No. J-17060/59/2019DDU-GKY-Part (1)
Government of Indi
Ministry of Rural Development
Department of Rural Development
(Rural Skills Division)
NDCC II Building, 7 Floor
Jai Singh Road, New Delhi- 110001
Dated: 21 Oct. 2019
Not nN
at _/2019
Subject; Fund Release Conditions for Project Implementing Agencies under
DDU-GRY.
| am directed to refer the section 5.9, table 6 defined in DDU-GKY program guidelines regarding
Payments and Release conditions to Project Implementing Agencies (PIAs). As directed by
Cabinet Secretary to increase the percentage of last instalment release system in Project mode of
DDU-GKY under Skill India Mission, Rural Skills Division of MoRD has accordingly revised the
release conditions for Project Implementing Agencies by SRLMs
Tnstaiment] % of Milestone
Installment
ist 25% of the On signing of MoU and identification of Training Centres
project cost
2nd 2% ofthe [On
project cost | a. Spending 60% of fund disbursed as 1* instalment as visible
in Website
b, Achieving 20% of training target completion and assessment
and with 7% verified placement
c. Submitting Audited expenditure statement like P&L
statement, balance sheet ete. with respect of previous year for
cases after 30" September.
ofthe project | a. Spending 90% of funds disbursed as 1* and 2installments
cost as visible in website
b. Achieving 60% of training targets completion and
assessment and with 25% verified placement
cc. Submitting Audited expenditure statement like P&L
statement, balance sheet ete. with respect of previous year for
ceases after 30° September
2425
489444(4)/2019/Strategic Project
~ ath 25% — JOn
ofthe project |. Achieving 100% of training targets completion and
cost assessment (inclusive of sub-targets such as for SC/ST,
‘minorities ete.) and with 70% verified placement
b. Submission of Project Closure documents as well as signed
| cheek list.
The project costs is after excluding the Welfare costs.
The above fund release conditions will be applicable to the following from the date of issue of this
notification
1. All the new project sanctioned after the issue of this notification.
2. If the PIA has got only first instalment and the £2 certificate has not been issued by
SRLM/Nodal Agency implementing DDU-GKY in the State, the remaining instalments to
the PIA. will be released on the basis of this notification conditions.
3. PIAS who got E2 certificate and awaiting release of 2nd Instalment, all the remaining
instalments will be released on the basis. of section 5.9, table 6 of guidelines,
4. PLAS who claims third or fourth instalment, funds will be released on the basis of section
5.9, table 6 of guidelines.
ation is being issued with the approval of the competent authority
(Dr. Sandeep Sharma)
Joint Director
To
1. Director General, NIRDPR, Hyderabad.
2. MD, NABCONS, Rajendra Place, New Delhi
3. The Additional Chief Secretaries! Principal Secretaries! Commi
the Nodal Departments of the States implementing DDU GKY
Copy to
CEOs/MDs of SRLMs/ SSDMs in States
PPS to Secretary (RD)
PPS to JS (RC)
PPS to JS (Skills)
Director (M& E), NIRDPR
All officials in DDU GKYICT- PMU team for uploading the notification & necessary
changes on DDU GRY Website.