Use a Corrective Action Plan after a Failed

Inspection
January 6, 2022

So, the inspector sent you their report, and you see quality issue(s) that you cannot accept in
some of your products. It’s classified as a failed inspection, and you tell the supplier about the
issues. This is where a corrective action plan will be helpful to find and eliminate the cause/s of
the issues…

Quality issues have been found. What next..?


You want this batch to be fixed, now (that’s a “correction”). And you also want to make sure those
same problems are not likely to come back in the future (and that requires “corrective actions”).

Now, what are the next steps?

In a previous article about dealing with quality problems, I described the appropriate steps as
follows – you’ll see quoted sections from that post below and some of my recent thoughts on the
points:

P.S. If you want to learn about corrective action plans, go straight to step 5.

1. Understand the nature of the quality issues


[Note 5 Jan. 2022] First, it may not be an issue. It may come from an error in the way to
measure/test/evaluate the products. Double-check that point before you project any
negative feelings…
Hopefully, you got many photos and descriptions of the problems. Maybe these “problems” are
actually acceptable. If not, you need to wonder:

 Is it widespread nonconformities? For example, the whole batch is made in the wrong grade
of steel and won’t perform as expected when put to use. If that’s really unacceptable for
you, you might have to cancel the order and forget about your advance payment.
 Or is it a high degree of inconsistency? For example, a batch of wallets is fine except for
30% of the embroideries that were sewn in a slant manner. This is much easier to solve
— about 70% of what was already produced is acceptable, and rework is possible on the
remaining quantity. Even in cases where rework is not realistic (e.g. dents on metal parts),
the whole batch is not written off.

Explain patiently what the problem is to the supplier. If that was already done but the results were
not satisfactory, and if you have no obvious reason to suspect your supplier of dishonest
behavior, you have to assume it is due to a communication problem.

In many cases we had to send someone in the factory to explain what their customer really wants.
If you can do this yourself, this is great. But try to document it and get it approved in writing by
the supplier — that’s how you can push them to rectify their mistakes later in the process
(provided they are honest).

2. Ask your supplier for information and for an action plan


I drew a simple flow chart a few years ago and it is applicable in most situations. But you should
involve your supplier in the decision for better results.

What do they think? Let’s say 30% of production is defective: can it all be reworked? Even the
worst defective pieces? Can they rework 3 pieces and show you photos of before, during, and
after rework?
[Note 5 Jan. 2022] The people repairing the goods may introduce new defects or
weaknesses. If the products need to pass certain tests, it is a must to confirm that the
reworked pieces do also pass that test. And, if it may lead to safety issues, you should
define or approve an instruction on how to conduct the rework and conduct a risk analysis
(that’s a must for medical devices as per ISO 13485, for instance).

Is it realistic to remake a small batch as replacement? How long would it take? (Usually they
refuse this, but on occasion it is negotiable.)

If you you prefer a ‘short shipment’, how long would it take them to sort out the good
pieces? Depending on your deadlines, you might ask them to send the acceptable 70% first — or
to send, say, 20% by air now because you can’t delay certain deliveries to customers.

Will the supplier accept to re-produce some pieces AND send some goods by air at their cost AND
pay for a second inspection? Usually they will resist. At this point, a strong contract that
includes the right terms and was signed & stamped by the supplier will help a lot. If that was
not done before you sent the deposit, it is certainly too late…

(In addition to the reluctance to spend money, there is another common source of resistance: the
fact that you work with an intermediary that has no control over the manufacturer. Your direct
supplier might want to get things right, but the factory just refuses because they don’t know you
and and they have no reason to believe in long-term business. This is quite common.).
3. Ask your supplier to correct the situation
In the worst case, the supplier adopts a “take it or leave it” attitude. Then it comes down to a
business decision and every case is different.

Hopefully your supplier accepts to do something. It doesn’t mean they will really have an impact,
though. From experience, there are mainly two dangers:

1. They do a “quick and dirty job” of sorting the pieces without taking the pain to apply
your quality standard. This is the most common case. Again, poor communication is
the main culprit. This is easy to spot — for example the inspector representing the
buyer found 30% of defective pieces but the factory’s inspectors only found problems
on 5% of the quantity.
2. They pretend to do a sorting & rework job, but they actually wait for the customer to
write “We can’t wait any longer–please ship the goods out.” Obviously the importer is
very frustrated, but in the short term the Chinese side “wins”.

What to do to avoid these issues? We have been applying the following recipe with good success:
– Prepare detailed work instructions (illustrated with clear photos) on what needs to be done. It
means we usually have to go to the factory, or we need a few samples in our office.
– Explain the customer’s standard and the steps to follow to the right people in the factory,
and follow up on what they do. Again, it often means we go to the factory. But sometimes we get
good results with tools like Wechat and Skype, with large exchanges of comments and photos, if
the factory’s salesperson is involved and motivated.
[Note 5 Jan. 2022] If you are confused about the meaning of “correction” vs. “corrective
action”, please see the comparison tables in this article.

4. Re-inspect before shipment


This one seems obvious but is often forgotten. Double-confirm that the original issues were fixed
and that no new issues were created during the factory’s rework.

Real story: an importer paid us to check quality, we found issues, their supplier promised to fix the
situation, the batch was shipped without a re-inspection (we were not consulted), and in the end
we were blamed because there were still issues!!

5. Corrective action plan: address the problem at the root, in


order to prevent a recurrence
What is more frustrating and expensive than a production quality issue?

A repeated production quality issue.

If you don’t want to suffer the same problem over and over, you need to work with the
manufacturer so they implement appropriate action(s) in a corrective action plan.

Here is an approach that can work well (note, there are many ways to set up a corrective action
plan, but some of the steps can’t be skipped…).
Step What to do?
What is the problem, how was it found and with what method, etc.
1. Clarify the Problem
Should more data be collected?
Analyze your findings. Is this due to only 1 problem? Or to several
problems?
2. Break Down the Problem
Use a tree diagram and/or a Pareto chart if appropriate.
What level of improvement do you (and the production staff) think
3. Set a Target
is sufficient and realistic?
Observe the process, the components, the products, etc. carefully.
Ask the people who worked on the process for their opinion.
4. Analyze the Root
What is/are the root cause(s) of the problem?
Cause(s)
Use a fishbone diagram if appropriate. Or use the flow chart that
can be found here.
For each root cause, what should be done to avoid this problem in
5. Think of Corrective the future?
Action(s) Make sure to address causes at the root and to get the opinion
from the production staff.
6. Implement Corrective If the factory agrees, have them apply the corrective action(s).
Action(s) Otherwise, have them promise to do it later at a certain time.
Are corrective action(s) well applied?
7. Monitor Results and
Do they have an impact on processes? Are you finding an
Process
improvement? (Compare to target in step 3.)
If step 7 is positive, is the factory ensuring that the corrective
8. Standardize and
action(s) will always be applied in the future?
Congratulate
If they have done a good job, say thanks to the team who did it.

Now, the problem is, it is often badly misused.

The most common trap is actually to go without a plan, in an unstructured way. It often goes as
follows:

 BUYER: Hello Supplier, please improve your processes so this issue doesn’t come back.
 SUPPLIER: Sure, we also don’t want to suffer this again. We are looking into it.
 SUPPLIER: We found the issue. The incoming QC lady didn’t pay attention to this critical
dimension. We stressed the importance of it. And we will assign a more senior inspector to
follow up on your orders in the future.
 BUYER: OK, thank you. We count on you.

There are a number of issues in this interaction:

1. The issue is not defined. The different parties might have something different in mind (yes,
that often happens!)
2. No root cause is addressed. Why was it an issue in the first place (whether caught or not
caught)? Why did the supplier deliver something wrong?
3. Blaming people for not paying attention is ridiculous. Why were they not paying attention?
Were they trained to know what is important? Were they trained on how to check it? Was
their leader/supervisor paying attention to the way they work? Were they pressed by time,
because of insufficient resources? In the end, it’s a management issue.
4. There is no follow up planned over time, to confirm effectiveness.

That’s why I always suggest that, if a problem is big & costly enough to warrant a strong
complaint, it should be dealt with in a systematic manner.

A very good tool for this, that has gotten quite popular over the past 20 years, is the 8D (or “Eight
Disciplines”). It is a highly structured way of analyzing a quality ‘escape’, defining it, going down to
root cause(s), setting up a corrective action plan, implementing the plan, and following up over
time to confirm the countermeasures are still in place and do have the intended effect.

I shot a video on how we fill out our 8D template you can watch here:

Most manufacturers in China or Vietnam don’t do a great job filling out an 8D report. They need
some hand-holding, and sometimes it is done jointly in a Zoom/Teams/Skype call. It takes some
practice to get it right… but hey, fixing a problem at the root properly does take some experience.

Conclusion
Now, everything I wrote in this article is reactive, after issues have come up and you have been
given a report of a failed inspection.

However, you should aim at spending at least as much time in preventive activities (picking better