RFI Sample

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

Name of Upgradation /Improvement of Rongjeng Mangsang Adokgre (44th to 55th Km) to Ildek a’kong (L=10.

60Km)-
Project : Pkg 02
Name of
Supervision MSV International Inc. & Orion Infra consulting pvt.ltd
Consultant

Name of
M.P.Agarwala Pvt.Ltd. & J C Construction JV
Contractor :

Agreement FWO No. & date : PW/CE/NH/WB/15/2019/68 & dt. 01.12.2020


Date: 03.11.2022 CH: 54+450 (Y-Junction) Time: 06:30 PM
JOINT MEASUREMENTS SHEET

RFI No. PWD/MPA/RMA/ 1952


BOQ Details of Actual measurements Remarks
SL No. Description Side
Item no. Nos L B H QTY

LAYING, FDD AND LEVEL


1 CHECKING FOR WMM TOP RHS 1 50 5.375 0.125 33.59
LAYER
Total= 33.59 CUM

Submitted by Verified by

Contractor Representative Authority's Representative


M.P. Agarwala pvt ltd & J C Construc on JV