DAX - Uso de Datas

You might also like

Download as txt, pdf, or txt
Download as txt, pdf, or txt
You are on page 1of 1

Calculo de datas

BI_Auxiliar_Previsto = FILTER(CROSSJOIN(
//FILTER(SELECTCOLUMNS(TAB_CALENDARIO;"Data";[Date]; "FimDoMes";[FimDoMes]);
[FimDoMes] = TRUE());
SELECTCOLUMNS('TAB_Datas do Gr�fico';"Data";[Data]);
SELECTCOLUMNS(PPM_Tarefas_Complementar;
"ProjectID";[ProjectId];
"TaskID";[TaskId];
"ID";[PPM_Tarefas.TaskIndex];
"DataINI";[TaskBaselineStartDate.1];
"DataFIM";[TaskBaselineFinishDate.1];
"Ativa";[PPM_Tarefas.TaskIsActive]
)
); [Ativa] = TRUE() )

BI_Auxiliar_Conclu�do = FILTER(CROSSJOIN(
SELECTCOLUMNS('TAB_Datas do Gr�fico';"Data";[Data]);
SELECTCOLUMNS(PPM_Tarefas_Complementar;
"ProjectID";[ProjectId];
"TaskID";[TaskId];
"ID";[PPM_Tarefas.TaskIndex];
"DataINI";IF(ISBLANK([PPM_Tarefas.TaskActualStartDate.1]);
[PPM_Tarefas.TaskStartDate.1];[PPM_Tarefas.TaskActualStartDate.1]);
"DataFIM";IF(ISBLANK([PPM_Tarefas.TaskActualFinishDate.1]);
[PPM_Tarefas.TaskFinishDate.1];[PPM_Tarefas.TaskActualFinishDate.1]);
"%Conclu�do";[PPM_Tarefas.TaskPercentCompleted]/100;
"Dura��o";[PPM_Tarefas.TaskDuration];
"Dura��oReal";[PPM_Tarefas.TaskActualDuration];
"Restante";[PPM_Tarefas.TaskRemainingDuration];
"Ativa";PPM_Tarefas_Complementar[PPM_Tarefas.TaskIsActive]
)
); [Ativa] = TRUE() )