LINK 4 Chegg

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 6

Answer :-

1)

Given data,

Drag Line size = 1.53 m3

swing angle = 120°

Average depth of cut = 2.4 m

Material = Common earth

job efficiency = 50 min/h

Swell percent = 25%

From table 3.7 , for drag line size 1.53 m3

Ideal output = 176 BCM/h

From table 3-8, for 1.53 m3

Optimum depth of cut = 3.0 m

Actual depth/Optimum depth = 2.4/3.0 = 0.8 = 80%

From table 3-9, swing depth factor = 0.9

Efficiency factor = 50/60 = 0.833

Volume change factor = 1+ 25% = 1 + 0.25 = 1.25 Estimated production =


176 × 0.9 × 0.833 × 1.25

= 164.934 = 165 LCM/h


2) Given data,

Drag line size = 1.53 m3

Swing angle = 70°

Average depth of cut = 2.7 m

job efficiency = 50 min/h

common earth

From table 3.7, for drag line size 1.53 m3

Ideal output = 176 BCM/h

From table 3-8, for 1.53 m3

Optimum depth of cut = 3.0 m

Actual depth/Optimum depth = 2.7/3.0 = 0.9 = 90%

from table 3-9,


for swing angle 70°, the swing depth factor = 1.063
Efficiency factor = 50/60 = 0.833

Swell percent for common earth = 25%

Volume change factor = 1 + 25% = 1 + 0.25 = 1.25

Estimated production = 176 × 1.063 × 0.833 × 1.25

= 194.80 = 195 LCM/h