CAP - Drying Plant L2 Schedule - r1 - 05292023
CAP - Drying Plant L2 Schedule - r1 - 05292023
CAP - Drying Plant L2 Schedule - r1 - 05292023
Central Axis Program 2025 38 22-Nov-22 A 03-Jun-26 28-Jul-26 2 03-Jun-26, Central Axis Program 2025
Actual Level of Effort Critical Remaining Work summary Date Revision Checked Approved
Page 1 of 2
29-May-23 Issued for May 2023 Month End
Actual Work Near critical
Remaining Work Milestone
01 JESA EPPM Classic Schedule Layout
Central Axis Program 2025
Drying Plant L2 Schedule
Activity ID Activity Name Orig Dur Start Finish BL1 Finish Var - BL1 2023 2024 2025 2026 2027
Finish Date
M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S
DRY1240 SMP Contractor - ITB to Contract Sign 3 17-Apr-24 16-Jul-24 16-Jul-24 0 SMP Contractor - ITB to Contract Sign
Electrical Contractor Bidding Cycle 3 17-Apr-24 16-Jul-24 16-Jul-24 0 16-Jul-24, Electrical Contractor Bidding Cycle
DRY3960 Electrical Contractor - ITB to Contract Sign 3 17-Apr-24 16-Jul-24 16-Jul-24 0 Electrical Contractor - ITB to Contract Sign
Instrumentation Contractor Bidding Cycle 4 17-May-24 13-Sep-24 13-Sep-24 0 13-Sep-24, Instrumentation Contractor Bidding Cycle
DRY4160 Instrumentation Contractor - ITB to Contract Sign 4 17-May-24 13-Sep-24 13-Sep-24 0 Instrumentation Contractor - ITB to Contract Sign
EPCM Development 22 20-Aug-24 03-Jun-26 28-Jul-26 2 03-Jun-26, EPCM Development
Construction 20 20-Aug-24 14-Apr-26 29-Jun-26 3 14-Apr-26, Construction
APP3610 Civil Construction Drying Plant 7 20-Aug-24 19-Mar-25 02-Jun-25 3 Civil Construction Drying Plant
APP1960 SMP Construction Drying Plant 12 19-Nov-24 14-Nov-25 28-Jan-26 3 SMP Construction Drying Plant
APP3620 Electrical Construction Drying Plant (Susbtation Incl) 12 19-Mar-25 16-Mar-26 28-May-26 3 Electrical Construction Drying Plant (Susbtation Incl)
APP3990 Instrumentation Construction Drying Plant 5 14-Nov-25 14-Apr-26 29-Jun-26 3 Instrumentation Construction Drying Plant
Commissioning 2 14-Apr-26 03-Jun-26 28-Jul-26 2 03-Jun-26, Commissioning
APP4160 Cold Commissioning/Mechanical Completion Drying Plant 1 14-Apr-26 04-May-26 Cold Commissioning/Mechanical Completion Drying Plant
APP1950 Hot Commissioning Drying Plant 1 04-May-26 03-Jun-26 28-Jul-26 2 Hot Commissioning Drying Plant
Actual Level of Effort Critical Remaining Work summary Date Revision Checked Approved
Page 2 of 2
29-May-23 Issued for May 2023 Month End
Actual Work Near critical
Remaining Work Milestone