Earthworks 035 Level Section
Earthworks 035 Level Section
(Five-Level Section)
• ACTIVITY PROBLEM
– The following are section notes of a five-level section
Station 1+ 125
? 12.0 10.0 ?
, ,5.3, ,
6.20 6.0 4.0 8.80
Station 1 + 175
. . . .
SOLUTION:
1. As mentioned in our discussion, always measure the horizontal distances
from the CENTER LINE – then plot the coordinates as shown in the figure.
SOLUTION:
2. After which connect the road edges to the farthest coordinate. (the
coordinates are circled with red)
SOLUTION:
3. Connect the centerline height to the coordinates until you reach the
farthest coordinate as shown. Now that you have your figure you can now
determine the area of the given cross-section.