Laporan Pekerjaan Minggu 5

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 2

OWNER / TASK PROVIDER : JOB PROGRESS REPORT CONTRACTOR :

No. SPP : 002/SPP/MRFH/CT/IX/2023 PROYEK CAFE TANGSEL


BPK. MUHAMMAD REZA FIRDAUS HASIBUAN LOCATION : Jl. Bukit Serua, Cuputat, Tanggerang Selatan
DURASI : 12 Sep 2023 s/d 11 Des 2023 (90 Hari Kalender) Period : 9-Oct-23 s/d 10-Oct-23 Week : 5 Bpk. Budi Yawantara
VALUE PREVIOUS WEEK CURENT WEEK CUMMULATIVE
NO SPESIFIKASI PEKERJAAN VOLUME UNIT (%) VOL PRESTASI VALUE VOL PRESTASI VALUE VOL PRESTASI VALUE REMARKS
A PEKERJAAN PERSIAPAN
1 Pematangan Lahan 407,00 m2 2,90 407,00 100,00 2,90 - - 407,00 100,00 2,90

B Pekerjaan Galian
1 Galian Pondasi 12,00 m3 0,37 12,00 100,00 0,37 - - 12,00 100,00 0,37
2 Galian Sloof 20X40 20,00 m3 0,62 20,00 100,00 0,62 - - 20,00 100,00 0,62
3 Galian Pond 52,50 m3 1,62 52,50 100,00 1,62 - - 52,50 100,00 1,62

C Pekerjaan Bekisting
Lantai Ground
1 Bekisting Pondasi 24,00 m2 1,05 24,00 100,00 1,05 - - 24,00 100,00 1,05
2 Bekisting Sloof 57,60 m2 2,53 57,60 100,00 2,53 - - 57,60 100,00 2,53
3 Bekisting Pedestal 28,80 m2 1,26 28,80 100,00 1,26 - - 28,80 100,00 1,26

D Pekerjaan Baja
Lantai Ground
1 Kolom double UNP100 827,20 kg 4,71 827,20 100,00 4,71 - - 827,20 100,00 4,71
2 Baseplate & Stifner 208,75 kg 1,19 208,75 100,00 1,19 - - 208,75 100,00 1,19
3 Baut m10 HTB 120,00 pcs 0,50 120,00 100,00 0,50 - - 120,00 100,00 0,50
4 Cat Zinchromate 1155,95 kg 0,41 1.155,95 100,00 0,41 - - 1.155,95 100,00 0,41

Lantai 2
1 Kolom double UNP100 827,20 kg 4,71 827,20 100,00 4,71 - - 827,20 100,00 4,71
2 Balok UNP100 1353,60 kg 7,71 1.353,60 100,00 7,71 - - 1.353,60 100,00 7,71
3 Footplate & Stifner 439,60 kg 2,50 439,60 100,00 2,50 - - 439,60 100,00 2,50
4 Baut m10 HTB 336,00 pcs 1,40 336,00 100,00 1,40 - - 336,00 100,00 1,40
5 Cat Zinchromate 2180,80 kg 0,78 2.180,80 100,00 0,78 - - 2.180,80 100,00 0,78
6 Chequerplate 3mm + rangka siku 4cm 52,00 m2 6,17 52,00 100,00 6,17 - - 52,00 100,00 6,17

E Pekerjaan Pembesian
LANTAI GROUND
1 Pembesian Foot/pondasi 462,10 kg 1,81 462,10 100,00 1,81 - - 462,10 100,00 1,81
2 Pembesian Sloof 869,94 kg 3,41 869,94 100,00 3,41 - - 869,94 100,00 3,41
3 Pembesian Pedestal Kolom 275,06 kg 1,08 275,06 100,00 1,08 - - 275,06 100,00 1,08
4 Pembesian Lantai 522,00 kg 2,04 522,00 100,00 2,04 - - 522,00 100,00 2,04

F Pekerjaan Pengecoran Beton Mutu K-250


LANTAI GROUND
1 Pengecoran Foot/pondasi 18,00 m3 0,45 18,00 100,00 0,45 - - 18,00 100,00 0,45
2 Pengecoran Sloof 14,00 m3 0,35 14,00 100,00 0,35 - - 14,00 100,00 0,35
3 Plat Lantai 9,60 m3 0,24 9,60 100,00 0,24 - - 9,60 100,00 0,24

G Pekerjaan Dinding
Lantai Ground
1 Pasangan Dinding Spandek warna 0,35 mm 88,00 m2 4,07 - - - - - - - -
2 Furnish Bar 30,00 m2 3,20 - - - - - - - -
3 Window wall kaca biasa 6mm 46,00 m2 9,28 - - - - - - - -
frame kusen aluminium 3 inch ex. Inkalum

Page 1 of 2
OWNER / TASK PROVIDER : JOB PROGRESS REPORT CONTRACTOR :
No. SPP : 002/SPP/MRFH/CT/IX/2023 PROYEK CAFE TANGSEL
BPK. MUHAMMAD REZA FIRDAUS HASIBUAN LOCATION : Jl. Bukit Serua, Cuputat, Tanggerang Selatan
DURASI : 12 Sep 2023 s/d 11 Des 2023 (90 Hari Kalender) Period : 9-Oct-23 s/d 10-Oct-23 Week : 5 Bpk. Budi Yawantara
VALUE PREVIOUS WEEK CURENT WEEK CUMMULATIVE
NO SPESIFIKASI PEKERJAAN VOLUME UNIT (%) VOL PRESTASI VALUE VOL PRESTASI VALUE VOL PRESTASI VALUE REMARKS

Lantai 2
Railing Hollow 40mmx40mm 28,00 m' 2,49 - - - - - - - -

H Pekerjaan Lantai
Lantai Ground
1 Screed lantai 2cm 50,00 m2 1,01 - - - - - - - -
Lantai 2
1 Screed lantai 2cm 50,00 m2 1,01 - - - - - - - -

J Pekerjaan Pintu & Jendela


1 Pekerjaan Pintu & Jendela toilet 1,00 ls 1,19 - - - - - - - -

K Pekerjaan Plumbing
1 Instalasi Air kotor 1,00 Ls 0,59 0,50 50,00 0,30 - - 0,50 50,00 0,30
2 Instalasi Air Bersih 1,00 Ls 0,83 0,50 50,00 0,42 - - 0,50 50,00 0,42
3 Instalasi Air Hujan 1,00 Ls 0,59 0,50 50,00 0,30 - - 0,50 50,00 0,30
4 Instalasi Area Pond & Pompa 1,00 Ls 2,37 0,50 50,00 1,19 - - 0,50 50,00 1,19

L Pekerjaan Electrical & AC


1 Pengadaan & Instalasi Kabel Power 1,00 Ls 1,90 - - - - - - - -
2 Stop Kontak & saklar 1,00 Ls 0,83 - - - - - - - -
3 Pengadaan & Instalasi AC 1,00 Ls 3,56 - - - - - - - -

M Pekerjaan Pengadaan & Instalasi Lighting


1 Pengadaan & Instalasi Lighting 1,00 Ls 2,37 - - - - - - - -

M Pekerjaan Landscape
1 Pohon Dan Jasa Tanam 1,00 Ls 2,37 0,20 20,00 0,47 - - 0,20 20,00 0,47

N Pekerjaan Atap
1 Rangka atap baja ringan 0,75mm 90,00 m2 2,35 45,00 50,00 1,18 45,00 50,00 1,18 90,00 100,00 2,35
2 Atap zincalume 0,45 90,00 m2 3,74 - - - 90,00 100,00 3,74 90,00 100,00 3,74

P Pekerjaan Tribun / kolam depan


1 Bangku keliling Tribun 6,00 m3 2,85 6,00 100,00 2,85 - - 6,00 100,00 2,85

Q Pekerjaan Paving block


1 Paving block termasuk abu batu t = 6 cm 100,00 m2 3,56 100,00 100,00 3,56 - - 100,00 100,00 3,56

TOTAL ACTUAL 100,00 60,07 4,91 64,98


TOTAL PLAN 43,57
DEVIATION 21,41

Karawang, 10 Oktober 2023


Witnessed By, Proposed By,

(…............................) (Budi Yawantara)


…............................ Project Manager

Page 2 of 2