Professional Documents
Culture Documents
Abstract WasteEng - Llano 2022
Abstract WasteEng - Llano 2022
Three models were developed in Aspen Plus v10 software: (1) ethanolic fermentation
after acid hydrolysis of algae carbohydrates was simulated to produce ethanol; (2)
butanol was produced by carbohydrates hydrolysis and fermentation using
acetobutylicum microorganisms; (3) biogas production through anaerobic digestion of
green algae residues was also simulated. These models operate at the same inlet
conditions to compare the same size plant. Plants were fed using 50,000 kg/h of Ulva
rigida feedstock. Once the simulations were run, economic analysis was conducted using
the Aspen Process Economy Analyzer (APEA) tool. Thus, capital costs, operating costs,
utilities, equipment, and installed costs were analyzed.
5. Results and discussion
The simulated plants include not only carbohydrates hydrolysis and fermentation or
anaerobic digestion but also purification step trough distillation in the acetone-butanol-
ethanol (ABE), distillation coupled with molecular sieves in the ethanol plant and
cryogenic distillation in the biogas plant. This step is necessary to get a final high-quality
product that permits to be used as a fuel without any other treatment. ABE plant
produces 2,666 kg/h of butanol (purity of 99.8 %); 678 kg/h of acetone, and 41 kg/h of
ethanol; the ethanol plant produces 8217 kg/h with a purity of 99.5 %. Finally, the biogas
plant produces 6,413 kg/h of biogas from which 410 kg/h is methane (purity of 95.8 %)
and 156 kg/h is H2 (purity of 99.9 %)
Next, in Figure 1 results of the APEA analysis are shown for the three simulated plants.
In all cases the highest costs are in descending order operating costs, followed by utilities
and capital costs. Among them these costs category represented between 76.3 and 85.6
% of the total costs. The most economic ulva-based biorefinery is the ABE plant with a
total cost of 74.4 M€, followed by the biogas plant (81.6 M€), and finally the ethanol
plant (115 M€).
Cost analysis
3.5E+07
3.0E+07
2.5E+07
2.0E+07
1.5E+07
1.0E+07
5.0E+06
0.0E+00
Capital costs Operating Utilities cots Equipment Installed costs Raw material
(€) costs (€/year) (€/year) costs (€) (€) costs (€/year)