From the overall observations, the building sounds good and minor distress is
observed at some locations, due to age of the building as well as presence of water or
moisture. The renovation works are underway at Third and Fourth Floors. This
includes, minor repair works, toilet renovation and interior works. Many of the
suggestions made in our previous stability report issued dated 15.06.2020. Some of
the new distresses are identified along with our previous comments and are discussed.
Presently, third and fourth floor renovation works are ongoing. At fourth floor roof,
at some locations corrosion of reinforcement is observed and the spalling of cover
concrete is also observed (Fig.1). At these location NDT tests are conducted and it is
found that the strength of concrete is good (Fig.2). This may be due to the provision of
less or no cover provided for slab reinforcements. Also, there may be some leakages
from terrace. This has to be identified and rectified. A proper treatment procedure shall
be carried out to fix this issue.
A very critical issue is also observed at the sunshade projection at top level. The
reinforcement got corroded in slab and beam (Fig.5). Part of cover concrete is also
spalled at some location. This may be due to water stagnation at top of the slab
projection and the damages observed at top surface finishes (Fig.6). This has to be
corrected such that no water stagnates over the slab projection. In addition to that a
proper retrofitting shall be carried out in the damaged slab and beam. Part of plastering
spalled at some location (Fig.7). This may be due to poor bonding of plaster with the
slab. All such loose plater has to be removed and re plastered properly with proper
hacking at the RCC surface.
Fig.(9) Dampness in walls and RCC column in DNox and EAX Lab
Non-Destructive Test - Office block 1 (cob 101):
Since, the age of the building is more than 10 years, it is decided to check the
strength of the concrete elements. Since, the renovations are underway at Third and
Fourth Floors, the structural elements such as columns, beams and slabs (Fig.10)
were exposed and tested for its compressive strength. A detailed methodology and
report are enclosed in Annexure II.
This is relatively new block constructed during 2015 and not much distress is
observed and the building is found to be sound at present. From the overall
observations, minor distress is observed at some locations, due to age of the building
as well as presence of water or moisture.
The settlement and wall cracks are identified in HT panel room and is reported
already. This has been addressed partly. The cracks are developed at the same
locations due to settlement of huge wall (Fig.11). The main door also got settled and
presently unable to close fully (Fig.12). At some locations flooring also got settled and
cracks are identified (Fig.13). This room has a wall of height 5.5m, which developed
cracks and showing settlement. This may be due to the height of the wall with no
intermediate ties, as well as no foundation.
At the main entrance (Western side) canopy area, dampness is observed. This may be
due to water leakage through the drain pipe connection at the slab level. This has to be
rectified (Fig.15).
At terrace, damages in weathering course are also observed (Fig.20). This has to
be properly finished. Else, this will further damage in due course and allow water to
seep in, results in damages to the roof slab and beam.
In canteen block Terrace floor level beam got corroded at some locations on
eastern side and bulging of concrete is seen (Fig.21). The water stagnation at this
location to be checked and rectified. At terrace floor, water stagnation is observed. The
solar water heater provided is leaking and this becomes the perennial source of water.
This has to be arrested. The weathering course floor finish also got damaged at some
locations and need to be rectified (Fig.22).
Service blocks consist of genset rooms, Steel Chimney and chiller plant above.
The chimney platform got corroded and damaged (Fig.23). This has to be replaced.
The supporting angle structure found to be in good condition. However, while removing
the platform plate, this has to be checked and to be finalized. The chimney wall
thickness may be checked once in five years and the stability may be ascertained. At
some locations in chimney wall connections, bolts are missing (Fig.24). This has to be
provided.
Fig. (23) corrosion and damages in chimney platform and chimney wall
Fig. (24) Missing bolts in connection
At terrace floor water stagnation and dampness at the wall is observed. This is
due to improper position of drain pipe (Fig.25). This need to be rectified.
The walls in the genset room shows cracks at some locations. This may be due
to minor settlement of floor or plinth beam (Fig.26). It is found to be non-structural and
requires some more time to observe. Presently it is in safe condition.
This consists of two numbers of fire sump with a fire pump room located below
ground level. At present this room is found to be in good condition. But there is a water
leakage is observed from the fire sump (Fig.27) and this has to be arrested
immediately.