ENVIRONMENTAL, HEALTH AND SAFETY RISK ASSESSMENT

DEPARTMENT / PROCESS: REINSTATEMENT WORKS FOR HACKING & DISPOSAL APPROVED BY: VEERA RAGHAVAN REVIEWED BY: VEERA RAGHAVAN

COMPANY: VR HACKERS & REINSTATEMENT PTE LTD OPERATION MANAGER OPERATION MANAGER

WORK SITE: Orchard Towrs, 400, Orchard Unit, #18-02, Singapore 238875 SIGNATURE / DATE: SIGNATURE / DATE:

ORIGINAL ASSESSMENT DATE: 24-05-2023 ; LAST REVIEW DATE: 24-05-2023 ; NEXT REVIEW DATE: 24-05-2024

1. Hazards and Risk Identifications 2. Risk Evaluations and Controls


S/n. Main Activity Sub Activities EHS Hazards / EHS Impact Initial Risk Existing Control Measures Residual Risk Additional Risk Control Person-In-Charge
Aspects (PIC)
L S R L S R

1. Two man method handling / 25kg max. 2.


1. Brief workers on manual handling method. KARUPPAIYAN
Never Bend, Lift, and Twist at the same time.
Loading & Unloading of Transportation of materials by manual Back injury during 2. All appropriate PPE must be worn. SUDHAHAR
1 Physical injuries. 3 3 9 3. Use mechanical aids whenever possible. 2 2 4
materials. lifting. manual lifting. 3. Plan the Lift ( SAFETY
4. Bend your knees and use your legs to lift. SUPERVISOR )
4. Close Supervising.

1. Make sure materials are not stacked up too high. 1.Brief workers & check daily. KARUPPAIYAN
Stacking of materials. Falling of materials. Physical injuries. 2 3 6 2. Make sure no materials are stored & placed at open side or edge of 2 2 4 2. Make sure all storage/material is in order SUDHAHAR
( SAFETY
building . 3. Plan deliveries to keep the material.
SUPERVISOR )
2 Storage of Material.
KARUPPAIYAN
1. Materials must be stored above 300mm ground level. SUDHAHAR
Mosquito breeding 1. To carry out daily inspection.
Materials storage area Dengue Fever. 3 4 12 2. Remove stagnant water immediately after rainy day or spray malaria 2 3 6 ( SAFETY
due to stagnant water. 2. Maintain good house-keeping.
oil. SUPERVISOR )

1. Make sure all opening are well covered.


2. Work area shall be well barricaded with signage displayed.
3. Do not work too (Less than 2 metre) closed at open side or edge of
building when using tools. 1. Supervisor to inspect the work area before work
4. Always comply with buddy system when using tools. commence. 2.
5. Hacking & Floor screeding tools must be in good working Workers must wear all PPE items.
4 Hacking & floor screeding AZHAGAPPA
Hacking Works. Physical injuries / condition & inspected. 3. Provide proper storage place. 5. N RAMESH
3 Physical Injuries. 3 4 12 6. Workers to use their safety belt / harness if working more than 2m 3 3 9 4.Apply Permit to hoist from Main contractor.
Fatal Accident. (SAFETY
height. 5. Conduct Training during Tool Box meeting. SUPERVISOR )
7. Always comply with fall protection plan when working at height. 6. Close Supervision
8. Only use proper & safe working platform & access.
10. To carry out daily check of Safety Harness.

1 of 3
ENVIRONMENTAL, HEALTH AND SAFETY RISK ASSESSMENT
DEPARTMENT / PROCESS: REINSTATEMENT WORKS FOR HACKING & DISPOSAL APPROVED BY: VEERA RAGHAVAN REVIEWED BY: VEERA RAGHAVAN

COMPANY: VR HACKERS & REINSTATEMENT PTE LTD OPERATION MANAGER OPERATION MANAGER

WORK SITE: Orchard Towrs, 400, Orchard Unit, #18-02, Singapore 238875 SIGNATURE / DATE: SIGNATURE / DATE:

ORIGINAL ASSESSMENT DATE: 24-05-2023 ; LAST REVIEW DATE: 24-05-2023 ; NEXT REVIEW DATE: 24-05-2024

1. Hazards and Risk Identifications 2. Risk Evaluations and Controls


S/n. Main Activity Sub Activities EHS Hazards / EHS Impact Initial Risk Existing Control Measures Residual Risk Additional Risk Control Person-In-Charge
Aspects (PIC)
L S R L S R

KARUPPAIYAN
no one entering work Serious injury / 1. Make sure workers use their safety harness. SUDHAHAR
Use of hacking equipments 3 4 12 2.Site to be securely fence off and locked at end of working day. 3 3 9 Refer RA. 3.1
site Fatal Accident. ( SAFETY
SUPERVISOR )

Hacking 1. Make sure workers use their safety harness for hacking &
4
screeding.
2. Secure all loose materials & hand tools properly.
3. Restrainer always anchored.
KARUPPAIYAN
Serious injury / 4. Services to be disconnected and confirmed as disconnected by SUDHAHAR
Explosion/Fire/Shock. 4 4 16 license persons only. 3 3 9 Refer RA. 4.13 & 4.14
Fatal Accident. ( SAFETY
5. Maintain good house at all times. SUPERVISOR )

Floor Screeding Use of screeding equipments 1. Workers must use safety shoe. 1. Conduct proper Training on the method of using KARUPPAIYAN
Injury to Make sure hammer is in good condition. tools. SUDHAHAR
5 Slips/Trips. persons. 2 3 6 2 2 4
wear handguard to prevent injured the hand. 2. CheckEquipment Before use ( SAFETY
Wear Proper PPE to prevent falling from floor. 3. Practise a good housekeeping. SUPERVISOR )

AZHAGAPPA
Using of equipments Injury to persons 1. Ensure use of PPE: safety gloves. Brief workers on correct method of using tools N RAMESH (
Hand injury. 3 3 9 2 2 4
2. To provide more man SAFETY
SUPERVISOR )
AZHAGAPPA
Body injuries / N RAMESH
Disruption of services. 3 3 9 1. Conduct pre-survey & check of tools condition. 2 3 6 Comply with proper practice.
Property damage. SAFETY
SUPERVISOR )
KARUPPAIYAN
Machine damage 1. Provide relevant tools to use. SUDHAHAR
General site hazards Floor damage. 3 3 9 2 2 4 Conduct briefing on daily toolbox meeting.
6 including dust,cuts etc, due vibrate. ( SAFETY
SUPERVISOR )
KARUPPAIYAN
Hand & Foot 1. Ensure proper PPE & tools use.
Body parts struck 3 3 9 2 3 6 Use correct position method. SUDHAHAR
injury. 2. Proper communication method during hacking & ( SAFETY
secreeding. SUPERVISOR )
AZHAGAPPA
Hand & Foot N RAMESH (
Disposal of debris 2 3 6 1. Remove all disposal debris from site. 2 2 6 Maintain good house keeping.
injury. SAFETY
SUPERVISOR )

2 of 3
ENVIRONMENTAL, HEALTH AND SAFETY RISK ASSESSMENT
DEPARTMENT / PROCESS: REINSTATEMENT WORKS FOR HACKING & DISPOSAL APPROVED BY: VEERA RAGHAVAN REVIEWED BY: VEERA RAGHAVAN

COMPANY: VR HACKERS & REINSTATEMENT PTE LTD OPERATION MANAGER OPERATION MANAGER

WORK SITE: Orchard Towrs, 400, Orchard Unit, #18-02, Singapore 238875 SIGNATURE / DATE: SIGNATURE / DATE:

ORIGINAL ASSESSMENT DATE: 24-05-2023 ; LAST REVIEW DATE: 24-05-2023 ; NEXT REVIEW DATE: 24-05-2024

1. Hazards and Risk Identifications 2. Risk Evaluations and Controls


S/n. Main Activity Sub Activities EHS Hazards / EHS Impact Initial Risk Existing Control Measures Residual Risk Additional Risk Control Person-In-Charge
Aspects (PIC)
L S R L S R

1. Manual Handling training. KARUPPAIYAN


Persons Injury Management to arrange training. SUDHAHAR
7 Manual Handling Manually All items to be 3 4 9 3 3 9
( SAFETY
check before manual SUPERVISOR )
handling.
Explosion due to
improper connection & KARUPPAIYAN
Persons Injuru Only trained,qualified & competent person with SUDHAHAR
short in contact. 4 4 8 1. Check & Test all equipment before use. 2 3 6
certificate to do. ( SAFETY
SUPERVISOR )

1. Checked with workers when conducting morning daily toolbox AZHAGAPPA


Heatstress – Exposed to Heat stress / Worker Serious injury / meeting on their health. Make sure informed your supervisor immediately & N RAMESH (
8 3 3 9 2 2 4
hot weather collapse due to unwell. Fatal Accident. 2. Drink a lot of water when you are thirsty. consult doctor if you are not well. SAFETY
3. Do not work @ height if you are not feeling well. SUPERVISOR )

1. Using of banksman at all times AZHAGAPPA


Pedestrians users Persons Only trained,qualified & competent person with N RAMESH (
9 Injury Persons affected by 1 2 3 2 .warning signs and where required physical barries. 1 2 2
during clear the certificate. SAFETY
debris to move lorry. dust. SUPERVISOR )

AZHAGAPPA
Falling Masonry/ Body injuries / Only trained,qualified & competent person with N RAMESH (
10 Site operatives 1 3 3 Use of personnel protective at all items. 1 2 2
uncontrol collapse. Property damage. certificate to do the testing. SAFETY
SUPERVISOR )

Likelihood (L) Severity (S) Index Risk Rating (R) Rating Required Action
No Action Required at
1 <Improbable> - Extremely unlikely to occur but still possible. 1 <Minor> - Not likely to cause injury. 1–2 Negligible
all
2 <Appreciable> - Injury required first-aid Manage by routine
2 <Remote> - Unlikely to occur under normal circumstances. 3–4 Low
treatment. procedures
Management
3 <Moderate> - Injury required medical
3 <Occasional> - Could possibly or known to occur 5–9 Medium Responsibility must be
treatment.
specified
4 <Major> - Serious injuries or life-
4 <Probable> - Likely to occur more than once 10 – 15 High Find Alternative Method
threatening.
5 <Catastrophic> - Fatality or multiple Not Acceptable / Stop
5 <Frequent> - Common or repeating occurrences 16 - 25 Very High
major injuries. Work

3 of 3