Professional Documents
Culture Documents
NNGP Anx3 BQ 7000
NNGP Anx3 BQ 7000
7 1 3 0 (Not Applicable) -
7 1 4 0 (Not Applicable) -
7 1 5 0 Cable Way
7 1 5 1 Duct / Tray
7 1 5 1 A Duct
7 1 5 1 A a W=300mm M
7 1 5 1 A b W=600mm M
7 1 5 1 A c W=900mm M
7 1 5 1 A d W=1200mm M
7 1 5 1 B Duct Cover
7 1 5 1 B a W=300mm M
7 1 5 1 B b W=600mm M
7 1 5 1 B c W=900mm M
7 1 5 1 B d W=1200mm M
7 1 5 1 C Ladder Tray
7 1 5 1 C a W=300mm M As per Electrical Room Layout
7 1 5 1 C b W=600mm M 66 303.60 150.75 45,767.70 - - 52,920.71 59,026.63 157,715.05 2,389.62
7 1 5 1 C c W=900mm M
7 1 5 1 C d W=1200mm M
7 1 5 1 D Ladder Tray Cover
7 1 5 1 D a W=300mm M
7 1 5 1 D b W=600mm M
7 1 5 1 D c W=900mm M
7 1 5 1 D d W=1200mm M
7 1 5 1 E Perforated Tray
7 1 5 1 E a W=50mm M
7 1 5 1 E b W=150mm M
7 1 5 1 E c W=300mm M
7 1 5 1 E d W=600mm M
7 1 5 1 F Perforated Tray Cover
7 1 5 1 F a W=50mm M
7 1 5 1 F b W=150mm M
7 1 5 1 F c W=300mm M
7 1 5 1 F d W=600mm M
7 1 5 2 Conduit Pipe
7 1 5 2 A 2 inch PVC M
7 1 5 2 B 4 inch PVC M
7 1 5 2 C 2 inch C.S. M
7 1 5 2 D 4 inch C.S. M
7 1 6 0 Cable
7 1 6 1 Plug-in Type Prefabricated System Cable and Coaxial Cable Pcs As per Control System Architecture
7 1 6 2 Hard-wired Instrument Signal and Power Cable
7 1 6 2 A 2-9 Cores Pcs 16 28.80 150.75 4,341.60 - - 5,020.15 5,599.36 14,961.11 935.07 As per Control System Architecture
7 3 2 0 Local Panel and Enclosure Pnl 1 8.00 150.75 1,206.00 - - 1,394.49 1,555.38 4,155.86 4,155.86 For Potable water System
7 5 0 0 Analyzer Installation
7 5 1 0 Pedestal Mount Type Pcs 4 36.40 150.75 5,487.30 - - 6,344.91 7,076.97 18,909.18 4,727.30 For pH Analyzer
QUANTITY LABOR MATERIAL EQUIPMENT OTHERS TOTAL COST BQ UNIT COST
UNIT REMARKS
FWBS DESCRIPTION (Adjusted) MANHOURS Php/MH Cost Php/BQ COST COST COST (12) Php/BQ
(1) (2) (3) (5) (6) (7) = (5)x(6) (8) (9)=(4)x(8) (10) (11) =(7+9+10+11) (13)=(12)/(4) (14)
7 8 2 1 C Conduit Piping M
7 8 2 2 Branch Cabling
7 8 2 2 A Armored Metal Cable (up to 30m) Pcs As per Instrument List, Addendum1
A1 Armored Metal cable (Up to 6m or for sensor cable) Pcs As per Instrument List
7 8 2 2 B Non-armored Metal Cable (up to 30M) Pcs 214 1,455.20 142.01 206,652.95 - - 253,656.86 282,923.44 743,233.26 3,473.05
B1 Non- armored Metal cable (Up to 6m or for sensor cable) Pcs 24 108.72 142.01 15,439.33 - - 18,951.05 21,137.60 55,527.98 2,313.67
7 8 2 2 C Armored Optical Fiber Cable Pcs
7 8 3 0 Junction Box
7 8 3 0 A 48 terminals or less Pcs 35 350.00 142.01 49,703.50 - - 61,008.73 68,047.83 178,760.06 5,107.43 Excluding Shield Terminal, Addendum1
7 8 3 0 B 49 to 80 terminals Pcs 7 84.00 142.01 11,928.84 - - 14,642.09 16,331.48 42,902.41 6,128.92 Excluding Shield Terminal
7 8 3 0 C 81 terminals over Pcs Excluding Shield Terminal
QUANTITY LABOR MATERIAL EQUIPMENT OTHERS TOTAL COST BQ UNIT COST
UNIT REMARKS
FWBS DESCRIPTION (Adjusted) MANHOURS Php/MH Cost Php/BQ COST COST COST (12) Php/BQ
(1) (2) (3) (5) (6) (7) = (5)x(6) (8) (9)=(4)x(8) (10) (11) =(7+9+10+11) (13)=(12)/(4) (14)
7 8 5 1 Consumer for Instrument Air Supply Pcs 2 14.40 142.01 2,044.94 - - 2,510.07 2,799.68 7,354.70 3,677.35 As per Instrument List
7 8 5 2 Instrument Air Distribution Manifold Pcs 46 335.80 142.01 47,686.96 - - 58,533.52 65,287.03 171,507.51 3,728.42 As per Instrument List, Addendum
7 8 5 3 Pneumatic Signal Tubing
7 8 5 3 A for Converter Signal (I/P, P/I) Pcs
7 8 5 3 B for Transmitter / Controller Signal Pcs
7 8 5 3 C for Fire Detection Signal Pcs 3 21.00 142.01 2,982.21 - - 3,660.52 4,082.87 10,725.60 3,575.20 As per Instrument List, (PCV PANEL)
7 8 6 0 Hydraulic Tubing M
7 8 7 0 Instrument Protection
7 8 7 1 Winterizing Box Pcs
7 8 7 2 Sun Shade Pcs 105 210.00 142.01 29,822.10 761.60 79,968.00 36,605.24 40,828.70 187,224.04 1,783.09 As per Instrument List. Addendum1
7 8 9 0 Other Work
Direct buried trench to Waster water pond = 200m L x 0.3mW <
7 8 9 1 Cable Protection Tile M2
BOP>
7 8 9 2 (Not Applicable)
7 8 9 3 Cable Route Marker
7 8 9 3 A for Concrete Paved Area Pcs
7 8 9 3 B for Other than Concrete Paved Area Pcs
7 8 9 4 Warning tape for underground cable protection M2 By Civil
7 8 9 5 Excavation M3 By Civil
Direct buried trench to Waster water pond = 200m L x 0.3mW x
7 8 9 6 Sand Filling / Sand Bedding M3
0.3mD <BOP>
7 8 9 7 Soil Backfilling M3 By Civil
7 9 2 0 Loop Test
7 9 2 0 A Analogue I/O Signal Pnt 145 870.00 155.22 135,041.40 - - 151,650.27 169,147.47 455,839.14 3,143.72 As per Instrument List, Addendum1
7 9 2 0 B Digital I/O Signal Pnt 345 897.00 155.22 139,232.34 - - 156,356.66 174,396.87 469,985.87 1,362.28 As per Instrument List
7 B 0 0 Demolition
7 B 1 0 Control System(Indoor)
7 B 1 1 Panel, Rack and Cabinet Pnl
7 B 1 2 DCS / Computer System Pcs
7 B 1 3 Cable Way M
7 B 1 4 Cable Pcs
7 B 2 0 (Not Applicable)
7 B 5 0 Analyzer Pcs
7 B 6 0 (Not Applicable)
Total of FWBS 7000 41,201.81 34,589.67 4,977,197.67 5,756,536.24 6,029,347.11 6,725,004.93 23,488,085.94