ANNEX-3 BILL OF QUANTITY AND COST BREAKDOWN

COST BREAKDOWN
FWBS 8000 ELECTRICAL WORK

cables

ÁUGUST 2023 LABOR MATERIAL EQUIPMENT OTHERS TOTAL COST BQ UNIT


FWBS CODE DESCRIPTION UNIT TOTAL MANHOURS Php/MH COST Php/BQ COST COST COST (12) COST REMARKS

(1) (2) (3) (5) (6) (7)=(5x6) (8) (9)=(4x8) (10) (11) =(7+9+10+11) (13)=(12)/(4)

8100 POWER GENERATOR & SUBSTATION

8110 Generator & Associated Equipment


8111 Power Generator (6.2MW) Set 1.00 46.58 149.70 6,973.03 - - 8,119.39 9,056.19 24,148.61 24,148.61 Installation By Mech
8112 Emergency Generator (Supply by EDC) Set 1.00 46.58 149.70 6,973.03 - - 8,119.39 9,056.19 24,148.61 24,148.61 Installation By Mech
8115 Power Conditioning System (PCS) or Inverter Station Assembly Set
8116 PV Module Set
8117 Tracker System (if PV Module is non-fixed type) Set

Summary

8120 Transformer, Power Capacitor & NEE


8121 Transformer (Non-Field Assembly)
8121A 100 KVA & Below Set
8121B 101 KVA to 500 KVA Set
8121C 501 KVA to 2000 KVA (1.6MVA) Set 1.00 120.00 149.70 17,964.00 - - 20,917.28 23,330.69 62,211.96 62,211.96 approx. 6000kg,Installation By Mech

8121D 2001 KVA to 5000 KVA Set


8121E 5001 KVA to 15000 KVA Set
8121F 15000 KVA Over Set

8122 Transformer (Field Assembly)


8122A 2001 KVA to 5000 KVA Set
8122B 5001 KVA to 15000 KVA (7.27MVA) Set 1.00 125.00 149.70 18,712.50 - - 21,788.83 24,302.80 64,804.13 64,804.13 approx. 11000kg,Installation By
Mech
8122C 15001 KVA to 30000 KVA Set
8122D 30001 KVA to 50000 KVA Set
8122E 50000 KVA Over Set

8123 Power Transformer (Dry type)


8123A 100KVA and above Set

8125 Power Capacitor


8125A 200 KVA & Below Set
8125B 201 KVA to 500KVA Set
8125C 501 KVA to 1000KVA Set
8125D 1001 KVA to 2000KVA Set
8125E 2000 KVA Over Set

8126 Harmonic Filter


8126A 200 KVA & Below Set
8126B 201 KVA to 500KVA Set
8126C 501 KVA to 1000KVA Set
8126D 1001 KVA to 2000KVA Set
8126E 2000 KVA Over Set

8128 Neutral Earthing Equipment (NEE) Set 1.00 18.75 149.70 2,806.88 - - 3,268.32 3,645.42 9,720.62 9,720.62 Located inside E-Container

Summary

8130 Extra High Vol. Equipment


8131 Gas Insulated SWGR (GIS) Bay
8134 Open Type Switchyard
8134A Circuit Breaker (3 poles) Set by 3rd Party
8134B Disconnecting Switch (3 poles) with Earth Switch Set by 3rd Party
8134Ba Disconnecting Switch (3 poles) without Earth Switch Set by 3rd Party
8134C Earthing Switch (3 poles) Set
8134D Potential transformer (PT) Pcs by 3rd Party
8134E Current Transformer (CT) Pcs by 3rd Party
8134F Lightning Arrester Pcs
8134G Insulator Post Pcs by 3rd Party
8134H Line Trap Pcs
8134J Conductor & Fitting M by 3rd Party
8138 Gantry Tower Ton
8139 Transmission Line Tower/Pole & Conductor
8139A Steel Structure Tower Set by 3rd Party
8139B Pole Type Set by 3rd Party
8139C Conductor and Fitting M by 3rd Party

Summary

8140 Switchgear and MCC


8141 Low Vol. Switchgear Pnl
8141A ACB Switchgear (2xBFA01 and 2xBFA02) Pnl 4.00 228.40 149.70 34,191.48 39,812.55 44,406.07 118,410.10 29,602.53 Located inside E-Container
8141B MCCB Switchgear (BRA01 Incomer UPS LV Panel) Pnl 1.00 57.10 149.70 8,547.87 9,953.14 11,101.52 29,602.53 29,602.53
8142 Low Vol. MCC
8142A Double front / Back to back arrangement Pnl
8142B Single front arrangement (8xBFA01 / 4xBFA02 / 3xBRA01) Pnl 15.00 834.00 149.70 124,849.80 145,375.08 162,148.26 432,373.15 28,824.88 Located inside E-Container
8143 3 KV to 5KV Switchgear and MCC
8143A Switchgear (Incomer, Bustie) Pnl
8143B Switchgear (Feeder, Starter) (1 TIER PER PANEL) Unit
8144 6 KV to 14.6 KV Switchgear and MCC
8144A Switchgear (2xIncomer, STG & Main TR) Pnl 2.00 130.20 149.70 19,490.94 22,695.25 25,313.79 67,499.98 33,749.99 Located inside E-Container
8144B Switchgear (1xFeeder) (1 TIER PER PANEL) Pnl 1.00 65.10 149.70 9,745.47 11,347.62 12,656.90 33,749.99 33,749.99 Located inside E-Container
8145 15 KV to 40.5 KV Switchgear Pnl
8145A Switchgear (Incomer, Bustie) Pnl
8145B Switchgear (Feeder, Starter) (("INDICATE NO. OF TIER) TIER PER PANEL) Unit
8146 45 KV to 72.5 KV Switchgear Pnl
8146A Switchgear (Incomer, Bustie) Pnl
8146B Switchgear (Feeder, Starter) (("INDICATE NO. OF TIER) TIER PER PANEL) Unit
8147 72.5 KV Over Switchgear Pnl
8147A Switchgear (Incomer, Bustie) Pnl
8147B Switchgear (Feeder, Starter) (("INDICATE NO. OF TIER) TIER PER PANEL) Unit
8148 Metering (13.8kV VT)/ Riser Panel / Dummy Panel Pnl 1.00 22.00 149.70 3,293.40 3,834.83 4,277.29 11,405.53 11,405.53 Located inside E-Container
8149 VSD
8149A LV VSD (BFA04/05/06/07/08/09) Set 6.00 132.00 149.70 19,760.40 23,009.01 25,663.75 68,433.16 11,405.53 Located inside E-Container
8149B HV VSD 1000KVA and below Set
8149C HV VSD 1001KVA to 5000KVA Set
8149D HV VSD 5001KVA to 10000KVA Set
8149E HV VSD 10001KVA and over Set
814R Retrofitting Works
814RA LV MCC Bucket
814RB MV Switchgear Unit

Summary

8150
8150 UPS system
8151 AC UPS Set
8151A Single Type ( Set 1.00 41.40 149.70 6,197.58 7,216.46 8,049.09 21,463.13 21,463.13 Located inside E-Container
8151B Dual Type Set
8152 DC UPS
8152A Single Type Set 1.00 41.40 149.70 6,197.58 7,216.46 8,049.09 21,463.13 21,463.13 Located inside E-Container
Single Type (CA 125DC UPS Install Only) Set -
8152B Dual Type Set
8153 Battery Bank
8153A Non-maintenance Free Set 2.00 130.20 149.70 19,490.94 22,695.25 25,313.79 67,499.98 33,749.99 Located inside E-Container
Non-maintenance Free (CA Batteries) Set -
ÁUGUST 2023 LABOR MATERIAL EQUIPMENT OTHERS TOTAL COST BQ UNIT
FWBS CODE DESCRIPTION UNIT TOTAL MANHOURS Php/MH COST Php/BQ COST COST COST (12) COST REMARKS

(1) (2) (3) (5) (6) (7)=(5x6) (8) (9)=(4x8) (10) (11) =(7+9+10+11) (13)=(12)/(4)
8153B Maintenance Free Set

Summary

8160
8160 Bus Duct
8161 Bus Duct
8161A L= 5m & Below Set
8161B L= 5.1m to 10m Set
8161C L= 10.1m to 15m Set
8161D L= Over 15m Set

Summary

8170
8170 Control, Distribution & Misc Panels and auxiliary transformer (if any)
8171 Self-Standing Panel with transformer
8171A Up to 800mm Width panel Pnl
8171B Above 800mm Width panel (Ltg Panel Normal & Emerg) Pnl 2.00 64.00 149.70 9,580.80 - 11,155.88 12,443.03 33,179.71 16,589.86 For BOP, assumed self-stand panel.
Steel matls not required
8171C Above 800mm Width panel (Ltg Panel Normal & Emerg) Pnl 2.00 65.60 149.70 9,820.32 - 11,434.78 12,754.11 34,009.21 17,004.60 Located inside E-Container
Above 800mm Width panel (CA Outdoor Ltg Panel Installation Only) Pnl -

8172 Self-Standing Panel without transformer


8172A Up to 800mm Width panel Pnl Located inside E-Container
8172B Above 800mm Width panel (EDC FCRS Panel Install Only) Pnl - Pre-installed inside E-Container
Above 800mm Width panel (CA Protection Panel Install Only) Pnl -
Above 800mm Width panel (CA Bay Control Panel Install Only) Pnl -
Above 800mm Width panel (CA NDME Panel Install Only) Pnl -
8173 Wall-Mount Panel
8173A Wall-mount panel (directly mounted on wall) Pnl
8173B Wall-mount panel (plus steel standing support) Pnl

8174 Steel Material for Support of Wall-Mount Panels (Ltg Pnl N&E) Kgs -
Steel Material for Support of Wall-Mount Panels (FCRS Panel) Kgs -
Steel Material for Support of Wall-Mount Panels (CA Panels) Kgs -

Summary

8180 Electrical Network Monitoring & Control System(ENMC)


8181 System Cabinet Set
8182 Human Machine Interface (HMI) Set
8183 Remote Terminal Unit (RTU) Set

Summary

8190 Other Work


8191 E-Containers Set INSTALLED BY MECHANICAL
8192 Cable Gland Box SqM
8193 MCT Frame
8193A MCT Frame Hole
no. of cables
8193B MCT Modules

819D Demolition of Equipment


819DA < see note 1 > Set
Summary

SUMMARY ( 8 1 0 0 )

8200 POWER WORK

8210
8210 Motor
8211 Motor
8211A LV Motor Set 39.00 936.00 149.70 140,119.20 - - 163,154.77 181,979.35 485,253.32 12,442.39
8211B HV Motor Set
8214 MOV Set

Summary

8220 Local Equipment


8221A Control Station / Remote Control Unit w/o Misc. foundation Set
8221B Emergency Stop Control Station w/ Misc. foundation Set BQ of Emerg PB by INS
8222A Safety Switch / Isolator Switch w/o Misc. foundation Set
8222B Safety Switch / Isolator Switch w/ Misc. foundation Set
8223A Local Dist. Panel/Starter w/o Misc. foundation Set
8223B Local Dist. Panel/Starter w/ Misc. foundation Set
8224A Power Outlet / Main Junction Box w/o Misc. foundation Set 2.00 14.36 149.70 2,149.69 - - 2,503.10 2,791.91 7,444.70 3,722.35
8224B Power Outlet / Main Junction Box w/ Misc. foundation Set
8225A Local Control Panel for Package Equipment w/o Misc. foundation Pnl
8225B Local Control Panel for Package Equipment w/ Misc. foundation Pnl

8228 Steel Material for Support of Local Equipment Kg 140.00 112.00 149.70 16,766.40 203.84 28,537.60 19,522.79 21,775.31 86,602.10 618.59
Summary

8260
8260 Cabling & Wiring
8261 Cable (Above Ground Cabling)
8261A Low Voltage
chg 0.6/1kV CU/XLPE/PVC/FR 1C - 150 sqmm M 426.00 153.36 140.00 21,470.40 31.36 13,359.36 26,732.28 29,816.62 91,378.66 214.50 material cost for branch cable way
and supports
8261Aa 0.6/1kV CU/XLPE/PVC/FR 1C - 500 sqmm M 888.00 355.20 140.00 49,728.00 31.36 27,847.68 61,915.14 69,058.83 208,549.65 234.85 material cost for branch cable way
and supports
8261Ab 1C - 630 sqmm M
chg 0.6/1kV CU/XLPE/PVC/FR 2C-2.5+E M 2,268.00 748.44 140.00 104,781.60 24.64 55,883.52 130,461.07 145,513.48 436,639.67 192.52 material cost for branch cable way
and supports
chg 8261Ac 0.6/1kV CU/XLPE/PVC/FR 2C-4+E M 1,974.00 651.42 140.00 91,198.80 24.64 48,639.36 113,549.45 126,650.63 380,038.23 192.52 material cost for branch cable way
and supports
chg 8261Ad 0.6/1kV CU/XLPE/PVC/FR 2C-6+E M 432.00 142.56 140.00 19,958.40 20.16 8,709.12 24,849.73 27,716.85 81,234.10 188.04 material cost for branch cable way
and supports
add 0.6/1kV CU/XLPE/PVC/FR 2C-10+E M 92.00 30.36 140.00 4,250.40 20.16 1,854.72 5,292.07 5,902.66 17,299.85 188.04 material cost for branch cable way
and supports
chg 0.6/1kV CU/XLPE/PVC/FR 2C-25+E M
8261Ae 0.6/1kV CU/XLPE/STA/FRPVC 2C-35 M
8261Af 0.6/1kV CU/XLPE/STA/FRPVC 3C-4 M
chg 0.6/1kV CU/XLPE/PVC/FR 3C-2.5+E M 522.00 172.26 140.00 24,116.40 20.16 10,523.52 30,026.75 33,491.20 98,157.87 188.04 material cost for branch cable way
and supports
chg 8261Ag 0.6/1kV CU/XLPE/PVC/FR 3C-4+E M 651.00 221.34 140.00 30,987.60 22.40 14,582.40 38,581.92 43,033.45 127,185.37 195.37 material cost for branch cable way
and supports
add 0.6/1kV CU/XLPE/PVC/FR 3C-4+E M 200.00 68.00 140.00 9,520.00 22.40 4,480.00 11,853.12 13,220.72 39,073.85 195.37 Vendor Supply. Install by Elect
chg 0.6/1kV CU/XLPE/PVC/FR 3C-6+E M 276.00 88.32 140.00 12,364.80 22.40 6,182.40 15,395.12 17,171.38 51,113.70 185.19 material cost for branch cable way
and supports
add 0.6/1kV CU/XLPE/PVC/FR/CTS 3C-6+3C-2.5 M 231.00 78.54 140.00 10,995.60 22.40 5,174.40 13,690.36 15,269.93 45,130.29 195.37 material cost for branch cable way
and supports
add 0.6/1kV CU/XLPE/PVC/FR 3C-10+E M
chg 8261Ah 0.6/1kV CU/XLPE/PVC/FR 3C-16+E M 600.00 204.00 140.00 28,560.00 24.64 14,784.00 35,559.37 39,662.17 118,565.54 197.61 material cost for branch cable way
and supports
add 0.6/1kV CU/XLPE/PVC/FR 3C-25+E M 676.00 236.60 140.00 33,124.00 24.64 16,656.64 41,241.90 46,000.33 137,022.88 202.70 material cost for branch cable way
and supports
chg 8261Ai 0.6/1kV CU/XLPE/STA/FRPVC 3C-50+E M 295.00 103.25 140.00 14,455.00 24.64 7,268.80 17,997.57 20,074.11 59,795.49 202.70 material cost for branch cable way
and supports
chg 0.6/1kV CU/XLPE/PVC/FR 3C-70+E M 30.00 9.90 140.00 1,386.00 24.64 739.20 1,725.68 1,924.78 5,775.66 192.52 material cost for branch cable way
and supports
chg 0.6/1kV CU/XLPE/PVC/FR/CTS 3C-70+3C-16 M 276.00 91.08 140.00 12,751.20 24.64 6,800.64 15,876.21 17,707.99 53,136.04 192.52 VSD/material cost for branch cable
way and supports
8261Aj 0.6/1kV CU/XLPE/STA/FRPVC 3C-95 M
add 0.6/1kV CU/XLPE/PVC/FR/CTS 3C-95+3C-16 M 55.00 19.80 140.00 2,772.00 24.64 1,355.20 3,451.35 3,849.56 11,428.11 207.78 VSD/material cost for branch cable
way and supports
0.6/1kV CU/XLPE/STA/FRPVC 3C-120 (SH) M
0.6/1kV CU/XLPE/STA/FRPVC 3C-240 M
add 8261Ak 0.6/1kV CU/XLPE/PVC/FR 3C-150+E M 135.00 48.60 140.00 6,804.00 26.88 3,628.80 8,471.50 9,448.93 28,353.23 210.02
ÁUGUST 2023 LABOR MATERIAL EQUIPMENT OTHERS TOTAL COST BQ UNIT
FWBS CODE DESCRIPTION UNIT TOTAL MANHOURS Php/MH COST Php/BQ COST COST COST (12) COST REMARKS

(1) (2) (3) (5) (6) (7)=(5x6) (8) (9)=(4x8) (10) (11) =(7+9+10+11) (13)=(12)/(4)
chg 0.6/1kV CU/XLPE/PVC/FR 3C-185+E M 356.00 128.16 140.00 17,942.40 26.88 9,569.28 22,339.65 24,917.17 74,768.51 210.02
add 0.6/1kV CU/XLPE/PVC/FR/CTS 3C-150+3C-25 M 216.00 77.76 140.00 10,886.40 26.88 5,806.08 13,554.40 15,118.28 45,365.16 210.02 VSD Panel to Motor
add 0.6/1kV CU/XLPE/PVC/FR/CTS 3C-185+3C-25 M 45.00 16.20 140.00 2,268.00 26.88 1,209.60 2,823.83 3,149.64 9,451.08 210.02 MCC to VSD Panel
add 0.6/1kV CU/XLPE/PVC/FR 4C-2.5+E M 18.00 6.48 140.00 907.20 26.88 483.84 1,129.53 1,259.86 3,780.43 210.02 E-Container ventilation panel
add 0.6/1kV CU/XLPE/PVC/FR 4C-35+E M -

add 0.6/1kV CU/PVC 1C-25 Flexible Battery Cable M 29.00 9.28 140.00 1,299.20 183.68 5,326.72 1,617.60 1,804.24 10,047.76 346.47 FDCC supply
add 0.6/1kV CU/PVC 1C-150 Flexible Battery Cable M 84.00 26.88 140.00 3,763.20 183.68 15,429.12 4,685.47 5,226.07 29,103.86 346.47 FDCC supply

8261Ak 2/3/4C - 2.5 sqmm - 25 sqmm. M


8261Al 2/3/4C - 35 sqmm - 70 sqmm. M
8261Am 2/3/4C - 95 sqmm - 150 sqmm. M
8261An 2/3/4C - 185 sqmm - 240 sqmm. M
(ENUMERATE THE SIZES OF CABLES USED)
8261B Medium Voltage (3-5kV)
8261Ba 3.6/6kV CU/TR-XLPE/AIA/FRPVC 1C-185 M
8261Bb 3.6/6kV CU/XLPE/STA/FRPVC 3C-120 M
8261Bc 3.6/6kV CU/TR-XLPE/SIA/FRPVC 3C-35 M
8261Bd 3.6/6kV CU/XLPE/STA/FRPVC 3C-35 M

8261C Medium Voltage (6-14.6kV)


add 8.7/15kV CU/TR-XLPE/PVC/FR 1C-150 M 426.00 153.36 140.00 21,470.40 42.56 18,130.56 26,732.28 29,816.62 96,149.86 225.70
8261Ca 8.7/15kV CU/TR-XLPE/AIA/FRPVC 1C-500 M
8261Cb 8.7/15kV CU/TR-XLPE/AIA/FRPVC 1C-185 M
1C-120 sqmm M

8261D Medium Voltage (15-40.5kV)


8261Da (ENUMERATE THE SIZES OF CABLES USED) M
8261Db M

8261E Medium Voltage (45-72.5kV)


8261Ea (ENUMERATE THE SIZES OF CABLES USED) M
8261Eb M

8261F Medium Voltage (72.5kV and Over)


8261Fa (ENUMERATE THE SIZES OF CABLES USED) M
8261Fb M

8261H Control
8261Ha 0.6/1kV CU/XLPE/STA/FRPVC 2C-4 M
8261Hb 0.6/1kV CU/XLPE/STA/FRPVC 2C-6 M
0.6/1kV CU/XLPE/PVC/FR 2C-10 M 308.00 80.08 140.00 11,211.20 - - 13,958.80 15,569.34 40,739.34 132.27
0.6/1kV CU/XLPE/STA/FRPVC 4C-2.5 M
0.6/1kV CU/XLPE/PVC/FR 4C-6 M -
0.6/1kV CU/XLPE/PVC/FR 4C-10 M 268.00 69.68 140.00 9,755.20 - - 12,145.97 13,547.35 35,448.52 132.27
0.6/1kV CU/XLPE/STA/FRPVC 5C-1.5 M
chg 8261Hc 0.6/1kV CU/XLPE/PVC/FR 7C-1.5 M 2,090.00 543.40 140.00 76,076.00 - - 94,720.41 105,649.12 276,445.53 132.27 Combined all control to 1.5
chg 0.6/1kV CU/XLPE/PVC/FR 7C-2.5 M - Deleted. Chge to 1.5
chg 0.6/1kV CU/XLPE/PVC/FR 12C-1.5 M 1,501.00 390.26 140.00 54,636.40 - - 68,026.48 75,875.28 198,538.15 132.27
8261Hd 0.6/1kV CU/XLPE/STA/FRPVC 20C-1.5 M
8261He 0.6/1kV CU/XLPE/STA/FRPVC 30C-1.5 M
8261Hf 0.6/1kV CU/XLPE/STA/FRPVC CAT-6 M
8261Hg 2C -12C M
8261Hh 13C - 24C M
8261Hi 0.6/1kV CU/XLPE/STA/FRPVC 8T-1.5 M
8261Hj 0.6/1kV CU/XLPE/STA/FRPVC 2P-1.5 M
8261Hm 0.6/1kV CU/XLPE/STA/FRPVC 5P-1.5 M
8261Hn 11P - above M
add 1Triad - 1.5 M Deleted cable for PTC. By INS
8261Ho 3Triad M
8261Hp 6Triad M
8261Hq 2C-2.5+E M
8261Hr 2C-4+E M
8261Hs Fiber Optic, Single Mode, 6C M
8261Ht Fiber Optic, Single Mode, 24C M

8262 Wire M

8263 Cable (Underground Cabling)


8263A Low Voltage
0.6/1kV CU/XLPE/PVC/FR 1C - 150 sqmm M
8263Aa 0.6/1kV CU/XLPE/PVC/FR 1C - 500 sqmm M 672.00 268.80 140.00 37,632.00 - - 46,854.70 52,260.74 136,747.44 203.49
8263Ab 1C - 630 sqmm M
chg 0.6/1kV CU/XLPE/PVC/FR 2C-2.5+E M 400.00 120.00 140.00 16,800.00 - - 20,917.28 23,330.69 61,047.96 152.62
chg 8263Ac 0.6/1kV CU/XLPE/PVC/FR 2C-4+E M 586.00 175.80 140.00 24,612.00 - - 30,643.81 34,179.45 89,435.27 152.62
8263Ad 0.6/1kV CU/XLPE/STA/FRPVC 3C-10 M
add 0.6/1kV CU/XLPE/PVC/FR 2C-6+E M 63.00 17.64 140.00 2,469.60 - - 3,074.84 3,429.61 8,974.05 142.45
add 0.6/1kV CU/XLPE/PVC/FR 2C-25+E M
8263Ae 0.6/1kV CU/XLPE/STA/FRPVC 2C-35 M
8263Af 0.6/1kV CU/XLPE/STA/FRPVC 3C-4 M
0.6/1kV CU/XLPE/STA/FRPVC 3C-6 M
chg 0.6/1kV CU/XLPE/STA/FRPVC 3C-2.5+E M 440.00 123.20 140.00 17,248.00 - - 21,475.07 23,952.84 62,675.91 142.45
chg 8263Ag 0.6/1kV CU/XLPE/PVC/FR 3C-4+E M 401.00 112.28 140.00 15,719.20 - - 19,571.60 21,829.74 57,120.54 142.45
0.6/1kV CU/XLPE/PVC/FR 3C-6+E M 54.00 15.12 140.00 2,116.80 - - 2,635.58 2,939.67 7,692.04 142.45
add 0.6/1kV CU/XLPE/PVC/FR/CTS 3C-6+3C-2.5 M 54.00 15.12 140.00 2,116.80 - - 2,635.58 2,939.67 7,692.04 142.45 VSD Motor
add 0.6/1kV CU/XLPE/PVC/FR 3C-10+E M
chg 8263Ah 0.6/1kV CU/XLPE/PVC/FR 3C-16+E M 234.00 74.88 140.00 10,483.20 - - 13,052.38 14,558.35 38,093.93 162.79
add 0.6/1kV CU/XLPE/PVC/FR 3C-25+E M 135.00 43.20 140.00 6,048.00 - - 7,530.22 8,399.05 21,977.27 162.79
chg 8263Ai 0.6/1kV CU/XLPE/PVC/FR 3C-50+E M 54.00 17.28 140.00 2,419.20 - - 3,012.09 3,359.62 8,790.91 162.79
chg 0.6/1kV CU/XLPE/PVC/FR 3C-70+E M 26.00 8.32 140.00 1,164.80 - - 1,450.26 1,617.59 4,232.66 162.79
add 0.6/1kV CU/XLPE/PVC/FR/CTS 3C-70+3C-16 M 54.00 17.28 140.00 2,419.20 - - 3,012.09 3,359.62 8,790.91 162.79 VSD
8263Aj 0.6/1kV CU/XLPE/STA/FRPVC 3C-95 M
add 0.6/1kV CU/XLPE/PVC/FR/CTS 3C-95+3C-16 M
8263Aj 0.6/1kV CU/XLPE/STA/FRPVC 3C-95 (SH) M
0.6/1kV CU/XLPE/STA/FRPVC 3C-120 (SH) M for edg power
add 0.6/1kV CU/XLPE/PVC/FR 3C-185+E M 36.00 11.52 140.00 1,612.80 - - 2,008.06 2,239.75 5,860.60 162.79
add 0.6/1kV CU/XLPE/PVC/FR/CTS 3C-150+3C-25 M 54.00 17.28 140.00 2,419.20 - - 3,012.09 3,359.62 8,790.91 162.79 VSD Panel to Motor
add 0.6/1kV CU/XLPE/PVC/FR/CTS 3C-185+3C-25 MCC to VSD Panel
8263Ak 0.6/1kV CU/XLPE/STA/FRPVC 3C-240 M
2/3/4C - 2.5 sqmm - 25 sqmm. M
0.6/1kV CU/XLPE/PVC/FR 4C - 2.5 M
0.6/1kV CU/XLPE/STA/FRPVC 4C - 4 M
add 0.6/1kV CU/XLPE/PVC/FR 4C-35+E M
2/3/4C - 35 sqmm - 70 sqmm. M
2/3/4C - 95 sqmm - 150 sqmm. M
2/3/4C - 185 sqmm - 240 sqmm. M
1C - 185 sqmm M
1C - 240 sqmm M
1C - 300 sqmm M
1C - 400 sqmm M
1C - 800 sqmm M
1C - 1000 sqmm M
2/3/4C - 2.5 sqmm - 25 sqmm. M
2/3/4C - 35 sqmm - 70 sqmm. M
2/3/4C - 95 sqmm - 150 sqmm. M
2/3/4C - 185 sqmm - 240 sqmm. M

8263B Medium Voltage (3-5kV)


8263Ba 3.6/6kV CU/TR-XLPE/AIA/FRPVC 1C-185 M
8263Bb 3.6/6kV CU/XLPE/STA/FRPVC 3C-120 M
8263Bc 3.6/6kV CU/TR-XLPE/SIA/FRPVC 3C-35 M
8263Bd 3.6/6kV CU/XLPE/STA/FRPVC 3C-35 M

8263C Medium Voltage (6-14.6kV)


ÁUGUST 2023 LABOR MATERIAL EQUIPMENT OTHERS TOTAL COST BQ UNIT
FWBS CODE DESCRIPTION UNIT TOTAL MANHOURS Php/MH COST Php/BQ COST COST COST (12) COST REMARKS

(1) (2) (3) (5) (6) (7)=(5x6) (8) (9)=(4x8) (10) (11) =(7+9+10+11) (13)=(12)/(4)
add 8.7/15kV CU/TR-XLPE/PVC/FR 1C-150 M 294.00 105.84 140.00 14,817.60 - - 18,449.04 20,577.66 53,844.30 183.14
8263Ca 8.7/15kV CU/TR-XLPE/AIA/FRPVC 1C-400 M
8263Cb 8.7/15kV CU/TR-XLPE/AIA/FRPVC 1C-185 M
Internal Cabling
1C-400 sqmm M
3C-150 sqmm M
External Cabling
1C-120 sqmm M
3C-240 M
3C-16 M
3C-185 M
8263D Medium Voltage (15-40.5kV)
(ENUMERATE THE SIZES OF CABLES USED) M

8263E Medium Voltage (45-72.5kV)


(ENUMERATE THE SIZES OF CABLES USED) M

8263F Medium Voltage (72.5kV and Over)


(ENUMERATE THE SIZES OF CABLES USED) M

8263H Control
8263Ha 0.6/1kV CU/XLPE/PVC/FRP 2C-4 M
0.6/1kV CU/XLPE/PVC/FRP 2C-10 M 210.00 54.60 140.00 7,644.00 - - 9,517.36 10,615.46 27,776.82 132.27
8263Hb 0.6/1kV CU/XLPE/PVC/FRP 2C-6 M
add 0.6/1kV CU/XLPE/PVC/FRP 4C-6 M
0.6/1kV CU/XLPE/PVC/FRP 4C-10 M 210.00 54.60 140.00 7,644.00 - - 9,517.36 10,615.46 27,776.82 132.27 Gen. Neutral CT & Protection
chg 0.6/1kV CU/XLPE/PVC/FRP 7C-2.5 M - 7c-2.5 + 4c-2.5 + 3c-2.5 (chg to 1.5)
chg 8263Hc 0.6/1kV CU/XLPE/PVC/FRP 7C-1.5 M 361.00 93.86 140.00 13,140.40 - - 16,360.80 18,248.48 47,749.68 132.27 2c-1.5 + 5c-1.5 + 7c-1.5 + all 2.5
0.6/1kV CU/XLPE/PVC/FRP 12C-1.5 M 317.00 82.42 140.00 11,538.80 - - 14,366.68 16,024.29 41,929.78 132.27
8263Hd 0.6/1kV CU/XLPE/PVC/FRP 20C-1.5 M
8263He 0.6/1kV CU/XLPE/PVC/FRP 30C-1.5 M
8263Hf 0.6/1kV CU/XLPE/PVC/FRP CAT-6 M
8263Hg 2C -12C M
8263Hh 13C - 24C M
8263Hi 0.6/1kV CU/XLPE/PVC/FRP 8T-1.5 M
8263Hj 0.6/1kV CU/XLPE/PVC/FRP 2P-1.5 M
8263Hk 0.6/1kV CU/XLPE/PVC/FRP 5P-1.5 M
8263Hl 1P - 10P M
8263Hm 11P - above M
add 1Triad - 1.5 M Deleted cable for PTC. By INS
8263Hn 3Triad M
8263Ho 6Triad M
8263Hp 2C-2.5+E M
8263Hq 2C-4+E M
8263Hs Fiber Optic, Single Mode, 6C M
8263Ht Fiber Optic, Single Mode, 24C M
2C -12C M
13C - 24C M
25C - 36C M
37C - 48C M
48C - above M
1P - 10P M
11P - above M
3Triad M
6Triad M
2C-2.5+E M
2C-4+E M

Summary

8270 Termination and Splicing of Cable & Wire


8271 Termination
chg 8271A Low Voltage Cable Pnt 414.00 3,808.80 153.50 584,650.80 5,376.00 2,225,664.00 663,914.42 740,515.95 4,214,745.17 10,180.54 LV + Gndg + VS Supply cables
8271B 3 KV to 5 KV Cable Pnt
8271C 6 KV to 14.6 KV Cable Pnt 20.00 320.00 153.50 49,120.00 - - 55,779.41 62,215.16 167,114.57 8,355.73 Materials by JPHIL
8271D 15 KV to 40.5 KV Cable Pnt
8271E 45 KV to 72.5 KV Cable Pnt
8271F 72.5 KV Over Cable Pnt
8271H Control Cable Pnt
0.6/1kV CU/XLPE/PVC/FRP 2C-10 Pnt 18.00 129.60 153.50 19,893.60 125.44 2,257.92 22,590.66 25,197.14 69,939.32 3,885.52
chg 0.6/1kV CU/XLPE/PVC/FRP 4C-6 Pnt - deleted/combined w 4C-10
chg 0.6/1kV CU/XLPE/PVC/FRP 4C-10 Pnt 18.00 129.60 153.50 19,893.60 250.88 4,515.84 22,590.66 25,197.14 72,197.24 4,010.96 added 4C-6
chg 0.6/1kV CU/XLPE/PVC/FRP 7C-2.5 Pnt - deleted/combined w 7C-1.5
chg 8271Ha 0.6/1kV CU/XLPE/PVC/FRP 7C-1.5 Pnt 112.00 813.12 153.50 124,813.92 72.13 8,078.34 141,735.48 158,088.72 432,716.46 3,863.54 added 7C-2.5
chg 8271Hb 0.6/1kV CU/XLPE/PVC/FRP 12C-1.5 Pnt 62.00 496.00 153.50 76,136.00 123.65 7,666.18 86,458.08 96,433.50 266,693.76 4,301.51
20C-1.5 Pnt
8271Hc 24C-1.5+E Pnt
1Triad - 1.5 Pnt deleted, INS scope (PTC)
8271Hd 6T-1.5 Pnt
5P-1.5 Pnt
2C-2.5+E Pnt
2C-4+E Pnt
Fiber Optic, Single Mode, 6C Core
Fiber Optic, Single Mode, 24C Core

8171J Wire Pnt


8272 Splicing
8272A Low Voltage Cable Pnt
8272B 3 KV to 5 KV Cable Pnt
8272C 6 KV to 14.6 KV Cable Pnt
8272D 15 KV to 40.5 KV Cable Pnt
8272E 45 KV to 72.5 KV Cable Pnt
8272F 72.5 KV Over Cable Pnt
8272H Control Cable (Metal Cable)
8272Ha 4C- Pnt
8272Hb 7C- Pnt
8272Hc 12C- Pnt
8272Hd <LE TO FILL ADDITIONAL SUBs AS REQUIRED> Pnt
Summary

8280 Cable Way


8281 Cable Ladder Tray & Cover
8281A 150W M
8281B 300W M 432.00 1,684.80 140.00 235,872.00 - - 293,678.59 327,562.82 857,113.41 1,984.06
8281C 450W M
8281D 600W M 144.00 745.92 140.00 104,428.80 - - 130,021.80 145,023.54 379,474.14 2,635.24
8281E 750W M
8281F 900W M 72.00 455.04 140.00 63,705.60 - - 79,318.32 88,469.96 231,493.88 3,215.19
8281G 1200W M
8281H OTHERS M
8281J 150W (COVER) M
8281K 300W (COVER) M 202.00 171.70 140.00 24,038.00 - - 29,929.14 33,382.32 87,349.46 432.42
8281L 450W (COVER) M
8281M 600W (COVER) M 60.00 51.00 140.00 7,140.00 - - 8,889.84 9,915.54 25,945.38 432.42
8281N 750W (COVER) M
8281O 900W (COVER) M 30.00 29.10 140.00 4,074.00 - - 5,072.44 5,657.69 14,804.13 493.47
8281P 1200W (COVER) M
8281Q OTHERS M

8282 Perforated Tray for Branch Cables


ÁUGUST 2023 LABOR MATERIAL EQUIPMENT OTHERS TOTAL COST BQ UNIT
FWBS CODE DESCRIPTION UNIT TOTAL MANHOURS Php/MH COST Php/BQ COST COST COST (12) COST REMARKS

(1) (2) (3) (5) (6) (7)=(5x6) (8) (9)=(4x8) (10) (11) =(7+9+10+11) (13)=(12)/(4)
8282A 100W M
8282B 150W M
8282C 200W M

8283 Cable Ladder Tray Support


8283A For Main Cable Ladder Tray w/o CIVIL structural support Kg 2,672.00 855.04 140.00 119,705.60 203.84 544,660.48 149,042.58 166,238.91 979,647.57 366.63
8283B For Branch Cable Ladder Tray w/o CIVIL structural support Kg

8284 Underground Eflex Connection


8284A PVC to PVC
8284Aa 1/2"
8284Ab 3/4"
8284Ac 1"
8284Ad 1-1/2"
8284Ae 2"
8284Af 2-1/2"
8284Ag 3" Sets 14.00 44.80 140.00 6,272.00 1,400.00 19,600.00 7,809.12 8,710.12 42,391.24 3,027.95
8284Ah 4"
8284Ai 5"
8284Aj 6"
8284B PVC to Stub up
8284Ba 2"
chg 8284Bb 3" Sets 12.00 51.60 140.00 7,224.00 1,400.00 16,800.00 8,994.43 10,032.19 43,050.62 3,587.55 Added 4 sets for Cooling Tower
8284Bc 4"
8284Bd 6" Sets 13.00 67.60 140.00 9,464.00 3,920.00 50,960.00 11,783.40 13,142.95 85,350.35 6,565.41
8284C Terminal and Pull Box Pcs

8284D Steel Material for support of RSC above ground installation kg


Summary

8290 Other Work

8295 Cable Trench


8295A Excavation M3
8295B Sand Filling M3
8295C Back Filling M3
8295D Cable Protection Tile M2
8295E Cable Warning Sheet M2

8296 Cable Route Marker Pcs 51.00 175.95 140.00 24,633.00 6,720.00 342,720.00 30,669.96 34,208.62 432,231.58 8,475.13

829D Demolition of Equipment


829DA < see note 1 > Set

829T Disconnection and Reconnection of Existing Cables Pnt

Summary

SUMMARY ( 8 2 0 0 )

8300 LIGHTING

8310 Lighting Panel Board


8310Aa Lighting Panel Board with Transformer (w/o miscellaneous foundation) Set - Assumed self-stand panel. Steel
matls not required
8310Ab Lighting Panel Board with Transformer (w/ miscellaneous foundation) Set
8310Ba Lighting Panel Board without Transformer (w/o miscellaneous foundation) Set
8310Bb Lighting Panel Board without Transformer (w/ miscellaneous foundation) Set

8311 Steel Material for Support of Lighting Panelboard Kg

Summary

8320
8320 Lighting in Plant
8321 Lighting Pole
8321A 50mm dia PIpe, 2.5M Height HDG Set 47.00 196.46 144.80 28,447.41 6,552.00 307,944.00 34,245.07 38,196.22 408,832.70 8,698.57
8321Ba Lighting Pole 5M Height, HDG Set 20.00 122.60 144.80 17,752.48 8,400.00 168,000.00 21,370.49 23,836.18 230,959.15 11,547.96
8321Bb Above 3M Height up to 8M Height, double arm Set
8321C Above 8M Height up to 15M Height Set

8322 Lighting Mast


8322A Up to 30M Height Set
8322B Above 30M Height Set
8323 Lighting Fixture with Cabling Works Set 78.00 725.40 144.80 105,037.92 - - 126,444.95 141,033.99 372,516.86 4,775.86
8324 Convenience Outlet with Cabling Works Set 2.00 22.64 144.80 3,278.27 - - 3,946.39 4,401.72 11,626.39 5,813.19
8325 Local Equipment
8325A Junction Box Set 55.00 374.00 144.80 54,155.20 - - 65,192.18 72,713.97 192,061.35 3,492.02
8325B Lighting Photocell Set 2.00 10.00 144.80 1,448.00 - - 1,743.11 1,944.22 5,135.33 2,567.67 1 photocell per each panel
8326 Cabling and Wiring M 3,350.00 1,072.00 144.80 155,225.60 - - 186,861.02 208,420.79 550,507.41 164.33
8326a Termination Pnt 282.00 1,178.76 144.80 170,684.45 288.96 81,486.72 205,470.43 229,177.32 686,818.92 2,435.53
832xxx Cable Way M
832xxx Conduit Piping M
832xxx Perforated Cable Tray M
8327 Trench for Lighting in Plant (dedicated for lighting cables only) M3

Summary

8330 Street, Fence, Security


8331 Lighting Pole
8331B Set 7.00
65.45 144.80 9,477.16 18,144.00 127,008.00 11,408.63 12,724.94 160,618.74 22,945.53
Street Lighting Pole 8M Height with 2M extended Arm with end point of 58mm dia , HDG
8331C Above 8M Height up to 15M Height single arm Set
Above 8M Height up to 15M Heightwith double arm Set
8332 Lighting Mast
8332A Up to 30M Height Set
8332B Above 30M Height Set
8333 Lighting Fixture Set 7.00 65.10 144.80 9,426.48 - - 11,347.62 12,656.90 33,431.00 4,775.86
8334 Control Panel Set
8335 Local Equipment
8335A Junction Box Set
8335B Lighting Switch Set
8336 Cabling & Wiring
8336A Cable M 411.00 131.52 144.80 19,044.10 - - 22,925.34 25,570.43 67,539.86 164.33
8336B Wire M
8337 Termination Pnt 30.00 125.40 144.80 18,157.92 288.96 8,668.80 21,858.56 24,380.57 73,065.84 2,435.53
8338 Cable Way M
8338A Conduit Piping M
8338B Perforated Cable Tray M
Summary

8340 Aircraft Obstacle Light


8343 Lighting Fixture Set
8344 Control Panel Pnl
8345 Local Equipment
8345A Junction Box Set
8345B Lighting Switch Set
8346 Cabling & Wiring M
8346A Cable M
8346B Wire M
8348 Cable Way M
8348A Conduit Piping M
8348B Perforated Cable Tray M
ÁUGUST 2023 LABOR MATERIAL EQUIPMENT OTHERS TOTAL COST BQ UNIT
FWBS CODE DESCRIPTION UNIT TOTAL MANHOURS Php/MH COST Php/BQ COST COST COST (12) COST REMARKS

(1) (2) (3) (5) (6) (7)=(5x6) (8) (9)=(4x8) (10) (11) =(7+9+10+11) (13)=(12)/(4)

Summary

8350 Navigation Light


8353 Lighting Fixture Set
8354 Control Panel Pnl
8355 Local Equipment
8355A Junction Box Set
8355B Lighting Switch Set
8356 Cabling & Wiring M
8356A Cable M
8356B Wire M
8358 Cable Way M
8358A Conduit Piping M
8358B Perforated Cable Tray M

Summary

8390
8390 Other Work

8395 Cable Trench


8395A Excavation M3
8395B Sand Filling M3
8395C Back Filling M3
8395D Cable Protection Tile M2
8395E Cable Warning Sheet M2

8396 Cable Route Marker Pcs

839D Demolition of Equipment


839DA < see note 1 > Set
Summary

SUMMARY ( 8 3 0 0 )

8400 EARTHING

8410 Wiring of Earthing


8411 Bare Copper
8411A 35 sqmm M
8411B 70 sqmm M 2,000.00 840.00 144.80 121,632.00 - - 146,420.95 163,314.80 431,367.75 215.68
8411C 120 sqmm M
8411D 185 sqmm M
8411E 240 sqmm M
8412 Insulated Copper
8412A 450/750V, 10 sqmm M
8412B 450/750V, 25 sqmm M 848.00 305.28 144.80 44,204.54 - - 53,213.56 59,353.26 156,771.36 184.87
8412C 450/750V, 35 sqmm M
8412D 450/750V, 70 sqmm M 1,472.00 559.36 144.80 80,995.33 - - 97,502.41 108,752.10 287,249.84 195.14
8412E 450/750V, 120 sqmm M
add 450/750V, 150 sqmm M
8412F 450/750V, 185 sqmm M
8412G 450/750V, 240 sqmm M
8412H 450/750V, 300 sqmm M
8420 Earthing Electrode
8421 Earthing Electrode without Boring Pnt 38.00 419.52 144.80 60,746.50 - - 73,126.81 81,564.08 215,437.38 5,669.40
8422 Earthing Electrode with Boring Pnt
8430 Connection to Equipment / Steel Structure / Piping Pnt 182.00 411.32 144.80 59,559.14 510.72 92,951.04 71,697.46 79,969.81 304,177.45 1,671.30
8440 Air Terminal Set 10.00 560.00 144.80 81,088.00 - - 97,613.97 108,876.53 287,578.50 28,757.85
8450 Earth Lug / Boss Pnt
8460 Copper Earth Bars
8461 250mm length Set
8462 450mm length Set 12.00 41.40 144.80 5,994.72 5,432.00 65,184.00 7,216.46 8,049.09 86,444.27 7,203.69
8470 Flexible Earth Bar (Earth Ring under Substation) M

8490 Other Work


8491 Inspection Pit Set 11.00 45.21 144.80 6,546.41 3,472.00 38,192.00 7,880.58 8,789.84 61,408.83 5,582.62 SS4, ORC2, CT1, Perimeter4
8492 Trench for earthing wire M3 94.00 522.64 144.80 75,678.27 - - 91,101.72 101,612.91 268,392.90 2,855.24
8493 Earth reel Set 2.00 12.00 144.80 1,737.60 - - 2,091.73 2,333.07 6,162.40 3,081.20

849D Demolition of Equipment


849DA < see note 1 > Set

SUMMARY ( 8 4 0 0 )

8500 FIRE ALARM SYSTEM

8510 Control Panel Set


8520 Local Equipment Pcs
8560 Cabling M
8570 Terminat'n/Splicing Pnt
8580 Cable Way
8581 Cable Tray M
8582 Conduit Piping M

8590 Other Work


8595 Cable Trench
8595A Excavation M3
8595B Sand Filling M3
8595C Back Filling M3
8595D Cable Protection Tile M2
8595E Cable Warning Sheet M2
8595F
8596 Cable Route Marker Pcs

SUMMARY ( 8 5 0 0 )

8600 COMMUNICATION SYSTEM

8610 Wired System


8611 Paging System
8611A Main Amp. Cabinet Pnl
8611B Handset Set
8611C Speaker Set
8611D Local Amp. Box Set

8612 Telephone System


8612A PABX Set
8612B Attendant Console Set
8612C Telephone Handset Set
8612D MDF/IDF Set
8612G UPS with Battery Set
8612Ga Local Cabinet Wall Mount with Switch Set
Summary

8620 Wireless System

8621 Micro Wave System


8621A Central Cabinet Pnl
8621B Local Cabinet Pnl
8621C Antenna System Set
8621D Antenna Tower Set
8621G UPS with Battery Set
ÁUGUST 2023 LABOR MATERIAL EQUIPMENT OTHERS TOTAL COST BQ UNIT
FWBS CODE DESCRIPTION UNIT TOTAL MANHOURS Php/MH COST Php/BQ COST COST COST (12) COST REMARKS

(1) (2) (3) (5) (6) (7)=(5x6) (8) (9)=(4x8) (10) (11) =(7+9+10+11) (13)=(12)/(4)

8622 VHF, UHF Radio


8622A Central Cabinet Pnl
8622B Local Cabinet Pnl
8622C Antenna System Set
8622D Antenna Tower Set
8622E Handset Set
8622G UPS with Battery Set

8623 Satellite Communication System


8623A Central Cabinet Pnl
8623B Local Cabinet Pnl
8623C Antenna System Set
8623E Hand Set Set
8623G UPS with Battery Set

Summary

8630 LAN/WAN & Data Communication System


8631 LAN/WAN
8631A Central Cabinet Pnl
8631B Local Cabinet Pnl
8631G UPS with Battery Set
8632 SCADA System
8632A Central Cabinet Pnl
8632B Local Cabinet Pnl
8632F Central Console Set
8632G UPS with Battery Set
Summary

8640 Other Communication System

8641 CCTV System INSTALLED INSIDE E-CONTAINER


8641A Central Cabinet Pnl 1.00 20.70 144.80 2,997.36 - - 3,608.23 4,024.54 10,630.13 10,630.13 CCTV AND ACS SYSTEM COMMON
CABINET
8641B Desk Top Type Operation Console Set 1.00 5.18 144.80 750.06 - - 902.93 1,007.11 2,660.10 2,660.10 CCTV AND ACS SYSTEM COMMON
WORKSTATION
8641C Monitor Set 1.00 5.18 144.80 750.06 - - 902.93 1,007.11 2,660.10 2,660.10 CCTV AND ACS SYSTEM COMMON
WORKSTATION
8641D Camera Set 8.00 82.80 144.80 11,989.44 - - 14,432.92 16,098.17 42,520.54 5,315.07

8642 Gate Control System


8642A Sliding Gate Set
8642B Traffic Barrier Set
8642C Turn Stile Set

8643 Security System


8643A Central Cabinet Pnl 0
Included in CCTV Cabinet
8643B Local Equipment Set
8643C Monitor/Display Set 0 Included in CCTV monitor
8643D Sensor Cables M 0 Deleted. For fence security w/c is not
reqd.
8643E Door Unit - Access Control Set 4.00 12.00 144.80 1,737.60 - - 2,091.73 2,333.07 6,162.40 1,540.60 Installed inside E-Container
8643G UPS with Battery Set

8650 Steel Material for support of Telephone, Speaker, Camera, Local Amp Box kg

Summary

8660 Cabling
8661 Metal Cable
8661A 2C-2.5+E 2C-4+E M 766.00 199.16 144.80 28,838.37 35.84 27,453.44 34,715.71 38,721.16 129,728.68 169.36 For CCTV Power Cable
8661B 2P-1.5 M 0 Deleted. CAT 6 will be utilized for
ACS
CAT6 M 200.00 60.00 144.80 8,688.00 - - 10,458.64 11,665.34 30,811.98 154.06 4 x DOOR (50m length per door)
8662 Fiber Optic Cable
8662A SM 6-Core SM 4-Core M 766.00 245.12 144.80 35,493.38 - - 42,727.03 47,656.81 125,877.22 164.33 CCTV signal cable
8662B SM 12-Core M
M
Summary

8670 Termin/Splic. of Cable


8671 Termination
8671A Metal Cable Pnt 46.00 190.44 144.80 27,575.71 76.16 3,503.36 33,195.72 37,025.80 101,300.59 2,202.19 16 ACS device (CAT6) + 7 cameras x
2 ends
8671B Fiber Optic Cable Core 56.00 380.80 144.80 55,139.84 627.20 35,123.20 66,377.50 74,036.04 230,676.58 4,119.22 7 cameras x 4 cores x 2 ends

8672 Splicing
8672A Metal Cable Pnt
8672B Fiber Optic Cable Core
Summary

8680 Cable Way


8681 Cable Ladder Tray & Cover
8681A 150W M
8681B 300W M
8681C 450W M
8681D 600W M
8681E 750W M
8681F 900W M
8681G 1200W M
8681H OTHERS M
8681J 150W (COVER) M
8681K 300W (COVER) M
8681L 450W (COVER) M
8681M 600W (COVER) M
8681N 750W (COVER) M
8681O 900W (COVER) M
8681P 1200W (COVER) M
8681Q OTHERS M

8682 Cable Ladder Tray Support


8682A For Main Cable Ladder Tray w/o CIVIL support Kg
8682B For Branch Cable Ladder Tray w/o CIVIL support Kg

8683 Conduit Piping for Conduit Wiring System


8683A Rigid Metal Conduit
8683Aa 1/2" M
8683Ab 3/4" M
8683Ac 1" M
8683Ad 1-1/2" M
8683Ae 2" M
8683Af 2-1/2" M
8683Ag 3" M
8683Ah 4" M
8683Ai 5" M
8683Aj 6" M
8683B Rigid PVC Conduit
8683Ba 2" M
8683Bb 3" M
8683Bc 4" M
8683Bd 6" M
8683C Terminal and Pull Box Pcs
ÁUGUST 2023 LABOR MATERIAL EQUIPMENT OTHERS TOTAL COST BQ UNIT
FWBS CODE DESCRIPTION UNIT TOTAL MANHOURS Php/MH COST Php/BQ COST COST COST (12) COST REMARKS

(1) (2) (3) (5) (6) (7)=(5x6) (8) (9)=(4x8) (10) (11) =(7+9+10+11) (13)=(12)/(4)
8684D Steel Material for support of RSC above ground installation kg
Summary

8690 Other Work

8695 Cable Trench


8695A Excavation M3
8695B Sand Filling M3
8695C Back Filling M3
8695D Cable Protection Tile M2
8695E Cable Warning Sheet M2

8696 Cable Route Marker Pcs

8697 Pole and Mast


8697A Pole (up to 15M) Set
9697B Mast (above 15M) Set

869D Demolition of Equipment


869DA < see note 1 > Set
Summary

SUMMARY ( 8 6 0 0 )

8700 CATHODIC PROTECTION

8710 Impressed Current System


8711 Transformer-Rectifier Set
8712 Test Box, Bond Box, etc., Pcs

8713 Anode
8713A Rod Type without Boring Pcs
8713B Rod Type with Boring Pcs
8713C Ribbon/Line Type M
8714 Reference Electrode
8714A Reference Electrode without Boring Pcs
8714B Reference Electrode with Boring Pcs
8716 Cabling & Wiring M
8717 Splicing and Connection
8717A U/G Splicing Pnt
8717B Connection to Piping/Equipment Pnt

Summary

8720 Sacrificial Anode System


8722 Test Box, Bond Box, etc., Pcs
8723 Anode Pcs
8723A Rod Type without Boring Pcs
8723B Rod Type with Boring Pcs
8723C Ribbon/Line Type M
8724 Reference Electrode Pcs
8724A Reference Electrode without Boring Pcs
8724B Reference Electrode with Boring Pcs
8726 Cabling & Wiring M
8727 Splicing and Connection
8727A U/G Splicing Pnt
8727B Connection to Piping/Equipment Pnt

Summary
8790 Other Works

8793 Soil Access Box Pcs


8795 Cable Trench
8795A Excavation M3
8795B Sand Filling M3
8795C Back Filling M3
8795D Cable Protection Tile M2
8795E Cable Warning Sheet M2

8796 Cable Route Marker Pcs

8790 Other Work


879D Demolition of Equipment
879DA < see note 1 > Set
Summary

SUMMARY ( 8 7 0 0 )

8800 ELECTRICAL HEAT TRACING

8810 Heat Tracing Panel


8811 Heat Tracing Panel w/o miscellaneous foundation Set
8812 Heat Tracing Panel w/ miscellaneous foundation Set

8813 Steel Material for Support of Heater Panel Kg

8820 Heating Element


8821 Self Regulating Type M
Self Regulating Type (Pipe) M
Self Regulating Type (Inst) M
Self Regulating Type (MCHE) M
8822 MI Cable M
8823 MI Cable with Heat Transfer Compound M
8850 Local Equipment
8851 Junction Box Set
8852 Isolation Switch Set
8860 Cabling & Wiring M
8870 Termination of Cable & Wire Pnt

8890 Other Work


889D Demolition of Equipment
889DA < see note 1 > Set
SUMMARY ( 8 8 0 0 )

ELECTRICAL WORKS
SUMMARY ( 8 0 0 0 ) 28,621.39 4,158,478.93 4,511,399.87 4,989,013.19 5,564,638.71 19,223,530.71

< Note 1 > In cases where demolition of existing equipment is included in the work scope of JGC Phil.,
each item shall be clearly indicated in each general category or FWBS (8X9D)
and related work scope in SOW.

Reference: JPEP-0-1600-F-0012 rev 0


(Note that this document should be updated based on the latest version of equivalent JGC reference document)