TITLE PORTFOLIO
VILLA EL PANGUE ll PROJECT
HIGH BRIDGE
Page2 of 72
INTRODUCTION
This report corresponds to the final portfolio project, with which the student will qualify for
the Professional title of Construction Technician.
The project mainly seeks to study the parameters used in the construction of a residential
home with a minimum of 2 Floor Levels, for this, a Housing Complex will be used that is
made up of a total of 87 houses, located in the commune of Puente Alto.
The project called “El Pangue 2” is the second stage of homes built on the site, at the hands
of the BIO BIO Construction company, which is currently in the Post-Sale stage.
The study of this project will be limited in such a way as to be able to carry out the
calculations and analyzes involved in only one house unit. The purpose of this work is to
carry out an in-depth analysis of the different items involved in the materialization of the
home, focusing primarily on the general and specific objectives, based on the key subjects of
the degree, which will be essential to be able to complete each one of the requirements
established by the institution.
The technical and administrative content inserted in this report is supported by the Chilean
Standards, regulations and supreme decrees in force, as well as each of the procedures that
the student had to incorporate in the development of the degree portfolio.
Page3 of 72
4.- General background of the Project
4.1.-Diagnosis
The municipality of Puente Alto is one of the largest in the metropolitan region, with
an area of 88 km 2 .
Page4 of 72
This is why the construction of new housing projects within the commune becomes
essential, and construction companies focus their gaze on the present need, bringing
proposals that are within the reach of the most vulnerable families in the Metropolitan
Region.
The reactivation of social integration takes on an important role, and the different
government entities such as the Ministry of Housing and Urban Planning (MINVU),
are the ones who support this impulse and development of the country, through the
growth and increase in the construction of Social housing. Likewise, they make
various subsidies available to the most needy families to purchase a home.
The “El Pangue ll” Housing project carried out by the construction company BIO BIO,
is made up of 87 houses, semi-detached and semi-detached. Each one has
approximately 90m 2 of useful land, of which only 55.95m 2 are built.
Page5 of 72
The characteristics of the house are the following:
Generalities
The model associated with this housing complex is semi-detached, therefore, the
studio will be delimited in the manner designated in the attached image, framed
Page6 of 72
between axes 1-2 / AD, both on the 1st and 2nd floors. , which will be used for
control analyzes and execution of work.
5.- Objectives
Page7 of 72
5.1.-General Objective
Analyze the different processes and construction stages involved in the “El Pangue
ll” housing complex project, emphasizing and deepening the development of the key
subjects of the degree.
5.2.-Specific Objectives
Carry out the ordering of the construction processes, carrying out the
itemization of the project, complying with the methodological order expressed
in NCh 1156/of 1999.
Cube the amount of the different materials used in the construction of the
home, using NCh 353/of 2000.
6.1.-Methodological Framework
Page8 of 72
The methodological framework used in the project was separated into different
research stages that are intertwined and fully display the necessary information
needed to carry out and fulfill the General Objectives of the project.
We detail the stages below:
1st Investigate: It is the search for proposals that lead us to materialize the interests
of the career, through an existing project.
2° Select: verify that the characteristics of the project comply with those stipulated,
and allow us to work under optimal conditions.
3rd Site Visit: Corresponds to the action of investigating and finding the enabled
information channels, approaching the site of the selected project, where the
following data was obtained:
6.2.-Planning
For the planning process, the documentation obtained in the research process
should have been used to the maximum, generating an ITEMIZED of general items
Page9 of 72
for the work. (No Budget included) through the technical specifications of the Project
studied.
For this we rely on Chilean Standard 1156/of 1999 on Ordering and Designation of
Items.
Page10 of 72
Page11 of 72
After the organization in the general Itemization of the work, we worked with the
amounts of the project, giving rise to the cubations of the items that make the
construction of the home possible.
These calculations were executed through Excel spreadsheets, using architectural
plans and details of the home.
In this phase, Standard 535/of 2000 “Location for building works” was used as
support.
CUBICATION OF GAMES
Foundations
Page12 of 72
CUBICACIÓN EXCAVACIÓN FUNDACIONES
CUBICACIÓN RADIER
SUBTOTAL
LARGO ANCHO
EJES DESCRIPCIÓN (m3)
(L) (A)
Total m3 2,0
Masonry Beam
Page13 of 72
CUBICACIÓN MOLDAJE VIGA ALBAÑILERIA
LARGO ALTO SUBTOTAL
EJES
(L) (h) m2
EJE A ENTRE 2-3 1,835 0,25 0,459
EJE 2 ENTRE A-B 3,754 0,25 0,939
EJE 2-B 0,250 0,25 0,063
EJE 2 ENTRE B-C 1,004 0,25 0,251
EJE 2-C 0,750 0,25 0,188
EJE 2 ENTRE C-D 2,274 0,25 0,569
EJE D ENTRE 1-3 4,420 0,25 1,105
EJE 3 ENTRE A-D 6,878 0,25 1,720
TOTAL m2 5,29
Page14 of 72
CUBICACIÓN MOLDAJE PILARES
LARGO ALTURA SUBTOTAL
EJES
(L) (h) m2
PILAR 1 0,35 2,31 0,81 1ER Y 2DO PISO
PILAR 2 0,24 2,31 0,55 2DO PISO
PILAR 2a 0,30 2,31 0,70 1ER PISO
PILAR 3 0,20 2,31 0,46 2DO PISO
PILAR 4 0,57 2,31 1,32 2DO PISO
PILAR 5 0,660 2,31 1,52 1ER PISO
PILAR 6 0,200 2,31 0,92 2DO PISO
PILAR 7 1,013 2,31 2,34 1ER PISO
PILAR 8 0,754 2,31 1,74 1ER PISO
PILAR 9 0,342 2,31 0,79 2DO PISO
TOTAL m2 11,16
H° slab
Brickwork
Page18 of 72
Page19 of 72
CUBICACIÓN ENFIERRADURA ALBAÑILERIA
DIAMETRO LARGO DISTRIBUCIÓN CANTIDAD COEFIC. SUBTOTAL CANT. BARRA
DESCRIPCIÓN
(mm) (L) (cm) BARRAS KG/m. (KG) COMERCIAL
RASGOS VENTANAS 12 31,75 - - 0,888 28,19 5
ANTEPECHO VENTANA 10 3,25 - 2 0,617 4,01 1
ESTRIBOS 6 1,1 0,2 10 0,222 2,44 2
ESCALERILLAS 4,2 1,50 - 60 - - 15
TOTAL KG 34,65
CANT. TIRAS BARRAS 6 2
CANT. TIRAS BARRAS 10 1
CANT. TIRAS BARRAS 12 5
CUBICACIÓN ALBAÑILERIA
DESTO. VANOS
ALTO SUBTOTAL
DESCRIPCIÓN DESCRIPCIÓN YAGA TENDEL LARGO PUERTAS Y
(h) m2
VENTANAS
ELEV- EJE 3 LADRILLO ECHO A MAQUINA 9,4x15,4x32 0,01 0,01 5,8 6,878 0 40,02
1 Ladrillo
ELEV- EJE A LADRILLO ECHO A MAQUINA 9,4x15,4x33 0,01 0,01 5,8 3,828 5,1 17,23
Equivale a
ELEV- EJE D LADRILLO ECHO A MAQUINA 9,4x15,4x34 0,01 0,01 5,8 4,428 5,8 20,02
0,0288 m2
ELEV- EJE 1 LADRILLO ECHO A MAQUINA 9,4x15,4x35 0,01 0,01 5,8 6,878 1,717 38,30
TOTAL m2 115,57
TOTAL UN. LADRILLOS 4012,95
Interior partitions
Page20 of 72
CUBICACIÓN TABIQUES INTERIOR PRIMER PISO
DESCRIPCIÓN LARGO ALTO DINTEL SUBTOTAL m2
DORMITORIO 3 3,05 2,02 0,196 6,161
COCINA 1,37 2,02 0,196 2,7674
ESCALA 0,7 1,67 - 1,169
TOTAL m2 10,10
Ceiling
Page21 of 72
CUBICACIÓN CIELO 2° PISO
AREA
DESCRIPCIÓN
m2
DORMITORIO 1 13,52
DORMITORIO 2
15,46
BAÑO
TOTAL m2 28,97916
Cornices
Floor Covering
Overalls
Wall Covering
Ceiling Covering
Exterior facade
Page24 of 72
CUBICACION FACHADA EXTERIOR 1°PISO
Page25 of 72
CUBICACIÓN CERCHAS
ANCHO ESPESOR LARGO PULG PIN./ PERDIDA CANTIDAD SUBTOTAL
TIPO CERCHA descripción
(") (") ml PULG MAD. % uni. PULGADAS
pendolón 2 4 0,96 0,21333333 0,01493333 3 0,6848
Diagonal 1 4 0,96 0,10666667 0,00746667 6 0,6848
CERCHA C1 Montante 1 4 0,48 0,05333333 0,00373333 6 0,3424
Tirante 2 4 3,678 0,81733333 0,05721333 3 2,62364
Pierna o par 2 4 1,839 0,40866667 0,02860667 6 2,62364
pendolón 2 4Page260,836 0,18577778
of 72 0,01300444 6 1,192693333
Diagonal 1 4 0,84 0,09288889 0,00650222 12 1,192693333
CERCHA C2 Montante 1 4 0,418 0,04644444 0,00325111 12 0,596346667
Tirante 2 4 3,278 0,72844444 0,05099111 6 4,676613333
Pierna o par 2 4 1,639 0,36422222 0,02549556 12 4,676613333
pendolón 2 2 0,916 0,10177778 0,00712444 1 0,108902222
Montante 2 2 0,458 0,05088889 0,00356222 2 0,108902222
SOBRETABIQUE 1
Pendola 2 2 0,229 0,02544444 0,00178111 2 0,054451111
Tirante 2 2 3,678 0,40866667 0,02860667 1 0,437273333
Pierna o par 2 2 1,839 0,20433333 0,01430333 2 0,437273333
pendolón 2 2 0,916 0,10177778 0,00712444 1 0,108902222
Diagonal 2 2 0,916 0,10177778 0,00712444 2 0,217804444
Montante 2 2 0,458 0,05088889 0,00356222 2 0,108902222
Pendola 2 2 0,229 0,02544444 0,00178111 2 0,054451111
Tirante 2 2 3,678 0,40866667 0,02860667 1 0,437273333
Pierna o par 2 2 1,84 0,20433333 0,01430333 2 0,437273333
pendolón 2 2 0,836 0,09288889 0,00650222 1 0,099391111
Diagonal 2 2 0,836 0,09288889 0,00650222 2 0,198782222
Montante 2 2 0,418 0,04644444 0,00325111 2 0,099391111
Pendola 2 2 0,209 0,02322222 0,00162556 2 0,049695556
Tirante 2 2 3,278 0,36422222 0,02549556 1 0,389717778
Pierna o par 2 2 1,639 0,18211111 0,01274778 2 0,389717778
TOTAL PULGADAS 23,25
TOTAL 2"x4" 16,48
TOTAL 1"x4" 2,82
TOTAL 2"X2" 3,96
CUBICACIÓN COSTANERAS
ANCHO ESPESOR LARGO PULG PIN./ PERDIDA CANTIDAD SUBTOTAL
EJES DESCRIPCIÓN
(") (") ml PULG MAD. % uni. PULGADAS
ENTRE 1-3/ ENTRE A-B COSTANERAS 2 2 4,428 0,492 0,03444 5,37 2,828967738
ENTRE 1-3/ ENTRE B-D COSTANERAS 2 2 3,6 0,4 0,028 6 2,580629508
TOTAL 2"X2" 5,41
CUBICACIÓN CUBIERTA
AREA
DESCRIPCIÓN PENDIENTE LARGO ANCHO
m2
SECCIÓN 1 40,00% 4,828 1,537 7,4
SECCIÓN 2 40,00% 3,2 4,155 13,3
SECCIÓN 3 TRIANGULO 40,00% - - 2,36
SECCIÓN 4 SEMI-TRIANGULO 40,00% - - 1,181
SECCIÓN 5 EXCEDENTE 40,00% 1,404 0,4 0,5616
TOTAL m2 24,8
Page27 of 72
CUBICACIÓN PUERTAS 1° PISO
DESCRIPCIÓN TIPO ALTO ANCHO UN. SUBTOTAL m2
ACCESO PRINCIPAL PV1 2,02 0,8 1 1,616
DORMITORIO 3
P1 2,02 0,7 2 2,828
ENTRADA COCINA
SALIDA COCINA PV2 2,02 1,35 1 2,727
TOTAL m2 7,171
CUBICACIÓN VENTANAS
DESCRIPCIÓN TIPO ALTO ANCHO UN. SUBTOTAL m2
1,581 7,24 1 11,4
LIVING/ COMEDOR v1
1,581 0,25 2 0,79
DORMITORIO 3 V2 1,07 1,011 1 1,08177
DORMITORIO 1 V3 1,23 1,835 1 2,25705
DORMITORIO 2 V4 1,07 1,355 1 1,44985
BAÑO V5 0,6 0,845 1 0,507
TOTAL m2 17,5
GANTT CHART
Finally, in planning, one of the computer tools available for optimal administration
and control of work was used, which is Microsoft Project, where our time scale called
GANTT CHART was created.
Page28 of 72
Remember that this schedule is a time estimate, and may be modified and/or
altered, according to the needs of the work and eventualities.
The estimated duration for the construction of the home is 30 Business Days.
Page29 of 72
Page30 of 72
Page31 of 72
Page32 of 72
7.- Project execution and control
Page33 of 72
In the execution of the Project, the most relevant construction processes will be
named step by step, and the work derived from each item in the realization of the
home from its preliminary stage.
PREVIOUS WORKS
Installation of tasks
Provisional Closure
It includes the construction of all temporary facilities, such as fences, warehouses,
installation of temporary drinking water, sewage and electricity services, offices,
dining rooms and bathrooms and whatever is necessary for the proper functioning of
the work.
The delimitation of the project, on the other hand, is a fundamental point, since the
temporary closures provide security and protection, not only for the interior of the
work, but also for those adjacent to its surroundings, mitigating noise, contamination
and pollution. generated by the different works carried out.
Page34 of 72
Cleaning and escarpment
Machetes
Shovel
Forklift truck
Rake
Pillory
The machinery used for cleaning was:
Excavators
Dumpers
Front loader
Hopper truck (removal of surplus and debris)
Leveling
Page35 of 72
In leveling natural terrain, topographic instruments are available,
Which will take readings in situ to generate a survey of the area to be built and
obtain the construction level of the project.
Resources:
Tachymeter
Tripod
reading sight
Lead
Measuring tapes
Safety helmet
safety shoes
Land Leveling
FOUNDATION EXCAVATION
Page36 of 72
Once the terrain layouts have been made, excavation must be done until reaching
the excavation seal specified on the plans. The seal will be received by the engineer
specializing in soil mechanics, it must be horizontal with a tolerance of +- 1% slope.
The excavation of the trenches is carried out according to the layout, respecting the
widths and depths indicated on the plans. (This must be executed by hand.)
Resources:
• Chuzo
• Shovel
• Forklift truck
• Pillory
Foundation Excavation
FOUNDATIONS
Page37 of 72
Foundation
Overlays
In accordance with the structural plan, respecting dimensions and type of concrete
indicated. The concrete is mixed taking the necessary precautions to avoid collapses
and deformations in the excavations.
The foundations will be in accordance with structural plans, respecting dimensions
and type of concrete and reinforcement. Special care will be taken to ensure that
rainwater from the land runs off and does not affect the building.
The concrete will contain water-repellent or some material that reduces permeability.
Concrete Characteristics
With the update of the Chilean standard 170/ of 2016, the characteristics of the
concrete used for the foundation and foundations are as follows:
Nomenclatures
G10 foundation concrete (90)
Concrete Surfacing G20 (90) 20 10
These structural elements will be concreted with premixed concrete brought from the
concrete plant, being cast through a basket and descent chute or wheelbarrow
manually. It must be carried out accompanied by correct vibrating and curing of the
concrete with the wet membrane method.
Page38 of 72
foundation concreting
Radier
Gravel bed measuring e = 8 cm will be placed on the interior compacted fill. Leveled
and compacted appropriately to receive the concrete with a radier e = 7cms.
Radier Concreting
Note: All concrete used in the work must be tested. The way to control that the
concrete on site meets the required specifications and conditions will be through the
Abrams cone and through temperature.
Page39 of 72
BRICKWORK
The Masonry walls will be made with machine-made brick measuring 32 X 15.4 X 9.4
and their reinforcements will be according to plans.
brick masonry
Constructive process
Page40 of 72
After concreting the foundation, in this case the Masonry beam, the rows of bricks
must be glued with mortar, considering the installations and the structural
requirements of the reinforcements, expressed in the structure plans.
The masonry of the house is of the Confined type, so it must be advanced in parallel
with the columns of concrete pillars, which are tied or intertwined with each other.
The crowning of the wall consists of tying the chain and subsequent concreting,
where the Concrete slab is also considered. The verticality of the walls must be
taken care of, avoiding collapse. The previous steps will be repeated until reaching
the 2nd level of the home.
MORTAR
Page41 of 72
The characteristics of the adhesive mortar for the masonry of the home are the
following:
glue mortar
Rehearsal
Three samples must be taken in test tubes from the ground for laboratory testing, to
which compression will be applied. By analyzing the rupture results of each one, it
will be possible to verify whether the mortar is appropriate and meets the
requirements of the project.
Press essays
STRUCTURE ARMORS
Page42 of 72
They will be executed in strict accordance with what is indicated in the plans,
specifications and calculation report, in relation to shape, dimensions, location, type
and quality of the elements that make them up.
The reinforcing bars will be made of steel quality A-630-420-H or higher, except for
the bars with a diameter of 6, which may be smooth with the nomenclature A-440-
280-H, according to NCH 204 according to the report and calculation drawings. The
steel must be of national origin.
Steel of different types may not be used in the same structural element. The use of
steel of the same grade and different origin must be authorized by supervision, with
prior consultation with the Calculator. Steel from other origins must have quality
certification and reports from authorized organizations.
They must be made of wood and their placement will be done in such a way as to
ensure their absolute non-deformability from the moment of assembly until the
removal of the structure.
Plumbing will be installed considering the permanent supervision of the field
professional.
The anchoring elements and/or installations that will be incorporated or embedded in
the resistant concrete structures must be placed in the formwork.
The formwork that will be used must guarantee a smooth surface free of
imperfections. When the formwork is used repeatedly, care must be taken to keep its
surface clean and smooth, eliminating and removing all those protuberances caused
by the concrete. This task will be carried out in order to achieve a smooth surface on
facades, interior walls and slabs.
Slab molding
Pillar Molding
Page43 of 72
The characteristics of the Concrete Pillars and slab according to the project are the
following:
Nomenclature
Given the Update of the Chilean standard 170/ of 2016, the characteristics would be
the following:
G20 (90) 20 10
Slab Concreting
INTERIOR PARTITION
Page44 of 72
They will be based on galvanized steel profiles and plasterboard sheets, finished
thickness 75 mm.
The profiles will be made of galvanized steel, uprights in tabigal type C profiles of
38x38x8x0.85 mm spaced from the axis approximately every 0.4 m and a lower and
upper sill of 39x20x0.5 mm. For assembly, the manufacturer's instructions must be
strictly considered, using the appropriate profiles, corners, sills, diagonals and
uprights, etc. The coating will be on one side in 10 mm thick ST cardboard gypsum
board and on the other side in 10 mm ST cardboard gypsum board, however in the
wet areas of the home such as the bathroom they will be covered with plaster
boards. 12.5mm thick moisture resistant cardboard.
The joint of the plates will be invisible with Joint Guard tape and suitable glue along
the entire joint. Metal corners are also contemplated.
Interior partitions
Page45 of 72
Ceilings are consulted in 10 mm plasterboard-cardboard sheets, with an invisible
joint with a Joint Guard type tape or similar and base putty, under a wooden
structure.
The placement of isolanglass in bulk free roll of 80mm thickness, placed on the
ceilings, is consulted.
The area where the Comuna Puente Alto home will be located corresponds to
number 3.
(*) According to the NCh 2251 standard: R100 = value equivalent to Thermal Resistance (m2K/W) x 100
INTERIOR COVERINGS
Page46 of 72
White latex coating on ceiling
Floor Covering
Page47 of 72
Ceramic Floor Bathroom
Exterior facade
ROOF STRUCTURE
Page48 of 72
DECK
Page49 of 72
Covered fiber cement sheet
Page50 of 72
Doors and windows
SANITATION
Page51 of 72
1. Technical specifications
Page52 of 72
1.0) Calculation of Maximum Daily Consumption (C):
ENDOWMENT:
LIVING PLACE
350 lt/room/day*5 rooms
Supply = 1750
lt/day
Page53 of 72
QMP = 1.7391* QI^ 0.6891
Where:
QI: Installed expenditure in L/min.
QMP: Probable maximum flow rate in L/min.
13 3 50
19 5 80
25 7 117
38 20 333
Have:
J = 15mca – (3.38 mca + 4 mca + (4.1m))
J = 3.52 mca
Therefore, if we lose more than 3.52 mca in the circuit that reaches the most
unfavorable device, we would have problems with its supply.
Page54 of 72
Artifacts and flows
PRESION 15 MCA
Meter diameter
MEDIDOR 19mm
Page55 of 72
COLD WATER PLANTS
Page56 of 72
Presion inicial (m.c.a) 15 Diametro medidor 19mm K = medidor 3,380 3,38
AGUA FRIA
Gasto Gasto Diametro Diametro Perdida de Carga llave Perdida Cota
Longitud
Material Velocidad cant. coeficiente coeficiente comp de Artefact Presión
Instalado Maximo Nominal Interior Unitaria En el tramo abier carga o
TRAMO Singularidad
Ql QMP D V
(m) (int) J J*l n k k opcional Js (m) m.c.a.
(L/min) (L/min) (mm) (m(s)
(m/m) (m/m) total (m.c.a.)
Matriz 15
. 0 0
Medidor de Agua Potable 75 3,38 11,62
. 0 0
1-2 Curva de 45 1 0,2
75 34,07 14,14 tipo PN-10 PP25 (3/4) 20,40 1,737 0,195 2,7510 T, salida bilateral 1 1,8 2,40 0,00 0,37 0,00 8,50
Ll paso
curva de 90 1 0,4
2-3 Lv 15 11,24 0,66 tipo PN-10 PP25 (3/4) 20,40 0,573 0,028 0,0184 codo de 90 1 0,9 1,10 0,00 0,02 1,00 10,58
Valvula de bola de paso estandar 1 0,2
2-4 60 29,22 1,46 tipo PN-10 PP25 (3/4) 20,40 1,490 0,149 0,2170 T, paso directo 1 0,6 0,60 0,00 0,07 0,00 8,21
Subida Calefon . 0 0
4-5 Lp 12 9,64 2,64 cu13 (1/2) 14,46 0,978 0,109 0,2889 T, salida lateral 1 1,3 1,50 0,00 0,07 0,80 7,34
CALCULATION TABLE BY SECTIONS
Page57 of 72
7-8 Bo 33 19,35 0,90 cu19 (3/4) 20,60 0,968 0,069 0,0621 Valvula de bola de paso estandar 1 0,2 2,90 0,00 0,14 2,00 6,01
codo de 90 1 0,9
8-9 Wc 18 12,74 0,58 cu13 (1/2) 14,46 1,293 0,178 0,1035 Valvula de bola de paso estandar 1 0,2 1,10 0,00 0,09 0,40 5,42
codo de 90 1 0,9
9-10 Lo 8 7,29 0,52 cu13 (1/2) 14,46 0,740 0,067 0,0349 codo de 90 1 0,9 1,10 0,00 0,03 0,80 4,55
Valvula de bola de paso estandar 1 0,2
HOT WATER PLANTS
Page58 of 72
Presion inicial (m.c.a) 8,39 Diametro medidor 19mm K medidor 3,38
AGUA CALIENTE
Gasto Gasto Diametro Diametro Perdida de Carga
llave comp
Longitud Material Velocidad cantidad coeficiente coeficiente Perdida de carga Cota Presion
abier
TRAMO Instalado Maximo Nominal Interior Unitaria En el tramo Singularidad
Ql QMP D V J k
2. Sewage facilities
(m) (int) n k opcional (m) m.c.a.
(L/min) (L/min) (mm) (m(s) (m/m) J*l (m/m) total Js (m.c.a.)
Calefon 50
Bajada 50 25,77 0,00 tipo PN-10 PP25 (3/4) 20,40 1,31 0,10 0,00 codo de 90 1 0,9 0,90 0,00 0,08 1,20 8,39
Calefon . 0 0
T, salida bilateral 1 1,8
1-2 50 25,77 0,40 tipo PN-10 PP25 (3/4) 20,40 1,31 0,10 0,04 . 0 0 1,80 0,00 0,16 0,00 8,19
. 0 0
curva de 90 1 0,4
2-3 Lv 15 11,24 0,94 tipo PN-10 PP25 (3/4) 20,40 0,57 0,02 0,02 Valvula de bola de paso estandar 1 0,2 1,50 0,00 0,03 1,00 7,15
codo de 90 1 0,9
2-4 Lp 12 9,64 1,12 cu13 (1/2) 14,46 0,98 0,09 0,10 codo de 90 1 0,9 1,10 0,00 0,05 0,80 6,19
Valvula de bola de paso estandar 1 0,2
2-5 23 15,09 0,00 tipo PN-10 PP25 (3/4) 20,40 0,77 0,04 0,00 curva de 90 1 0,4 0,40 0,00 0,01 4,10 4,08
sube a 2° piso . 0 0
curva de 90 1 0,4
Page59 of 72
5-6 Bo 15 11,24 0,58 cu13 (1/2) 14,46 1,14 0,12 0,07 0,60 0,00 0,04 2,00 6,09
Valvula de bola de paso estandar 1 0,2
6-7 Lo 8 7,29 1,40 cu13 (1/2) 14,46 0,74 0,05 0,08 curva de 90 1 0,4 0,60 0,00 0,02 0,80 5,19
Valvula de bola de paso estandar 1 0,2
SEWER PLANTS
UEH CALCULATIONS
Page60 of 72
ARTEFACTO LONGITUD PENDIENTE DIAMETRO
DESCARGA PENDIENTE DIAMETRO
TRAMO OBS. QUE TRAMO MINIMA MINIMO
DESCARGA
m UEHs % mm % mm
Baño tina; WC; Lavamanos;
1-2 6,17 16 3%
lavadero;Lavaplatos;lavadero interior 110 3% 110
Baño tina; WC; Lavamanos;
2-3 0,95 13 3%
lavadero;Lavaplatos 110 3% 110
3-4 Baño tina; WC; Lavamanos;lavadero 1,16 10 3% 3% 110
4-5 Lavadero 0,9 3 3% 50 3% 50
Descarga
4-6
Vertical Baño tina; WC; Lavamanos 2,7 7 - 110 - 110
hacia 1° Piso
6-7 Baño tina; WC; Lavamanos 0,56 7 3% 110 3% 110
7-8 Lavamanos;WC 0,7 4 3% 110 3% 110
8-9 Lavamanos 0,7 1 3% 40 3% 40
Page61 of 72
ASSESSMENT
In the cubing stage we showed that the continuous foundation did not have
reinforcement, something that undoubtedly improves its characteristics and
structural behavior.
Thermal insulation of interior partitions was not included in the project. One of
the important factors in the comfort of the home.
The Sanitary facilities comply with the conditions indicated in the RIDAA.
Planning was a very important step within the construction process of the
home, since it allowed us to project the expected results and create an
efficient work methodology.
RESULTS
The Project complies with the quality standards required by the OGUC and
current Chilean regulations in each of the committed stages.
The “El Pangue ll” Housing complex benefits 87 families within the
Metropolitan Region.
Page62 of 72
CONCLUSIONS
With respect to the topics addressed in this portfolio, we can highlight that each of
the technical and practical aspects of the demands imposed by the institution were
included, obeying what was specified in the key subjects of the degree:
Cubage
Work planning and control
Concrete
Sanitation
Add that the rough construction stage is the most important of all, from the
construction side, since it provides us with the rigid framework of the structure and is
the supporting base of the home, in addition, add that brick masonry is the material
predominant.
REFLECTIONS
I think that the work carried out personally has been quite a challenge, accepting that
I would have liked to have been able to experience a site visit even in the
construction stage.
The important thing about this process is the enormous effort and self-demonstration
of the capabilities that as a professional I possess to approach a project, only with
the available tools.
The performance and technical use in the different problems present, the creativity,
elaboration and results in the activities and tasks associated with the stage of
planning, control and construction processes of the home, have given me conviction
and confidence.
Thanks to DUOC I have achieved my objectives, now it remains to demonstrate my
acquired skills and competencies, inserted in the construction world of work.
10.-Bibliography
Page63 of 72
Nch 353/of 2000
Nch1156/of 1999
Nch 170/of 2016
11.- Annexes
Page64 of 72
Definitive Acceptance Certificate of Building Works