JAROGA CONSTRUCTIONS GEMA CONSTRUCTION , PROJECTS v TECHNICAL CONSULTANCY

PROP. ING. JAVIER RODRIGUEZ GARRIDO


R.F.C. ROG/150696721 CU.R.P. ROGJ960615HOCDRVO9
CPINO SUAREZ my caí. REVOLUCION 96069 ACAYUCAN VERACRuZ
TEL: 9241366848 EMAIL: pavier.rodgarrido(G mail.com

CONCEPT CATALOG
WORK CONSTRUCTION OF A HOUSE
LOCATION C. PINO SUAREZ COL.REVOLUCION
MUNICIPALITY ACAYUCAN VERACRUZ
KEY CONCEPT UNIT QUANTITY P.UNIT AMOUNT
PA PRELIMINARY
CLEANING AND UPROOTING OF FLAT LAND BY HAND,
PA-001 INCLUDING: PILE OF MATERIAL ON SITE AND HAULING TO THE M2 75.95 $ 19.25 $ 1,462.04
FIRST 20.00 M STATION.
CLEARING OF NATURAL SOIL BY ANY MEANS, WITH AN
AVERAGE THICKNESS OF 10 CM. INCLUDES: LOADING AND
PA-002 HAULING OF PRODUCT OFF SITE, LABOR, TOOLS AND M2 75.95 $ 20.23 $ 1,536.47
EQUIPMENT.
LAYOUT AND LEVELING OF BUILDINGS ESTABLISHING
DEFINITIVE REFERENCES, WITH TOTAL STATION. INCLUDES:
QUALIFIED TECHNICAL PERSONNEL, STAKES, BOUNDARY
PA-003 MARKERS, INTERAXIS LOCATION, LEVEL BENCHES, MARKING M2 75.95 $ 6.76 $ 513.42
MATERIALS, EQUIPMENT, TOOLS AND LABOR.

CB FOUNDATION
HAND EXCAVATION IN DRY MATERIAL STOCKPILES TYPE II,
DEPTH FROM 0.00 TO 2.00 M., INCLUDES: SLOPE AND BOTTOM
CB-001 FINE TUNING, LABOR, TOOLS AND NECESSARY EQUIPMENT. M3 14.33 $ 180.50 $ 2,586.57

5 CM. INSOLE. OF CONCRETE THICKNESS MADE ON SITE


F'C=100 KG/CM2.MAXIMUM AGGREGATE 3/4", INCLUDES:
CB-002 HAULING TO FIRST STATION AT 20.00 M., MATERIAL, LABOR, M2 63.74 $ 109.23 $ 6,962.32
TOOLS AND NECESSARY EQUIPMENT.
DISTRIBUTION CHAIN OF 25X20 CM SECTION WITH 10 CM
CHAMFER OF CONCRETE MADE ON SITE F'C=250 KG/CM2
REINFORCED WITH ARMEX 15X30-4; INCLUDES: FALSEWORK,
CB-003 FALSEWORK, COMMON FINISHING, LABOR, NECESSARY ML 34.50 $ 234.50 $ 8,090.25
EQUIPMENT, MATERIALS, HAULING TO FIRST STATION AT 20.00
M.
25X20 CM SECTION CENTRAL SECTION CHAIN WITH 2
CHAFLANES OF 10 CM OF CONCRETE MADE IN WORK F'C=250
KG/CM2 REINFORCED WITH ARMEX 15x30-4; INCLUDES:
CB-004 CIMBRA, DECORATION, COMMON FINISHING, LABOR, ML 26.20 $ 242.65 $ 6,357.43
NECESSARY EQUIPMENT, MATERIALS, DRAWING TO FIRST
STATION AT 20.00 M.

FOUNDATION FLOORING, WITH 10 CM PERALT, REINFORCED


WITH 6X6 ELECTROSOLDABLED MESH TOP RIGHT-LEAF
REINFORCEMENT AND No. 3(3/8") OF 75 CM LENGTH,
CB-005 CONCRETE F'C=250KG/CM2 MAXIMUM AGGREGATE 3/4"; M2 72.42 $ 923.67 $ 66,892.18
INCLUDES: MATERIAL, LABOR, TOOLS AND NECESSARY
EQUIPMENT.

ALB MASONRY

BLOCK WALL OF 15 X 20 X 40 CM. IN 15 CM. OF THICKNESS


ALB-001 WITH 1:5 CEMENT-SAND MORTAR, INCLUDING: MATERIAL, M2
LABOR, TOOLS AND NECESSARY EQUIPMENT.

15 X 15 CM. SECTION CASTLE, CONCRETE F'C=250 KG/CM2. 3/4"


MAXIMUM AGGREGATE, REINFORCED WITH 4 No. 3 ( 3/8" ) and
No. 3 ( 3/8" ) and No. 3 ( 3/8" ) and No. 3 ( 3/8" ) and No. 3 ( 3/8 2
ALB-002 ML
EVERY 20 CM, INCLUDES: 2-SIDED COMMON FORMWORK,
FALSEWORK, MATERIAL, LABOR, TOOLS AND NECESSARY
EQUIPMENT.
JAROGA CONSTRUCTIONS". CONSTRUCTION IN GENE RAL, PROJECTS v TECHNICAL ADVICE
PROP. ING. JAVIER RODRIGUEZ GARRIDO
R.F.C. ROGI 150696 721 CU.R.P.ROGJ960615HOCDRVO9
CPINO SUAREZ 101 COI. REVOLUCION 9606-9 ACAYUCAN VERACRuZ
TEL: 9241366848 EMAIL: pavier.rodgarrido(Gmail.oom

CASTLE FLOODED IN BLOCK CELL 15X20X40 CM FILLED WITH


CONCRETE F'C=250KG/CM2 MAXIMUM AGGREGATE 3/4",
ALB-003 ML
REINFORCED WITH 1 No.3 (3/8") ROD, INCLUDING MATERIAL,
LABOR, TOOLS AND EQUIPMENT NECESSARY.

15 X 20 CM. SECTION ENCLOSURE CHAIN, CONCRETE F'C=250


KG/CM2. 3/4" MAXIMUM AGGREGATE, REINFORCED WITH 4 No. 3
ALB-004 ( 3/8" ) No. STRIPS 2 EVERY 20 CM, INCLUDES: 2-SIDED ML
COMMON FORMWORK, FALSEWORK, MATERIAL, LABOR, TOOLS
AND NECESSARY EQUIPMENT.

FLAT SLATE ON STRUCTURE, 10 CM. BEARING, COMMON


CIMBERS REINFORCED WITH No.3 (3/8") RODS @20CM IN BOTH
DIRECTS WITH BAYONETAL AT 1/4 OF THE CLARO LENGTH AND
ALB-005 ANCHOR HOOKS AT THE PERIMETER OF THE WALLS, M2
CONCRETE F'C = 250 KG/CM2. MAXIMUM 3/4" AGGREGATE,
INCLUDES: MATERIAL, LABOR, TOOLS AND NECESSARY
EQUIPMENT.
ACA FINISHES

COMMON PLASTERING IN SOFFITS WITH CEMENT-SAND


ACA-001 MORTAR 1:5, AVERAGE THICKNESS 2 CM, INCLUDES: M2
MATERIAL, LABOR, TOOLS AND NECESSARY EQUIPMENT.

COMMON PLASTERING ON PLUMB AND SCREED WALLS WITH


CEMENT-SAND MORTAR 1:5, AVERAGE THICKNESS 2 CM,
ACA-002 M2
INCLUDES: MATERIAL, LABOR, TOOLS AND NECESSARY
EQUIPMENT.

FLATTENING OF ONE EDGE WITH CEMENT-SAND MORTAR 1:5,


ACA-003 INCLUDING: MATERIAL, LABOR, TOOLS AND NECESSARY ML
EQUIPMENT.

FINE CEMENT-SAND MORTAR 1:5, OF 3 CM. THICKNESS,


ACA-004 POLISHED FINISH, INCLUDES: MATERIAL, LABOR, TOOLS AND M2
NECESSARY EQUIPMENT.

SUPPLY AND INSTALLATION OF DOORS OF 1.90M X 0.90M, WITH


ACA-005 ALUMINUM FRAMES AND ALUMINUM DRUM, INCLUDES: PZA
MATERIALS, LABOR, TOOLS AND NECESSARY EQUIPMENT.

SUPPLY AND INSTALLATION OF DOORS OF 1.90M X 0.85M, WITH


ACA-006 ALUMINUM FRAMES AND ALUMINUM DRUM, INCLUDES: PZA
MATERIALS, LABOR, TOOLS AND NECESSARY EQUIPMENT.

SUPPLY AND INSTALLATION OF DOORS OF 1.90M X 0.75M, WITH


ACA-007 ALUMINUM FRAMES AND ALUMINUM DRUM, INCLUDES: PZA
MATERIALS, LABOR, TOOLS AND NECESSARY EQUIPMENT.

SUPPLY AND INSTALLATION OF 1.40M X 1.20M WINDOWS, WITH


ACA-008 NATURAL ALUMINUM FRAMES AND GLASS WINDOWS, PZA
INCLUDING: MATERIALS, LABOR, TOOLS AND EQUIPMENT.

SUPPLY AND PLACEMENT OF PIGEON BREAST PARAPET,


ACA-009 INCLUDING: HAULING TO 1A. STATION 20.00 M., INCLUDES: ML
MATERIAL, LABOR, TOOLS AND NECESSARY EQUIPMENT.

SUPPLY AND APPLICATION OF VINYL PAINT ON WALLS AND


ACA-010 CEILINGS WITH FINE MIXTURE UP TO 4.00 M. HEIGHT, M2
INCLUDES: ONE COAT OF SEALER AND TWO COATS OF PAINT.
"JAROGA CONSTRUCTIONS"
TO CONSTRUCTION IN GENERAL SUPPLIES * TECHNICAL ADVICE
P PROP. ING. JAVIER RODRIGUEZ GARRIDO
R.F.C. ROG/150696721 C.U.R.R ROGJ960615HOCDRVO9
) CPINO SUAREZ 101 COL. REVOLUCION 96069 ACAYUCAN VERACRuZ
yLTEL : 9241366848 EMAIL: pavier.rodgarrido(G mail.com

SUPPLY AND APPLICATION OF WATERPROOFING ON ROOF


ACA-011 WITH FESTER MEMBRANE OR SIMILAR, WITH SEAL, INCLUDING: M2
MATERIAL, LABOR, TOOLS AND NECESSARY EQUIPMENT.

SUBTOTAL $ 94,400.67
VAT $ 15,104.11
TOTAL $ 109,504.78
ELABORATED: Vo.Bo:

JAVIER RODRIGUEZ GARRIDO

REMARKS: