Work Flow

Study: Opportunities for Improvement: Lives Saved by Getting Patients with


Acute MI to Goal Therapy as Fast as Possible
Time
Task Responsibility
Estimate

Duke investigator and Clinetic to collaborate on


Develop protocol for IRB ~ 2-3
developing the protocol. Clinetic to submit to
submission and approval months
central IRB if that approach is deemed optimal.

Clinetic to perform feasibility analysis. Clinetic to


Site feasibility analysis
collaborate with Amgen and Duke investigator on ~2-4
(beyond DUHS) and site
site selection. Clinetic responsible for site months
contracting
contracting

Define detailed Clinetic to lead and facilitate the process. Amgen


~ 1-2
requirements for Clinetic and Duke investigators to provide input and
months
dashboard approve the final design.

Contracting with health ~ 2-3


Clinetic responsible
systems months

Clinetic to work with the health system IT groups to


Establish EHR data ~ 2-3
establish the EHR data feeds required for the
feeds months
dashboard and analysis.

Design and develop the


Clinetic responsible for building dashboard ~ 2 months
Clinetic dashboard

Develop report of Duke investigators to lead with support from ~ 1-2


findings Clinetic months

Clinetic on point for end-to-end project execution


Project
Project Management including managing project milestones and
duration
timelines

~ 12 -18
Total Note: Some items can be worked on in parallel
months