Professional Documents
Culture Documents
Budget For Multifamily Housing With 5 Floors Semi-Basement
Budget For Multifamily Housing With 5 Floors Semi-Basement
Budget
0102004 Multifamily Housing Construction Santa Sofia, San Isidro District, Province and Department of Lima
JOSA SAC Real Estate 1/21/2018
LIMA - LIMA - LIMA
STRUCTURES 249,969.02
PRELIMINARY WORKS
CLEANING DURING THE EXECUTION OF THE WORK glb 1.00 9,600.00 9,600.00
PROVISIONAL WORKS 0.00
EXCAVATIONS 0.00
HAND COMPACTED FILLING WITH OWN MATERIAL IN FOUNDATIONS m3 67.98 51.70 3,514.84
FOOTWEAR 0.00
CONCRETE f´c = 210 kg/cm2 FOR REINFORCED FOUNDATION m3 66.41 67.83 4,504.72
CONCRETE f´c = 280 kg/cm2 FOR REINFORCED FOUNDATION m3 9.43 68.00 641.24
CONCRETE f´c = 210 kg/cm2 FOR RETAINING WALL m3 38.36 177.18 6,796.78
CONCRETE f´c = 210 kg/cm2 FOR FOUNDATION BEAM m3 6.34 75.25 477.07
PREMIX CONCRETE f'c=280 kg/cm2 FOR ELEVATOR PIT m3 9.72 252.80 2,457.22
COLUMNS 0.00
PLATES 0.00
BEAMS 0.00
PREMIX CONCRETE f'c=210 kg/cm2 FOR SOLID SLAB m3 31.73 15.70 498.29
PREMIX CONCRETE f'c=210 kg/cm2 FOR LIGHTWEIGHT SLAB m3 75.54 15.70 1,186.28
READY MIX CONCRETE f'c=210 kg/cm2 FOR MOORING COLUMN m3 9.00 31.68 285.12
SEVERAL 0.00
ARCHITECTURE 133,117.05
KK BRICK WALL MIX. C:A 1:4, TYPE IV, P. ROPE TAKING m2 1,587.96 20.50 32,551.83
PRIMARY STRIPING AND SCRATCHING OF EXTERIOR WALLS MIX. C:A 1:5. m2 15.87 11.53 183.02
PRIMARY STRIPING AND SCRATCHING OF INTERIOR WALLS MIX. C:A 1:5 m2 345.90 11.26 3,894.90
STAMPING ON INTERIOR WALLS SCRUBLED WITH MIXTURE. C:A 1:5 m2 2,834.10 11.26 31,912.53
STAMPING ON EXTERIOR WALLS RUBED WITH MIXTURE. C:A 1:5 m2 138.91 16.91 2,348.27
TAKING OF RETAINING WALLS WITH MIXTURE. C:A 1:5 m2 180.20 11.26 2,029.09
STAIR BOTTOM DRESS WITH MIX. C:A 1:5 m2 33.30 21.37 711.75
TAKING THE SIDE OF THE STAIR WITH MIX. C:A 1:5 m2 1.89 28.16 53.22
FLOORS 0.00
CONCRETE FLOOR f´c = 175 kg/cm2, E=15 CM, RUBBERED, SWEEP AND m2 288.86 9.05 2,613.56
BURNISHED FINISH
48mm CEMENT FLOOR BURNISHED POLISHED FINISH @10CM m2 35.77 20.07 718.01
CONCRETE RAMP f´c = 175 kg/cm2, E = 15 CM, BURNISHED SWEEP FINISH m2 32.51 9.05 294.15
OTHERS 0.00
SANITATION 20,918.10
PRELIMINARY WORK
COLD WATER
COLD WATER OUTLET WITH CLASS 10 PVC PIPE WITH 1/2" THREAD pt 32.00 57.46 1,838.59
COLD WATER OUTLET WITH CLASS 10 PVC PIPE WITH 3/4" THREAD pt 1.00 59.50 59.50
DISTRIBUTION NETWORKS
NETWORK ACCESSORIES
PVC ELBOW WITH 1/2" x 90º THREAD piece 2.00 16.74 33.47
PVC ELBOW WITH THREAD 3/4" x 90º piece 170.00 16.74 2,845.29
PVC ELBOW WITH THREAD 1" x 90º piece 8.00 16.74 133.90
PVC ELBOW WITH THREAD 1 1/2" x 90º piece 3.00 16.74 50.21
PVC REDUCTION WITH 3/4" - 1/2" THREAD piece 137.00 16.74 2,292.97
PVC REDUCTION WITH THREAD 1 1/2" - 3/4" piece 5.00 16.74 83.69
MISCELLANEOUS PARTS
HOT WATER OUTLET WITH CLASS 10 CPVC PIPE WITH 1/2" THREAD pt 11.00 86.18 948.02
DISTRIBUTION NETWORKS
NETWORK ACCESSORIES
CPVC ELBOW WITH THREAD 3/4" x 90º piece 37.00 16.74 619.27
CPVC TEE WITH 3/4" THREAD piece 6.00 16.74 100.42
SEVERAL
LIGHTING OUTPUTS
ELECTRICAL BOARDS
INTERCOM SYSTEM
SEVERAL glb
EARTHING SYSTEM und 4.00 700.00 2,800.00
===== ===============
SUBTOTAL 467,028.15
551,093.21]
Date: 01/21/2018 14:05:34 pm
ROOFED AREA ACCORDING TO LICENSE = 1210.13 M2 RATIO PER M2 = S/.
455.40
PREVIOUS CONTRACT AMOUNT 545,305.06
UPDATED CONTRACT AMOUNT 551,093.20
5,788.14
DIFFERENCE