JOB TITLE / AIM: Lifting, Shifting and storage of Pipes Inside all floors.

JSA DATE: 13.10.2023 JSA NO./ REVISION: R1


SUPERVISOR/ JSA LEADER: Mr. Akram, SCRIBE: Mr. Syed Khaja Misbhuddin
PARTICIPANTS : Mr. PANKAJ
LIST ASSOCIATED PROCEDURES/WORK INSTRUCTIONS OR TEMPORARY WIs:
1. PTW system,
2. Signal man and stand by,
3. Barricade and warning signs,
4. Continual supervision,
5. Competent workers deployment,
6. Vehicle fitness,
7. Good condition of Lifting tools & tackles – TPI verification and submission of certificates.
Attach copies of any relevant documentation/ drawings.
Part 2: Job Safety Analysis
Job Steps:
1. Mobilization of Equipment & Lifting tools and tackles,
2. Lifting, Shifting and storage of Pipes Inside Tower 2 all floors
3. Working night shift hours.

Part 3: Equipment’s / Tools to be used: Winch machine, Rigging accessories & Hand Tools
Part 4: Contingency Plans. Standard PPE’s: First aid kit must be present at work site and the HSE personnel will be the first response in case of
emergency, ERPs & Emergency contact numbers to be in placed at job location
Part 5:JSA Review Process. After the job has been completed, JSA leader should note: any hazards, which were identified in the original JSA? In
case of any new hazard identified by any of the working team member during the job, JSA review process should be carried on.
JSA No: JOB TITLE: Lifting, Shifting & Installation and storage of Pipes Inside Tower 2 all floors
Step# Describe Job Step Potential Hazards Hazard Controls
1 Mobilization of equipment &  Involvement of unskilled personnel  Trained & skilled staff to be authorized for
Materials job
 Unauthorized/
 Obtain relevant permit before
uninspected
vehicle/equipment entry in the area
equipment/tools at site
 Ensure use of appropriate PPE’s on site
 Personnel/Structures hit by
Equipment/Heavy Vehicle  JSA Briefing to all of workforce involved
 Damaging to drains/culverts beside  Deliver tool box talk to all of vehicles
roads drivers & operators
 Striking of vehicles with  Banks man should be available at site
structure/overhead live lines  Be careful about nearby drains/culverts
 Personnel injury / property damage while vehicle movement on roads
 Keep away all unauthorized people during
movement of heavy vehicle/equipment
 Do not left un attendant any of
equipment/tool in the area
 Ensure Close HSE monitoring
/Supervision
 Flame arrestor to be installed in vehicles

2 Lifting, Shifting and storage of Pipes  Uncertified Operator,  operator should be certified
Inside Tower 2 All floors.  Unauthorized personnel involvement  Banks man/signal man should be available
at site to control the movement of heavy
vehicles/equipment
 Place Winch machine at levelled &
compacted ground surface
 Keep away all unauthorized people during
movement of heavy vehicle/equipment
 Ensure Close HSE monitoring
/Supervision
JSA No: JOB TITLE: Lifting, Shifting & Installation and storage of Pipes Inside Tower 2 all floors
Step# Describe Job Step Potential Hazards Hazard Controls
 Sling broken, load drop  Ensure proper & inspected
 Miscommunication/signal error accessories being used for lifting
operation
 Ensure that load is properly placed &
lifted
 Ensure proper communication
between rigger/signal man & operator
 Keep away during Winch machine
operation
 Swing area should properly barricaded
 Slip, Trip & fall  Ensure proper stacking of all materials
at site
 Keep access/walk ways always clear from
any obstruction
 Ensure proper housekeeping of workplace
all the time
 Inclement weather condition  Stop Winch machine work in case of
any inclement weather conditions (Rain,
storm, fog etc.)
 Restrict movement of heavy
vehicles/equipment’s in
rain/fog
 Fire & explosion  Ensure availability of inspected fire
extinguishers at site
 Flame arrestor to be installed in all
vehicles/equipment’s
3 Storage of Pipes Inside Tower 2 all  Personnel hand injury while handling  Ensure Involvement of skilled labour
floors with units,  Ensure use of proper PPE’s
 People under suspended load,  Deliver TBT before commencing work
 Unbalancing of load while holding it  Ensure use of inspected & colour coded
hand tools & rigging accessories
 Area should be properly barricaded during
lifting operations
 Restrict unauthorized movement
JSA No: JOB TITLE: Lifting, Shifting & Installation and storage of Pipes Inside Tower 2 all floors
Step# Describe Job Step Potential Hazards Hazard Controls
 Improper signalling during lowering of  Ensure proper communication between
units. rigger/signal man & operator
 Rigger/signal man should wear vest
 Inappropriate PPE’s/Tools  Use of appropriate PPE’s during unloading
 Ensure use of inspected tools for the right
job
 Use tag line to control the load
 Personnel impact injury
 Availability of fresh water at site
 First aid box should be in place at site
4 Working at night shift hours  Poor visibility at night hours  Ensure proper lighting arrangement for
late night working hours
 Vehicles/equipments hit with people,  Careful movement of vehicles in night
equipment or structure hours
 Place refection tapes at hard barriers,
structures
 Banks men should worn high visibility
reflection vests
 Slip , trip & fall  No working should be allowed in poor
lighting conditions
 Ensure proper housekeeping to avoid
tripping

Prepared By: Approved By: