10MMØ STIRRUPS SPACED @

2-50MM, 4-100MM, REST @


200MM

3-12MMø 2-12MMø
0.30M 0.30M
2-12MMø 3-12MMø
0.20M 0.20M

2.70m @ SUPPORT @ MIDSPAN

4-12MMø VERTICAL BARS


W/ 10MMØ TIES SPACED @
4-50MM, 8-100MM, REST @
200MM

NGL
0.25m 0.60m

WELL COMPACTED
GRAVEL

0.20m

4-12MMø VERTICAL BARS


W/ 10MMØ TIES SPACED @
4-50MM, 8-100MM, REST @
200MM
COLUMN, FOOTING, ROOF BEAM DETAIL
0.80m

5-12MMø BARS
BOTHWAYS SPACED AS
SHOWN

0.80m

PREPARED BY: CHECKED BY: PROJECT TITLE: APPROVED BY: SHEET CONTENTS: SHEET NO.

CONSTRUCTION OF MATERIAL RECOVERY X


FACILITY AS SHOWN
ENGR. BRIEN CEASAR S. CANARIA ENGR. GENESIS A. SANTIAGO PROJECT LOCATION: BRGY. PITAO, SAN CLEMENTE, TARLAC HON. ELMA L. MACADAMIA X
ENGINEERING I MUNICIPAL ENGINEER MUNICIPAL MAYOR