KAPI - COMMON TOILETS REVISED SCHEDULE

KEYLAND AYALA, MAKATI CITY

Projected Catch up Schedule


END OF TILE WORKS AND TOILET PARTITIONS
START OF T&C

AUGUST SEPTEMBER OCTOBER


ACTIVITY DURATION 2nd WEEK 3rd WEEK 4th WEEK 5th WEEK 1st WEEK 2nd WEEK 3rd WEEK 4th WEEK 1st WEEK
9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9
8th FLOOR 2.5 weeks
MALE AND FEMALE SITE CLEARING 2days
DISMANTLE OF EXISTING TOILET PARTITION 1day
DISMANTLE OF EXISTING TILES 2days
WATER PROOFING INSTALLATION 1day
LEAK TEST 2days
INSTALLATION OF GRANITE BACK SPLASH 2days
INSTALLATION OF TOILET MIRROR 2days
TILING WORKS AND GROUTING 3days
INSTALLATION OF TOILET PARTITION 5days
CLOSEOUT OF PUNCHLIST (WITH CLEANING) 4days
5th FLOOR 2.5 weeks
MALE AND FEMALE SITE CLEARING 2days
DISMANTLE OF EXISTING TOILET PARTITION 1day
DISMANTLE OF EXISTING TILES 2days
WATER PROOFING INSTALLATION 1day
LEAK TEST 2days
INSTALLATION OF GRANITE BACK SPLASH 2days
INSTALLATION OF TOILET MIRROR 2days
TILING WORKS AND GROUTING 3days
INSTALLATION OF TOILET PARTITION 4days
CLOSEOUT OF PUNCHLIST (WITH CLEANING) 4days
3rd FLOOR 2.5 weeks
MALE AND FEMALE SITE CLEARING 2days
DISMANTLE OF EXISTING TOILET PARTITION 1day
DISMANTLE OF EXISTING TILES 2days
WATER PROOFING INSTALLATION 1day
LEAK TEST 2days
INSTALLATION OF GRANITE BACK SPLASH 2days
INSTALLATION OF TOILET MIRROR 2days
TILING WORKS AND GROUTING 3days
INSTALLATION OF TOILET PARTITION 4days
CLOSEOUT OF PUNCHLIST (WITH CLEANING) 4days
Ground FLOOR 2.5 weeks
MALE AND FEMALE SITE CLEARING 2days
DISMANTLE OF EXISTING TOILET PARTITION 1day
DISMANTLE OF EXISTING TILES 2days
WATER PROOFING INSTALLATION 1day
LEAK TEST 2days
INSTALLATION OF GRANITE BACK SPLASH 2days
INSTALLATION OF TOILET MIRROR 2days
TILING WORKS AND GROUTING 3days
INSTALLATION OF TOILET PARTITION 4days
CLOSEOUT OF PUNCHLIST (WITH CLEANING) 4days
6th FLOOR 2.5 weeks
MALE AND FEMALE SITE CLEARING 2days
DISMANTLE OF EXISTING TOILET PARTITION 1day
DISMANTLE OF EXISTING TILES 2days
WATER PROOFING INSTALLATION 1day
LEAK TEST 2days
INSTALLATION OF GRANITE BACK SPLASH 2days
INSTALLATION OF TOILET MIRROR 2days
TILING WORKS AND GROUTING 3days
INSTALLATION OF TOILET PARTITION 4days
CLOSEOUT OF PUNCHLIST (WITH CLEANING) 4days
PWD
CLOSEOUT OF PUNCHLIST (WITH CLEANING) 4days

TOTAL DURATION 9 weeks

*THIS SCHEDULE SERVES ONLY AS A GUIDE CONSTRUCTION DURATION MAY CHANGE DUE TO UNFORSEEN CONDITIONS OR CHANGES IN PLANS