1.

The purpose of the ____________________ is to inspect progress


towards the Sprint Goal and adapt the Sprint Backlog as necessary,
adjusting the incoming planned work.
A. Daily Scrum
B. Adaptation
C. Sprint planning
D. Sprint Retrospective

2. Successful use of Scrum depends on people becoming more


proficient in living five values. What are these five values?
A. Commitment, Focus Speed Respect and Courage
B. Commitment, Focus, Openness, Respect and Courage
C. Self-management, Focus, Speed, Respect, and Courage.
D. Sprint Planning, Daily Scrum, Sprint Review, Sprint Retrospective

3. The purpose of ____________________ is to plan ways to increase


quality and effectiveness.
A. Sprint Review
B. Sprint Retrospective
C. Sprint Planning
D. Sprint

4. The Daily Scrum is an event of _________________________ for


Scrum Team Developers.
A. Fifteen minutes
B. Four hours
C. One hour
D. Eight hours

5. The Sprint Planning has a maximum time limit of ______________ for a


one-month Sprint.
A. Twenty-four hours
B. One hour
C. Eight hours
D. Four hours
6. The Product Owner is the head of the developers and the developers
and the Scrum Master report to him. This statement is incorrect
because of what?
A. In the Scrum Team there are no teams or hierarchies.
B. The Scrum Master is the boss of the developers.
C. The Technical Lead is the head of the developers and the Product
Owner of the Scrum Master.
D. The project manager is the head of the developers and the Scrum
Master.

7. The ________________________ is responsible for creating and


clearly communicating the elements of the Product Backlog.
A. Contract Managers
B. Developers
C. Product Owner
D. Scrum Master

8. Scrum employs an approach _________________ and


___________________ to optimize predictability and control risk.
A. Iterative, Imperative
B. Iterative, Incremental
C. Predictive, Incremental
D. Evolutionary, Imperative

9. The Sprint Backlog consists of the ____________________ (why), the


set of Product Backlog items selected for the Sprint (what), as well as
an action plan to deliver the "Increment" (how).
A. Definition of Finished
B. Product Objective
C. Sprint Objective
D. Increase

10. The Sprint Objective, the Product Backlog items selected for the
Sprint, plus the plan for delivering them are together called
______________________.
A. Product Backlog
B. Sprint Backlog
C. Speed
D. Increase
11. The entire Scrum Team collaborates to define a _________________
that communicates why the Sprint is valuable to stakeholders. The
________________ must be completed before the end of the Sprint
Planning.
A. Increase
B. Product Backlog
C. Breakdown of tasks
D. Sprint Objective

12. The Scrum Team is small enough.


A. It cannot be more than 5 developers.
B. It cannot be more than 10 developers.
C. It cannot be more than 15 developers.
D. It cannot be more than 12 developers.

13. _____________________ You are limited to a maximum of three hours


for a one-month Sprint.
A. Sprint Review
B. Sprint Retrospective
C. Sprint Planning
D. Sprint

14. The ____________________________ is responsible for maximizing


the value of the product resulting from the Scrum Team's work.
A. Scrum Master
B. Contract Manager
C. Product Owner
D. Developers

15. Developers must adhere to the definition given. If there are several
Scrum Teams working together on a product, they must mutually
define and meet the same definition of completion.
A. Partially True. As long as it is authorized by the Scrum master.
B. False you must have a Product backlog for each piece of equipment.
C. False. Each team can have its definition of finished.
D. True. They must adhere to the same definition determined.
16. A Sprint may be cancelled if the Sprint Objective becomes obsolete.
Only the Product Owner has the authority to cancel the Sprint. Is this
statement True or False?
A. False. Only the Scrum Master has the authority to cancel the Sprint.
B. False. Only the Contract Manager has the authority to cancel the Sprint.
C. True. Only the Product Owner has the authority to cancel the Sprint.
D. True. As long as it is authorized by the Product Leader.

17. The Srum Team has 3 specific responsibilities. What are they?
A. A Scrum Master, a Business Owner and Developers
B. A Scrum Master, a Service Manager and Developers
C. A Scrum Master, a Product Owner and Developers
D. A Scrum Master, Testers and Developers

18. The ________________________ becomes more difficult when the


people involved are not empowered and self-managing.
A. Management
B. Inspection
C. Transparency
D. Adaptation

19. The _______________________ describes a future state of the product


that can serve as a target for the Scrum Team to plan for.
A. Sprint Objective
B. Definition of finished or DOD in English.
C. Increase
D. Product Objective.

20. The entire ScrumTeam is responsible for creating an "Increment"


______________________ in each Sprint.
A. Potentially deployable
B. In production
C. Valuable and Useful
D. Approved