Date of issue:

EMERGENCY PLAN 03/09/2021

FOR LIFTING WORK Version: 01

1. OBJECTIVE

Establish an emergency plan for the activity of lifting cargo with cranes, so that the
trained employees of CAO COLOMBIA S.AS. These work instructions must ensure
that the risks to the health of a victim are reduced to a minimum. The emergency
plan minimizes the risk behavior of employees during the development of lifting
activities, and in case of an emergency it is attended in a safe manner.

2. SCOPE

Erection of metallic structures for load lifting with crane.

3. RESPONSIBILITIES

Crane operator: responsible for the safe operation of the hoist.

Rigger: in charge of directing the load lifting maneuver.

SSTA Inspector: Verify the safe application of this plan, as well as verify all
preventive measures for access to the load hoisting area.

Workers: To comply with this plan.

4. GENERAL RULES

All elements used for lifting loads must be inspected before being used in the
maneuver.

Hazards associated with machine operation.

Overturning.
Sinking.
Fire.
Vehicle ejection.
Explosions or fires.
Falling from a different level.
Particle projection.
Electrical contact.

Thermal contacts.
Temperature changes.
Load drop.

Page 1 of 8
Date of issue:
EMERGENCY PLAN 03/09/2021

FOR LIFTING WORK Version: 01

Falling from a different level.


Hit-and-run.
Collision with other machines, vehicles, equipment or structures.
Damage to health derived from: vibrations, noise and particulate matter.

Personal protective equipment:

Safety helmet.
Hearing protectors (insert or cup type).
Respiratory protection
Gloves against mechanical aggressions.
Safety boots.
Safety goggles (dark or light)

Safety elements required for the operation.

Portable fire extinguisher located in the area.


Audible back-up alarm.
Harness and slings.
Beacon. (when required.)
Cones
Hazard tape to delimit the perimeter of the area.

Elements required for lifting loads.

Steel wire rope slings


Polyester flat type sling
Lifting Line
Hooks

Page 2 of 8
Date of issue:
EMERGENCY PLAN 03/09/2021

FOR LIFTING WORK Version: 01

5. DEFINITIONS

Load lifting: Operation performed to move large and/or heavy objects that cannot be
transported manually; the equipment used for load lifting is any device that allows lifting or
lowering a load, previously calculated, in a safe and controlled manner.

Rigging: It is any element that participates in the connection of loads to the load lifting
accessory (slings, accessories).

Sling: Cables, chains, metallic meshes and synthetic belts, which allow the load to be
attached to a hoisting device.

Rigging accessories: Such as shackles, eyebolts, hooks, turnbuckles, rods, spreader frames,
lifting eyes, differentials.

Steel wire rope: Set of steel wires grouped and twisted helically, constituting a metallic rope
capable of resisting tensile stresses and with adequate flexibility properties. The cable is
made up of three basic components which, according to their configuration, constitute cables
with different characteristics, useful for different purposes.

Load radius: Horizontal distance from the axis of rotation of the equipment (crane) to the
center of gravity of the load.

Page 3 of 8
13
EMERGENCY PLAN Date of issue: 03/09/2021

FOR LIFTING WORK Version: 01

6. DESCRIPTION OF THE PROCEDURE FOR LIFTING LOADS WITH CRANE

ITEM ACTIVITY RESPONSIBLE PREVENTIVE CONTROL REGISTRY

Certifications
Everyone involved in the safety for rigger and
management of mechanical lifting must crane operator
have clear roles and responsibilities, personnel.
knowledge, experience, and
Competence of competence for effective supervision of
1. Crane operator.
personnel. the execution of activities. Certificates of
All equipment, rigging, lifting
accessories and others must have crane,
their respective certificates to support rigging,
their use. hoisting
accessories.
13
EMERGENCY PLAN Date of issue: 03/09/2021

FOR LIFTING WORK Version: 01

Check for first aid kit, stretcher, fire


extinguisher, emergency numbers,
etc.

(Firefighters,
Ambulance,) brigadistas available in
the area for the attention of an
emergency or urgency.

Go to the pre
operational, check the condition of
hoses, oil levels, fuel level, tire
condition and potential damage to the Pre-operational
machine. inspection of the
crane.
Record the results of the pre-
operational inspection in the format
provided, if you detect anything that Permission
does not allow you to start the pre-
operational inspection. labor, from
report hoisting of loads.
immediately to the supervisor.

Check the locking systems, Analysis


operation, brakes, lights, mirrors,
visibility, seat belt, horn, steering, from
reverse alarm before starting work. safe work.

Check all controls to make sure they Inspections of the


are in the correct position before crane elements.
starting.

Check that the indicators are working


and are in the proper ranges.

Diligence of the load hoisting permit


corresponding to the activity.

Fill out the ATS or established hazard


identification mechanism.
Preventive Inspect all
measures at the the
beginning of the load SSTA load lifting devices
2 lifting operation. SUPERVISOR
Date of issue:
EMERGENCY PLAN 03/09/2021

FOR LIFTING WORK Version: 01

Mark the work area, taking into


account the crane's radius of
action.

Remove all vehicles, equipment,


machines, and employees not
related to the activity from the
crane's radius of action.

Verify that the personnel involved


in the activity have the
competencies.

Inform the supervisor in charge


that you are going to start
activities and consult the
standards
safety of the work area.

Check always
the
height, width and weight
restrictions of the work area and
ensure that your machine does
not exceed these limits.
13
EMERGENCY PLAN Date of issue: 03/09/2021

FOR LIFTING WORK Version: 01

Never leave the vehicle with the


arm hydraulic
extended or lifted, it may
suddenly descend y
cause serious injury to personnel
or damage.

Constantly check circulation


from people,
vehicles, machinery or
equipment.
Preventive Keep permanent
measures during communication with personnel in
operation SST the area, brigadistas, workers,
3
SUPERVISOR supervisors, operators.
from
load hoisting. Check the conditions
In the presence of rain or strong
winds, suspend the activity in the
event of heavy rains or strong
winds.

Never allow games or jokes to be


played during the lifting of loads.
Constantly check ground
conditions and performance
from
the
crane stabilizers
13
EMERGENCY PLAN Date of issue: 03/09/2021

FOR LIFTING WORK Version: 01

Remove all signaling elements


installed in the work area, restore
order.

Remove any element


4
or used for hoisting cargo.

Verify the condition of all elements


Preventive used for lifting loads.
measures at
end Check the condition of the crane.

the SUPERVISOR Conduct a closing meeting of the


load lifting operation. SSTA.
End.