Professional Documents
Culture Documents
Pages From Guidebook For Road Construction and Maintenance Management
Pages From Guidebook For Road Construction and Maintenance Management
Slab The slab is made of reinforced or plain concrete which also includes
load transfer devices and joint sealing materials. The concrete slab
acts like a bridge girder over the subgrade.
Subbase It is the portion of the pavement structure between the subgrade and
the slab. It usually consists of compacted layer/s of granular
materials.
Subbase It is the portion of the pavement structure between the subgrade and
the base course. It consists of a compacted layer of granular
materials placed on a prepared subgrade.
Approval of
Material Test Design Mix Trial Paving Start
Design Mix and
and Trial Mix Paving
Methodology
Conduct of slump test Checking of temperature Checking of the thickness Finishing by means of a
of the mix floater
Finishing by means of a Checking of the texturing Texturing of the surface Spraying of curing
screeder Tool compound
Dowel bars are placed in contraction joints and in some construction joints when it falls
at full block (4.5m) to transfer a portion of the load across the joint and to hold the two slab
ends at the same elevation. To function properly, dowels must be parallel to the surface and to
the centerline of the pavement.
Length and size of bars vary depending on pavement thickness as shown in Table 4.3.
(1) The Engineer and the Contractor conduct joint inspections prior to the commencement
of work to confirm the current conditions and identify the PCC slabs to be replaced.
(2) The Contractor removes broken/deteriorated PCCP slabs in accordance with the Plans,
Specifications or as directed by the Engineer.
(3) The subgrade and subbase course are prepared in accordance with the specifications or
as directed by the Engineer.
(4) Existing tie bars on longitudinal joints are to be retained if these are still in good
condition. Where necessary, new tie bars shall be installed on drilled holes and bonded
with high viscosity epoxy resin.
(5) Install forms; side surfaces of the
existing PCCP shall be cleaned.
(6) Pour concrete; perform the required
surface texturing, cutting and curing.
(7) Thoroughly clean the joints and apply
sealants adequately.
Figure 4.6 Deteriorated PCCP
4.2.11 Subbase
The subbase materials shall be spread on the prepared subgrade and compacted to the
required thickness.
Figure 4.11 Laying of Base Materials by Means of Road Grader and Paver
The porous asphalt mixture is composed of large proportion of coarse aggregate, small
proportion of fine aggregate, mineral filler and PMB.
This mixture has air voids within the range of 18% to 25% that easily allows the passage
of water.