Certificate of Bulidning REpair
Certificate of Bulidning REpair
Region X
DIVISION OF BUKIDNON
Malaybalay City
We hereby certify the above project has been duly completed on November 29, 2022 and that
all works incorporated there as to materials, quality, and quantity were done in accordance
with approved plans specification and other requirements.
I hereby certify that the project as described has been satisfactorily completed in
accordance with with approved plans and specifications as certified by the District Building
Inspector. Final payment is therefore recommended.
As project user, I hereby accept this repair/ maintenance project and assume full
responsibility for the proper use and up keep of the structure/ school facility.
Accepted: Witness:
Department of Education
Region X
DIVISION OF BUKIDNON
Malaybalay City
QUEZON I DISTRICT
DON ANTONIO O. FLOIRENDO SR. ELEMENTARY SCHOOL
Per actual inspection, the physical accomplishment is 100% completed as per approve
Program of Work.
INSPECTED:
LUWEN T. VILLANUEVA
District Building Inspector