Construction Sequence
Project Commencement
Exacavtion
Anti termite
Blinding for footing
Block work for footing / foundation
Or Formwork for Footings
Footing Steel reinforcements
Footing Concrete casting
Backfilling to footing level
Column necks shuttering
Column necks Casting
Concrete curing & De-shuttering
Column necks waterproofing
Foundation waterproofing
Backfilling and compaction
Blinding for Ground beam
Anti-termite / waterproofing
Ground beam steel rebars
Electrical sleeves fixing
Ground beam shuttering
Ground beam casting & De shuttering
Ground beam waterproofing
Plumbing/Electrical sleeves Installations
Ground beam Backfilling
Slab on grade
Column reinforcement
Column shuttering
Concrete casting
Curing & De shuttering
Beams & slab framing & shuttering
Beam & slab steel reinforcement
Drainage & electrical embedded sleeves
Slab & beam concrete casting
Slab & beam De shuttering
Parapet half column reinforcement
Parapet half column form work
Parapet half column casting
Parapet De shuttering
Parapet masonry work
Roof waterproofing
MEP roof equipment fixing
Masonry works
MEP 1st fix
Plastering
Architectural finishes
Testing & commissioning
Authority approvals
Snagging & De-snagging
Handover
Project completion