task_code status_code wbs_id task_namestart_date end_date resource_lidelete_record_flag

Activity ID Activity Status WBS Code Activity N (*)Start (*)Finish (*)ResourcDelete This Row
A1000 Not Started CPFCB.1 Project c 09-Sep-23
A1010 Not Started CPFCB.1 Project completion 09-Sep-23
A1020 Exacavtion
A1030 Anti termite
A1040 Blinding for footing
A1050 Block work for footing / foundation
A1060 Or Formwork for Footings
A1070 Footing Steel reinforcements
A1080 Footing Concrete casting
A1090 Backfilling to footing level
A1100 Column necks shuttering
A1110 Column necks Casting
A1120 Concrete curing & De-shuttering
A1130 Column necks waterproofing
A1140 Foundation waterproofing
A1150 Backfilling and compaction
A1160 Blinding for Ground beam
A1170 Anti-termite / waterproofing
A1180 Ground beam steel rebars
A1190 Electrical sleeves fixing
A1200 Ground beam shuttering
A1210 Ground beam casting & De shuttering
A1220 Ground beam waterproofing
A1230 Plumbing/Electrical sleeves Installations
A1240 Ground beam Backfilling
A1250 Slab on grade
A1260 Column reinforcement
A1270 Column shuttering
A1280 Concrete casting
A1290 Curing & De shuttering
A1300 Beams & slab framing & shuttering
A1310 Beam & slab steel reinforcement
A1320 Drainage & electrical embedded sleeves
A1330 Slab & beam concrete casting
A1340 Slab & beam De shuttering
A1350 Parapet half column reinforcement
A1360 Parapet half column form work
A1370 Parapet half column casting
A1380 Parapet De shuttering
A1390 Parapet masonry work
A1400 Roof waterproofing
A1410 MEP roof equipment fixing
A1420 Masonry works
A1430 MEP 1st fix
A1440 Plastering
A1450 Architectural finishes
A1460 Testing & commissioning
A1470 Authority approvals
A1480 Snagging & De-snagging
A1490 Handover
user_data
UserSettings Do Not Edit
DateFormat=dd'-'mmm'-'yy
CurrencyFormat=US Dollar