The Director,
SIMPLEX DRILLING AND Construction Limited
LUSAKA
Dear Sir/Madam,
Imani Mwilizi
DIRECTOR OF WORKS/PROJECT MANAGER
Cc : Council Chairperson
: Council Secretary
: File
12 May, 2023
The Director,
SCR Drilling and Construction Limited,
Zenmon, Great North Rd,
LUSAKA
Dear Sir/Madam,
TENDER NO: PTC/CDF22/D2/22 LOT 2 – CONTRACT FOR BOREHOLE SITING,
DRILLING AND INSTALLATION 10 INDIA MARK II HAND PUMPS AT HAMAFUWA,
CHUUMBU, HANAMWITALA, MUTABA AND HAMALAMBO IN MUZOKA WARD,
LWEENDO, MUCHACHACHA, MUZELENGANI AND MAAMBO IN KASIYA WARD
AND CHIMOWA IN PEMBA WARD
RE: COMPLETION OF THREE (03) WATER POINTS AND CORRECTION OF
DEFECTS
Reference is made to the above subject matter.
Pemba Town Council wish to inform you that the five (05) Water Points namely Chuumbu,
Muchachacha, Muzelengani, Maambo and Chimowa are defective. Muchachacha Water Point
is not functional while Chuumbu, Muzelengani, Maambo and Chimowa Water Points are not able
to retain water in the pipes. The five (05) borehole sites Hanamwitala, Hamalambo, Hamafuwa,
Mutaba and Lweendo awaits borehole drilling
Against this background, you are hereby given seven (07) day in which you must mobilize and
begin with correction of defects as follows.
• Ensure that the four Water Points namely Muchachacha, Muzelengani, Maambo and
Chimowa retain water in the pipes after pumping. Each Stainless-Steel pipe require a seal
that prevents water leakage.
• Break the drainages for Maambo and Chuumbu, reconstruct the drainages and ensure that
they are not very steep towards the soakaway
Upon correction of defects, proceed to the borehole sites as follows.
• Borehole siting, drilling and Installation Stainless Steel (SS) Hand Pumps at Hanamwitala
and Hamafuwa. Two borehole drilling attempts at each of the two sites were dry boreholes.
• Drilling and Installation Stainless Steel (SS) Hand Pumps at Mutaba, Lweendo and
Hamalambo. Borehole drilling attempts were not made at these three sites.
Be informed that all works must be completed and the Water Points handed over to the Project
Manager not later than 18st June, 2023.
Your cooperation in this regard will be highly appreciated.
Yours Faithfully,
PEMBA TOWN COUNCIL
S.K Chilombo
COUNCIL SECRETARY
CC : Council Chairman
Director of Works/Project Manager
: File
12 May, 2023
The Director,
SMR Construction Limited
Opposite Embassy of Ireland, Olympia,
LUSAKA
Dear Sir,
Yours Faithfully,
PEMBA TOWN COUNCIL
S.K Chilombo
COUNCIL SECRETARY
CC : Council Chairman
Director of Works/Project Manager
: File