Project Estimation in Square-foot Method

The Estimate Needed Area Length is Feet Width in Feet

125 200

The Estimate Needed Perimeter Length is Feet Width in Feet

125 200

Height of the Building 26 FT

From the given table the galvanized steel sliding over steel frame rate (for 25000 Sqft) per Sq. Ft is

From the given table the base perimeter is 640LF and there is a addition or deduction of $2.6 SF per 100 F perimeter

Addition or deduction of perimeter ($/SF) ((650'-640')/100)*2.6 per SF per 100 FT

Addition or deduction of perimeter ($/SF) 0.26 $ per SF addition

From the given table the base story height is 24' and there is a addition or deduction of $.45 per 1'

Addition or deduction of height ($/SF) ((26'-24')/1)*.45

Addition or deduction of height ($/SF) 0.90 $ per SF addition

Base cost ($/SF) D7+B10+B13 $86.21

Base cost $ E3*C15 $2,155,250.00

Other Cost, 50 feet asphalt is around the building

Length of the building with asphalt 125+50+50 225

Width of the building with asphalt 200+50+50 300

Area of the building with asphalt C17*C18 67500

Area of the Asphalt C19-E3 42500

As per given data the rate of the bituminous pavement per SFT is $3.96

Total asphalt cost C20*C21

Final Estimated Cost of the building C15+D22 $2,323,550.00


t Method Interpolation
Area in Sq. Ft x y
B3*C3 25000 SFT

Perimeter in Feet

2*(B5+C5) 650 FT

$85.05 #DIV/0!
6 SF per 100 F perimeter

FT

FT

SFT

SFT

$168,300.00

$2,323,550.00
Project Estimation in Square-foot Method
The Estimate Needed Area Length is Feet Width in Feet

250 180

The Estimate Needed Perimeter Length is Feet Width in Feet

250 180

Height of the Building 20 FT

From the given table the base perimeter is 640LF and there is a addition or deduction of $2.6 SF per 100 F perimeter

Addition or deduction of perimeter ($/SF) ((650'-640')/100)*2.6 per SF per 100 FT

Addition or deduction of perimeter ($/SF) 0.135 $ per SF addition

From the given table the base story height is 24' and there is a addition or deduction of $.45 per 1'

Addition or deduction of height ($/SF) ((26'-24')/1)*.45

Addition or deduction of height ($/SF) 0.76 $ per SF addition

Base cost ($/SF) D7+B10+B13 $72.70

Base cost $ E3*C15 $3,271,275.00

Other Cost, 50 feet asphalt is around the building

Length of the building with asphalt 125+50+50 225

Width of the building with asphalt 200+50+50 300

Area of the building with asphalt C17*C18 67500

Area of the Asphalt C19-E3 22500

As per given data the rate of the bituminous pavement per SFT is $3.96

Total asphalt cost C20*C21

Final Estimated Cost of the building C15+D22 $3,360,375.00


t Method
Area in Sq. Ft x y
B3*C3 45000 SFT 0.35 40,000
Perimeter in Feet 45,000
2*(B5+C5) 860 FT 0.4 50,000

$71.80 0.375
6 SF per 100 F perimeter

FT

FT

SFT

SFT

$89,100.00

$3,360,375.00