Assignment 3
Assignment 3
Area-B
Length of area B 19.33 Feet
Width of area B 24.33 Feet
Centerline of area B 43.00 Feet
Depth of the excavtion 8.83 Feet
Avg Width
Footing Width 2 Feet
working space 2 Feet
(Since Excavation slope is
Length of the slope 4.42 Feet
2:1)
Top Widht of the Trench 12.83 Feet
Bottom Widht of the Trench 4 Feet
Avg Width of the Trench 8.42 Feet
Excavation of the Trench for area B 3196.93 CFT
Excavation of the Trench for area B at the out side 1598.47 CFT
Excavation of the Trench for area B at the out side 59.20 CY
Area-C
Length of area C 20 Feet
Width of area C 15 Feet
Centerline of area C 49.33 Feet
Depth of the excavtion 8.83 Feet
Avg Width
Footing Width 2 Feet
working space 2 Feet
(Since Excavation slope is
Length of the slope 4.42 Feet
2:1)
Top Widht of the Trench 12.83 Feet
Bottom Widht of the Trench 4 Feet
Avg Width of the Trench 8.42 Feet
Excavation of the Trench for area C 3667.796 CFT
Excavation of the Trench for area C at the out side 1833.898 CFT
Excavation of the Trench for area C at the out side 67.92 CY
Dispose or Surplus
Unit Length in Feet Widht in Feet Depth in Feet Volume in CFT
Total Excavated Qty 13736.81
Total Backfilling Qty 4632.08
Total Surplus QTY in C.Y 337.21
Last year a three story 22,000 sft building's per SFT cost $158.59
Last year a three story 22,000 sft building's cost $3,488,980.00
Inflacion on the current year is 5%
Current year a three story 22,000 sft building's cost $3,663,429.00