KIPALIKU

Sto. Tomas, Davao

VOLUME ESTIMATES
NAME OF CANAL: TURN OUT 1
From Sta. 0 + 000.00 to Sta.
L= 300.44 m.
b= 0.40 m.
322 D= 0.50 m.
257.6 wall thickness = 0.10 m.
flooring thickness = 0.13 m.

A. Clearing and Grubbing


top width = 2.04 A = 300.44 x 2.04
A= 612.90 sq.m.

B. 170 kg/sqcm. Concrete


1. Canal
V = { [ ( 0.63 x 0.6 ) - ( 0.5 x 0.4 ) ] x 300.44 } - ( 0.2 x 0.1 x 0.1 x 2 x 51 )

V= 53.27 cu.m.

C. 211 kg/sqcm. Concrete


2. Strut
Strut Spacing = 6.00 m.
Strut width = 0.10 m.
Strut thickness = 0.20 m.
No. of Strut = 300.44 / 6
No. of Strut = 51 pcs.

V = 51 x [ ( 0.6 x 0.2 x 0.1 ) ]


V= 0.61 cu.m.

D. Gravel Blanket
V = 300.44 x 0.6 x 0.1
V= 18.03 cu.m.

E. Reinforcing Steel Bars


length 0.30 BAR DIAMETER CUTTING LENGTH
BAR MARK
vert. hor. no. of pcs ( mm. ) ( m. )
1.03 0.50 1,003.00 U-Bars 12 1.53
40 6.00 376.00 Longitudinal Bars 10 6.00
Strut
1.46 153.00 Longitudinal Bars 12 1.46
0.20 85.00 Lateral ties 10 0.20
TOTAL

F. Filter Drain
Every 4 meters
V = 0.15 x 0.20 x 0.40 x ( 1 + 300.44 / 4 ) x 2
V= 1.83 cu.m.

G. 38 mm Weephole
l.m. = 0.30 x ( 1 + 300.44 / 4 ) x 2
45.67 l.m.
15.22 pcs.
order, = 16.00 pcs.
l.m. = 48.00 l.m.

Prepared by:
KIPALIKU RIS
Sto. Tomas, Davao del Norte

0 + 300.44 CANAL SECTION

0.10 0.40 0.10

0.50
0.63

0.44 } - ( 0.2 x 0.1 x 0.1 x 2 x 51 )

170 kg/sqcm 0.13

Gravel Blanket 0.10


0.60

SEE PLAN FOR COMPLETE


STRUT DETAIL
0.60 0.10

0.10 211 kg/sqcm 0.20

PLAN SECTION
BAR LENGTH NO. OF LENGTHS
Kgs.
( m. ) ( pcs. )
9.0 201.00 1,606.39
6.0 376.00 1,389.70

6.0 39.00 207.79


6.0 3.00 11.09
TOTAL 3,214.97

Checked by: Approved by:

JULIUS M. LIM NELSON L. SAHOT


Senior Engineer A Acting Division Manager
KIPALIKU
Sto. Tomas, Davao

VOLUME ESTIMATES
NAME OF CANAL: TURN OUT 2
From Sta. 0 + 000.00 to Sta.
L= 617.14 m.
b= 0.40 m.
322 D= 0.50 m.
257.6 wall thickness = 0.10 m.
flooring thickness = 0.13 m.

A. Clearing and Grubbing


top width = 2.04 A = 617.14 x 2.04
A= 1,258.97 sq.m.

B. 170 kg/sqcm. Concrete


1. Canal
V = { [ ( 0.63 x 0.6 ) - ( 0.5 x 0.4 ) ] x 617.14 } - ( 0.2 x 0.1 x 0.1 x 2 x 104 )

V= 109.43 cu.m.

C. 211 kg/sqcm. Concrete


2. Strut
Strut Spacing = 6.00 m.
Strut width = 0.10 m.
Strut thickness = 0.20 m.
No. of Strut = 617.14 / 6
No. of Strut = 104 pcs.

V = 104 x [ ( 0.6 x 0.2 x 0.1 ) ]


V= 1.25 cu.m.

D. Gravel Blanket
V = 617.14 x 0.6 x 0.1
V= 37.03 cu.m.

E. Reinforcing Steel Bars


length 0.30 BAR DIAMETER CUTTING LENGTH
BAR MARK
vert. hor. no. of pcs ( mm. ) ( m. )
1.03 0.50 2,059.00 U-Bars 12 1.53
40 6.00 772.00 Longitudinal Bars 10 6.00
Strut
1.46 312.00 Longitudinal Bars 12 1.46
0.20 174.00 Lateral ties 10 0.20
TOTAL

F. Filter Drain
Every 4 meters
V = 0.15 x 0.20 x 0.40 x ( 1 + 617.14 / 4 ) x 2
V= 3.73 cu.m.

G. 38 mm Weephole
l.m. = 0.30 x ( 1 + 617.14 / 4 ) x 2
93.17 l.m.
31.06 pcs.
order, = 32.00 pcs.
l.m. = 96.00 l.m.

Prepared by:
KIPALIKU RIS
Sto. Tomas, Davao del Norte

0 + 617.14 CANAL SECTION

0.10 0.40 0.10

0.50
0.63

7.14 } - ( 0.2 x 0.1 x 0.1 x 2 x 104 )

170 kg/sqcm 0.13

Gravel Blanket 0.10


0.60

SEE PLAN FOR COMPLETE


STRUT DETAIL
0.60 0.10

0.10 211 kg/sqcm 0.20

PLAN SECTION
BAR LENGTH NO. OF LENGTHS
Kgs.
( m. ) ( pcs. )
9.0 412.00 3,292.70
6.0 772.00 2,853.31

6.0 78.00 415.58


6.0 6.00 22.18
TOTAL 6,583.77

Checked by: Approved by:

JULIUS M. LIM NELSON L. SAHOT


Senior Engineer A Acting Division Manager
KIPALIKU
Sto. Tomas, Davao

VOLUME ESTIMATES
NAME OF CANAL: TURN OUT 3
From Sta. 0 + 000.00 to Sta.
L= 830.78 m.
b= 0.40 m.
322 D= 0.50 m.
257.6 wall thickness = 0.10 m.
flooring thickness = 0.13 m.

A. Clearing and Grubbing


top width = 2.04 A = 830.78 x 2.04
A= 1,694.79 sq.m.

B. 170 kg/sqcm. Concrete


1. Canal
V = { [ ( 0.63 x 0.6 ) - ( 0.5 x 0.4 ) ] x 830.78 } - ( 0.2 x 0.1 x 0.1 x 2 x 139 )

V= 147.32 cu.m.

C. 211 kg/sqcm. Concrete


2. Strut
Strut Spacing = 6.00 m.
Strut width = 0.10 m.
Strut thickness = 0.20 m.
No. of Strut = 830.78 / 6
No. of Strut = 139 pcs.

V = 139 x [ ( 0.6 x 0.2 x 0.1 ) ]


V= 1.67 cu.m.

D. Gravel Blanket
V = 830.78 x 0.6 x 0.1
V= 49.85 cu.m.

E. Reinforcing Steel Bars


length 0.30 BAR DIAMETER CUTTING LENGTH
BAR MARK
vert. hor. no. of pcs ( mm. ) ( m. )
1.03 0.50 2,771.00 U-Bars 12 1.53
40 6.00 1,039.00 Longitudinal Bars 10 6.00
Strut
1.46 417.00 Longitudinal Bars 12 1.46
0.20 232.00 Lateral ties 10 0.20
TOTAL

F. Filter Drain
Every 4 meters
V = 0.15 x 0.20 x 0.40 x ( 1 + 830.78 / 4 ) x 2
V= 5.01 cu.m.

G. 38 mm Weephole
l.m. = 0.30 x ( 1 + 830.78 / 4 ) x 2
125.22 l.m.
41.74 pcs.
order, = 42.00 pcs.
l.m. = 126.00 l.m.

Prepared by:
KIPALIKU RIS
Sto. Tomas, Davao del Norte

0 + 830.78 CANAL SECTION

0.10 0.40 0.10

0.50
0.63

0.78 } - ( 0.2 x 0.1 x 0.1 x 2 x 139 )

170 kg/sqcm 0.13

Gravel Blanket 0.10


0.60

SEE PLAN FOR COMPLETE


STRUT DETAIL
0.60 0.10

0.10 211 kg/sqcm 0.20

PLAN SECTION
BAR LENGTH NO. OF LENGTHS
Kgs.
( m. ) ( pcs. )
9.0 555.00 4,435.56
6.0 1,039.00 3,840.14

6.0 105.00 559.44


6.0 8.00 29.57
TOTAL 8,864.71

Checked by: Approved by:

JULIUS M. LIM NELSON L. SAHOT


Senior Engineer A Acting Division Manager
KIPALIKU
Sto. Tomas, Davao

VOLUME ESTIMATES
NAME OF CANAL: TURN OUT 4
From Sta. 0 + 000.00 to Sta.
L= 797.86 m.
b= 0.40 m.
322 D= 0.50 m.
257.6 wall thickness = 0.10 m.
flooring thickness = 0.13 m.

A. Clearing and Grubbing


top width = 2.04 A = 797.86 x 2.04
A= 1,627.63 sq.m.

B. 170 kg/sqcm. Concrete


1. Canal
V = { [ ( 0.63 x 0.6 ) - ( 0.5 x 0.4 ) ] x 797.86 } - ( 0.2 x 0.1 x 0.1 x 2 x 134 )

V= 141.48 cu.m.

C. 211 kg/sqcm. Concrete


2. Strut
Strut Spacing = 6.00 m.
Strut width = 0.10 m.
Strut thickness = 0.20 m.
No. of Strut = 797.86 / 6
No. of Strut = 134 pcs.

V = 134 x [ ( 0.6 x 0.2 x 0.1 ) ]


V= 1.61 cu.m.

D. Gravel Blanket
V = 797.86 x 0.6 x 0.1
V= 47.87 cu.m.

E. Reinforcing Steel Bars


length 0.30 BAR DIAMETER CUTTING LENGTH
BAR MARK
vert. hor. no. of pcs ( mm. ) ( m. )
1.03 0.50 2,661.00 U-Bars 12 1.53
40 6.00 998.00 Longitudinal Bars 10 6.00
Strut
1.46 402.00 Longitudinal Bars 12 1.46
0.20 224.00 Lateral ties 10 0.20
TOTAL

F. Filter Drain
Every 4 meters
V = 0.15 x 0.20 x 0.40 x ( 1 + 797.86 / 4 ) x 2
V= 4.81 cu.m.

G. 38 mm Weephole
l.m. = 0.30 x ( 1 + 797.86 / 4 ) x 2
120.28 l.m.
40.09 pcs.
order, = 41.00 pcs.
l.m. = 123.00 l.m.

Prepared by:
KIPALIKU RIS
Sto. Tomas, Davao del Norte

0 + 797.86 CANAL SECTION

0.10 0.40 0.10

0.50
0.63

7.86 } - ( 0.2 x 0.1 x 0.1 x 2 x 134 )

170 kg/sqcm 0.13

Gravel Blanket 0.10


0.60

SEE PLAN FOR COMPLETE


STRUT DETAIL
0.60 0.10

0.10 211 kg/sqcm 0.20

PLAN SECTION
BAR LENGTH NO. OF LENGTHS
Kgs.
( m. ) ( pcs. )
9.0 533.00 4,259.74
6.0 998.00 3,688.61

6.0 101.00 538.13


6.0 8.00 29.57
TOTAL 8,516.05

Checked by: Approved by:

JULIUS M. LIM NELSON L. SAHOT


Senior Engineer A Acting Division Manager
KIPALIKU
Sto. Tomas, Davao

VOLUME ESTIMATES
NAME OF CANAL: TURN OUT 5
From Sta. 0 + 000.00 to Sta.
L= 1,424.43 m.
b= 0.40 m.
322 D= 0.50 m.
257.6 wall thickness = 0.10 m.
flooring thickness = 0.13 m.

A. Clearing and Grubbing


top width = 2.04 A = 1424.43 x 2.04
A= 2,905.84 sq.m.

B. 170 kg/sqcm. Concrete


1. Canal
V = { [ ( 0.63 x 0.6 ) - ( 0.5 x 0.4 ) ] x 1424.43 } - ( 0.2 x 0.1 x 0.1 x 2 x 238 )

V= 252.60 cu.m.

C. 211 kg/sqcm. Concrete


2. Strut
Strut Spacing = 6.00 m.
Strut width = 0.10 m.
Strut thickness = 0.20 m.
No. of Strut = 1424.43 / 6
No. of Strut = 238 pcs.

V = 238 x [ ( 0.6 x 0.2 x 0.1 ) ]


V= 2.86 cu.m.

D. Gravel Blanket
V = 1424.43 x 0.6 x 0.1
V= 85.47 cu.m.

E. Reinforcing Steel Bars


length 0.30 BAR DIAMETER CUTTING LENGTH
BAR MARK
vert. hor. no. of pcs ( mm. ) ( m. )
1.03 0.50 4,750.00 U-Bars 12 1.53
40 6.00 1,781.00 Longitudinal Bars 10 6.00
Strut
1.46 714.00 Longitudinal Bars 12 1.46
0.20 397.00 Lateral ties 10 0.20
TOTAL

F. Filter Drain
Every 4 meters
V = 0.15 x 0.20 x 0.40 x ( 1 + 1424.43 / 4 ) x 2
V= 8.57 cu.m.

G. 38 mm Weephole
l.m. = 0.30 x ( 1 + 1424.43 / 4 ) x 2
214.26 l.m.
71.42 pcs.
order, = 72.00 pcs.
l.m. = 216.00 l.m.

Prepared by:
KIPALIKU RIS
Sto. Tomas, Davao del Norte

1 + 424.43 CANAL SECTION

0.10 0.40 0.10

0.50
0.63

24.43 } - ( 0.2 x 0.1 x 0.1 x 2 x 238 )

170 kg/sqcm 0.13

Gravel Blanket 0.10


0.60

SEE PLAN FOR COMPLETE


STRUT DETAIL
0.60 0.10

0.10 211 kg/sqcm 0.20

PLAN SECTION
BAR LENGTH NO. OF LENGTHS
Kgs.
( m. ) ( pcs. )
9.0 950.00 7,592.40
6.0 1,781.00 6,582.58

6.0 179.00 953.71


6.0 14.00 51.74
TOTAL 15,180.43

Checked by: Approved by:

JULIUS M. LIM NELSON L. SAHOT


Senior Engineer A Acting Division Manager
KIPALIKU
Sto. Tomas, Davao

VOLUME ESTIMATES
NAME OF CANAL: TURN OUT 6
From Sta. 0 + 000.00 to Sta.
L= 182.40 m.
b= 0.40 m.
322 D= 0.50 m.
257.6 wall thickness = 0.10 m.
flooring thickness = 0.13 m.

A. Clearing and Grubbing


top width = 2.04 A = 182.4 x 2.04
A= 372.10 sq.m.

B. 170 kg/sqcm. Concrete


1. Canal
V = { [ ( 0.63 x 0.6 ) - ( 0.5 x 0.4 ) ] x 182.4 } - ( 0.2 x 0.1 x 0.1 x 2 x 31 )

V= 32.34 cu.m.

C. 211 kg/sqcm. Concrete


2. Strut
Strut Spacing = 6.00 m.
Strut width = 0.10 m.
Strut thickness = 0.20 m.
No. of Strut = 182.4 / 6
No. of Strut = 31 pcs.

V = 31 x [ ( 0.6 x 0.2 x 0.1 ) ]


V= 0.37 cu.m.

D. Gravel Blanket
V = 182.4 x 0.6 x 0.1
V= 10.94 cu.m.

E. Reinforcing Steel Bars


length 0.30 BAR DIAMETER CUTTING LENGTH
BAR MARK
vert. hor. no. of pcs ( mm. ) ( m. )
1.03 0.50 609.00 U-Bars 12 1.53
40 6.00 228.00 Longitudinal Bars 10 6.00
Strut
1.46 93.00 Longitudinal Bars 12 1.46
0.20 52.00 Lateral ties 10 0.20
TOTAL

F. Filter Drain
Every 4 meters
V = 0.15 x 0.20 x 0.40 x ( 1 + 182.4 / 4 ) x 2
V= 1.12 cu.m.

G. 38 mm Weephole
l.m. = 0.30 x ( 1 + 182.4 / 4 ) x 2
27.96 l.m.
9.32 pcs.
order, = 10.00 pcs.
l.m. = 30.00 l.m.

Prepared by:
KIPALIKU RIS
Sto. Tomas, Davao del Norte

0 + 182.40 CANAL SECTION

0.10 0.40 0.10

0.50
0.63

2.4 } - ( 0.2 x 0.1 x 0.1 x 2 x 31 )

170 kg/sqcm 0.13

Gravel Blanket 0.10


0.60

SEE PLAN FOR COMPLETE


STRUT DETAIL
0.60 0.10

0.10 211 kg/sqcm 0.20

PLAN SECTION
BAR LENGTH NO. OF LENGTHS
Kgs.
( m. ) ( pcs. )
9.0 122.00 975.02
6.0 228.00 842.69

6.0 24.00 127.87


6.0 2.00 7.39
TOTAL 1,952.97

Checked by: Approved by:

JULIUS M. LIM NELSON L. SAHOT


Senior Engineer A Acting Division Manager
KIPALIKU
Sto. Tomas, Davao

VOLUME ESTIMATES
NAME OF CANAL: TURN OUT 7
From Sta. 0 + 000.00 to Sta.
L= 1,829.53 m.
b= 0.40 m.
322 D= 0.50 m.
257.6 wall thickness = 0.10 m.
flooring thickness = 0.13 m.

A. Clearing and Grubbing


top width = 2.04 A = 1829.53 x 2.04
A= 3,732.24 sq.m.

B. 170 kg/sqcm. Concrete


1. Canal
V = { [ ( 0.63 x 0.6 ) - ( 0.5 x 0.4 ) ] x 1829.53 } - ( 0.2 x 0.1 x 0.1 x 2 x 306 )

V= 324.43 cu.m.

C. 211 kg/sqcm. Concrete


2. Strut
Strut Spacing = 6.00 m.
Strut width = 0.10 m.
Strut thickness = 0.20 m.
No. of Strut = 1829.53 / 6
No. of Strut = 306 pcs.

V = 306 x [ ( 0.6 x 0.2 x 0.1 ) ]


V= 3.67 cu.m.

D. Gravel Blanket
V = 1829.53 x 0.6 x 0.1
V= 109.77 cu.m.

E. Reinforcing Steel Bars


length 0.30 BAR DIAMETER CUTTING LENGTH
BAR MARK
vert. hor. no. of pcs ( mm. ) ( m. )
1.03 0.50 6,100.00 U-Bars 12 1.53
40 6.00 2,287.00 Longitudinal Bars 10 6.00
Strut
1.46 918.00 Longitudinal Bars 12 1.46
0.20 510.00 Lateral ties 10 0.20
TOTAL

F. Filter Drain
Every 4 meters
V = 0.15 x 0.20 x 0.40 x ( 1 + 1829.53 / 4 ) x 2
V= 11 cu.m.

G. 38 mm Weephole
l.m. = 0.30 x ( 1 + 1829.53 / 4 ) x 2
275.03 l.m.
91.68 pcs.
order, = 92.00 pcs.
l.m. = 276.00 l.m.

Prepared by:
KIPALIKU RIS
Sto. Tomas, Davao del Norte

1 + 829.53 CANAL SECTION

0.10 0.40 0.10

0.50
0.63

29.53 } - ( 0.2 x 0.1 x 0.1 x 2 x 306 )

170 kg/sqcm 0.13

Gravel Blanket 0.10


0.60

SEE PLAN FOR COMPLETE


STRUT DETAIL
0.60 0.10

0.10 211 kg/sqcm 0.20

PLAN SECTION
BAR LENGTH NO. OF LENGTHS
Kgs.
( m. ) ( pcs. )
9.0 1,220.00 9,750.24
6.0 2,287.00 8,452.75

6.0 230.00 1,225.44


6.0 17.00 62.83
TOTAL 19,491.26

Checked by: Approved by:

JULIUS M. LIM NELSON L. SAHOT


Senior Engineer A Acting Division Manager
KIPALIKU
Sto. Tomas, Davao

VOLUME ESTIMATES
NAME OF CANAL: TURN OUT 8
From Sta. 0 + 000.00 to Sta.
L= 649.22 m.
b= 0.40 m.
322 D= 0.50 m.
257.6 wall thickness = 0.10 m.
flooring thickness = 0.13 m.

A. Clearing and Grubbing


top width = 2.04 A = 649.22 x 2.04
A= 1,324.41 sq.m.

B. 170 kg/sqcm. Concrete


1. Canal
V = { [ ( 0.63 x 0.6 ) - ( 0.5 x 0.4 ) ] x 649.22 } - ( 0.2 x 0.1 x 0.1 x 2 x 109 )

V= 115.13 cu.m.

C. 211 kg/sqcm. Concrete


2. Strut
Strut Spacing = 6.00 m.
Strut width = 0.10 m.
Strut thickness = 0.20 m.
No. of Strut = 649.22 / 6
No. of Strut = 109 pcs.

V = 109 x [ ( 0.6 x 0.2 x 0.1 ) ]


V= 1.31 cu.m.

D. Gravel Blanket
V = 649.22 x 0.6 x 0.1
V= 38.95 cu.m.

E. Reinforcing Steel Bars


length 0.30 BAR DIAMETER CUTTING LENGTH
BAR MARK
vert. hor. no. of pcs ( mm. ) ( m. )
1.03 0.50 2,166.00 U-Bars 12 1.53
40 6.00 812.00 Longitudinal Bars 10 6.00
Strut
1.46 327.00 Longitudinal Bars 12 1.46
0.20 182.00 Lateral ties 10 0.20
TOTAL

F. Filter Drain
Every 4 meters
V = 0.15 x 0.20 x 0.40 x ( 1 + 649.22 / 4 ) x 2
V= 3.92 cu.m.

G. 38 mm Weephole
l.m. = 0.30 x ( 1 + 649.22 / 4 ) x 2
97.98 l.m.
32.66 pcs.
order, = 33.00 pcs.
l.m. = 99.00 l.m.

Prepared by:
KIPALIKU RIS
Sto. Tomas, Davao del Norte

0 + 649.22 CANAL SECTION

0.10 0.40 0.10

0.50
0.63

9.22 } - ( 0.2 x 0.1 x 0.1 x 2 x 109 )

170 kg/sqcm 0.13

Gravel Blanket 0.10


0.60

SEE PLAN FOR COMPLETE


STRUT DETAIL
0.60 0.10

0.10 211 kg/sqcm 0.20

PLAN SECTION
BAR LENGTH NO. OF LENGTHS
Kgs.
( m. ) ( pcs. )
9.0 434.00 3,468.53
6.0 812.00 3,001.15

6.0 82.00 436.90


6.0 7.00 25.87
TOTAL 6,932.45

Checked by: Approved by:

JULIUS M. LIM NELSON L. SAHOT


Senior Engineer A Acting Division Manager
KIPALIKU
Sto. Tomas, Davao

VOLUME ESTIMATES
NAME OF CANAL: TURN OUT 9
From Sta. 0 + 000.00 to Sta.
L= 400.47 m.
b= 0.40 m.
322 D= 0.50 m.
257.6 wall thickness = 0.10 m.
flooring thickness = 0.13 m.

A. Clearing and Grubbing


top width = 2.04 A = 400.47 x 2.04
A= 816.96 sq.m.

B. 170 kg/sqcm. Concrete


1. Canal
V = { [ ( 0.63 x 0.6 ) - ( 0.5 x 0.4 ) ] x 400.47 } - ( 0.2 x 0.1 x 0.1 x 2 x 68 )

V= 71.01 cu.m.

C. 211 kg/sqcm. Concrete


2. Strut
Strut Spacing = 6.00 m.
Strut width = 0.10 m.
Strut thickness = 0.20 m.
No. of Strut = 400.47 / 6
No. of Strut = 68 pcs.

V = 68 x [ ( 0.6 x 0.2 x 0.1 ) ]


V= 0.82 cu.m.

D. Gravel Blanket
V = 400.47 x 0.6 x 0.1
V= 24.03 cu.m.

E. Reinforcing Steel Bars


length 0.30 BAR DIAMETER CUTTING LENGTH
BAR MARK
vert. hor. no. of pcs ( mm. ) ( m. )
1.03 0.50 1,336.00 U-Bars 12 1.53
40 6.00 501.00 Longitudinal Bars 10 6.00
Strut
1.46 204.00 Longitudinal Bars 12 1.46
0.20 114.00 Lateral ties 10 0.20
TOTAL

F. Filter Drain
Every 4 meters
V = 0.15 x 0.20 x 0.40 x ( 1 + 400.47 / 4 ) x 2
V= 2.43 cu.m.

G. 38 mm Weephole
l.m. = 0.30 x ( 1 + 400.47 / 4 ) x 2
60.67 l.m.
20.22 pcs.
order, = 21.00 pcs.
l.m. = 63.00 l.m.

Prepared by:
KIPALIKU RIS
Sto. Tomas, Davao del Norte

0 + 400.47 CANAL SECTION

0.10 0.40 0.10

0.50
0.63

0.47 } - ( 0.2 x 0.1 x 0.1 x 2 x 68 )

170 kg/sqcm 0.13

Gravel Blanket 0.10


0.60

SEE PLAN FOR COMPLETE


STRUT DETAIL
0.60 0.10

0.10 211 kg/sqcm 0.20

PLAN SECTION
BAR LENGTH NO. OF LENGTHS
Kgs.
( m. ) ( pcs. )
9.0 268.00 2,141.86
6.0 501.00 1,851.70

6.0 51.00 271.73


6.0 4.00 14.78
TOTAL 4,280.07

Checked by: Approved by:

JULIUS M. LIM NELSON L. SAHOT


Senior Engineer A Acting Division Manager
KIPALIKU
Sto. Tomas, Davao

VOLUME ESTIMATES
NAME OF CANAL: TURN OUT 10
From Sta. 0 + 000.00 to Sta.
L= 88.44 m.
b= 0.40 m.
322 D= 0.50 m.
257.6 wall thickness = 0.10 m.
flooring thickness = 0.13 m.

A. Clearing and Grubbing


top width = 2.04 A = 88.44 x 2.04
A= 180.42 sq.m.

B. 170 kg/sqcm. Concrete


1. Canal
V = { [ ( 0.63 x 0.6 ) - ( 0.5 x 0.4 ) ] x 88.44 } - ( 0.2 x 0.1 x 0.1 x 2 x 16 )

V= 15.68 cu.m.

C. 211 kg/sqcm. Concrete


2. Strut
Strut Spacing = 6.00 m.
Strut width = 0.10 m.
Strut thickness = 0.20 m.
No. of Strut = 88.44 / 6
No. of Strut = 16 pcs.

V = 16 x [ ( 0.6 x 0.2 x 0.1 ) ]


V= 0.19 cu.m.

D. Gravel Blanket
V = 88.44 x 0.6 x 0.1
V= 5.31 cu.m.

E. Reinforcing Steel Bars


length 0.30 BAR DIAMETER CUTTING LENGTH
BAR MARK
vert. hor. no. of pcs ( mm. ) ( m. )
1.03 0.50 296.00 U-Bars 12 1.53
40 6.00 111.00 Longitudinal Bars 10 6.00
Strut
1.46 48.00 Longitudinal Bars 12 1.46
0.20 27.00 Lateral ties 10 0.20
TOTAL

F. Filter Drain
Every 4 meters
V = 0.15 x 0.20 x 0.40 x ( 1 + 88.44 / 4 ) x 2
V= 0.55 cu.m.

G. 38 mm Weephole
l.m. = 0.30 x ( 1 + 88.44 / 4 ) x 2
13.87 l.m.
4.62 pcs.
order, = 5.00 pcs.
l.m. = 15.00 l.m.

Prepared by:
KIPALIKU RIS
Sto. Tomas, Davao del Norte

0 + 088.44 CANAL SECTION

0.10 0.40 0.10

0.50
0.63

44 } - ( 0.2 x 0.1 x 0.1 x 2 x 16 )

170 kg/sqcm 0.13

Gravel Blanket 0.10


0.60

SEE PLAN FOR COMPLETE


STRUT DETAIL
0.60 0.10

0.10 211 kg/sqcm 0.20

PLAN SECTION
BAR LENGTH NO. OF LENGTHS
Kgs.
( m. ) ( pcs. )
9.0 60.00 479.52
6.0 111.00 410.26

6.0 12.00 63.94


6.0 1.00 3.70
TOTAL 957.42

Checked by: Approved by:

JULIUS M. LIM NELSON L. SAHOT


Senior Engineer A Acting Division Manager
KIPALIKU
Sto. Tomas, Davao

VOLUME ESTIMATES
NAME OF CANAL: TURN OUT 11
From Sta. 0 + 000.00 to Sta.
L= 149.38 m.
b= 0.40 m.
322 D= 0.50 m.
257.6 wall thickness = 0.10 m.
flooring thickness = 0.13 m.

A. Clearing and Grubbing


top width = 2.04 A = 149.38 x 2.04
A= 304.74 sq.m.

B. 170 kg/sqcm. Concrete


1. Canal
V = { [ ( 0.63 x 0.6 ) - ( 0.5 x 0.4 ) ] x 149.38 } - ( 0.2 x 0.1 x 0.1 x 2 x 26 )

V= 26.49 cu.m.

C. 211 kg/sqcm. Concrete


2. Strut
Strut Spacing = 6.00 m.
Strut width = 0.10 m.
Strut thickness = 0.20 m.
No. of Strut = 149.38 / 6
No. of Strut = 26 pcs.

V = 26 x [ ( 0.6 x 0.2 x 0.1 ) ]


V= 0.31 cu.m.

D. Gravel Blanket
V = 149.38 x 0.6 x 0.1
V= 8.96 cu.m.

E. Reinforcing Steel Bars


length 0.30 BAR DIAMETER CUTTING LENGTH
BAR MARK
vert. hor. no. of pcs ( mm. ) ( m. )
1.03 0.50 499.00 U-Bars 12 1.53
40 6.00 187.00 Longitudinal Bars 10 6.00
Strut
1.46 78.00 Longitudinal Bars 12 1.46
0.20 44.00 Lateral ties 10 0.20
TOTAL

F. Filter Drain
Every 4 meters
V = 0.15 x 0.20 x 0.40 x ( 1 + 149.38 / 4 ) x 2
V= 0.92 cu.m.

G. 38 mm Weephole
l.m. = 0.30 x ( 1 + 149.38 / 4 ) x 2
23.01 l.m.
7.67 pcs.
order, = 8.00 pcs.
l.m. = 24.00 l.m.

Prepared by:
KIPALIKU RIS
Sto. Tomas, Davao del Norte

0 + 149.38 CANAL SECTION

0.10 0.40 0.10

0.50
0.63

9.38 } - ( 0.2 x 0.1 x 0.1 x 2 x 26 )

170 kg/sqcm 0.13

Gravel Blanket 0.10


0.60

SEE PLAN FOR COMPLETE


STRUT DETAIL
0.60 0.10

0.10 211 kg/sqcm 0.20

PLAN SECTION
BAR LENGTH NO. OF LENGTHS
Kgs.
( m. ) ( pcs. )
9.0 100.00 799.20
6.0 187.00 691.15

6.0 20.00 106.56


6.0 2.00 7.39
TOTAL 1,604.30

Checked by: Approved by:

JULIUS M. LIM NELSON L. SAHOT


Senior Engineer A Acting Division Manager
KIPALIKU
Sto. Tomas, Davao

VOLUME ESTIMATES
NAME OF CANAL: TURN OUT 12
From Sta. 0 + 000.00 to Sta.
L= 219.78 m.
b= 0.40 m.
322 D= 0.50 m.
257.6 wall thickness = 0.10 m.
flooring thickness = 0.13 m.

A. Clearing and Grubbing


top width = 2.04 A = 219.78 x 2.04
A= 448.35 sq.m.

B. 170 kg/sqcm. Concrete


1. Canal
V = { [ ( 0.63 x 0.6 ) - ( 0.5 x 0.4 ) ] x 219.78 } - ( 0.2 x 0.1 x 0.1 x 2 x 38 )

V= 38.97 cu.m.

C. 211 kg/sqcm. Concrete


2. Strut
Strut Spacing = 6.00 m.
Strut width = 0.10 m.
Strut thickness = 0.20 m.
No. of Strut = 219.78 / 6
No. of Strut = 38 pcs.

V = 38 x [ ( 0.6 x 0.2 x 0.1 ) ]


V= 0.46 cu.m.

D. Gravel Blanket
V = 219.78 x 0.6 x 0.1
V= 13.19 cu.m.

E. Reinforcing Steel Bars


length 0.30 BAR DIAMETER CUTTING LENGTH
BAR MARK
vert. hor. no. of pcs ( mm. ) ( m. )
1.03 0.50 734.00 U-Bars 12 1.53
40 6.00 275.00 Longitudinal Bars 10 6.00
Strut
1.46 114.00 Longitudinal Bars 12 1.46
0.20 64.00 Lateral ties 10 0.20
TOTAL

F. Filter Drain
Every 4 meters
V = 0.15 x 0.20 x 0.40 x ( 1 + 219.78 / 4 ) x 2
V= 1.34 cu.m.

G. 38 mm Weephole
l.m. = 0.30 x ( 1 + 219.78 / 4 ) x 2
33.57 l.m.
11.19 pcs.
order, = 12.00 pcs.
l.m. = 36.00 l.m.

Prepared by:
KIPALIKU RIS
Sto. Tomas, Davao del Norte

0 + 219.78 CANAL SECTION

0.10 0.40 0.10

0.50
0.63

9.78 } - ( 0.2 x 0.1 x 0.1 x 2 x 38 )

170 kg/sqcm 0.13

Gravel Blanket 0.10


0.60

SEE PLAN FOR COMPLETE


STRUT DETAIL
0.60 0.10

0.10 211 kg/sqcm 0.20

PLAN SECTION
BAR LENGTH NO. OF LENGTHS
Kgs.
( m. ) ( pcs. )
9.0 147.00 1,174.82
6.0 275.00 1,016.40

6.0 29.00 154.51


6.0 3.00 11.09
TOTAL 2,356.82

Checked by: Approved by:

JULIUS M. LIM NELSON L. SAHOT


Senior Engineer A Acting Division Manager
KIPALIKU
Sto. Tomas, Davao

VOLUME ESTIMATES
NAME OF CANAL: TURN OUT 13
From Sta. 0 + 000.00 to Sta.
L= 737.41 m.
b= 0.40 m.
322 D= 0.50 m.
257.6 wall thickness = 0.10 m.
flooring thickness = 0.13 m.

A. Clearing and Grubbing


top width = 2.04 A = 737.41 x 2.04
A= 1,504.32 sq.m.

B. 170 kg/sqcm. Concrete


1. Canal
V = { [ ( 0.63 x 0.6 ) - ( 0.5 x 0.4 ) ] x 737.41 } - ( 0.2 x 0.1 x 0.1 x 2 x 124 )

V= 130.76 cu.m.

C. 211 kg/sqcm. Concrete


2. Strut
Strut Spacing = 6.00 m.
Strut width = 0.10 m.
Strut thickness = 0.20 m.
No. of Strut = 737.41 / 6
No. of Strut = 124 pcs.

V = 124 x [ ( 0.6 x 0.2 x 0.1 ) ]


V= 1.49 cu.m.

D. Gravel Blanket
V = 737.41 x 0.6 x 0.1
V= 44.24 cu.m.

E. Reinforcing Steel Bars


length 0.30 BAR DIAMETER CUTTING LENGTH
BAR MARK
vert. hor. no. of pcs ( mm. ) ( m. )
1.03 0.50 2,460.00 U-Bars 12 1.53
40 6.00 922.00 Longitudinal Bars 10 6.00
Strut
1.46 372.00 Longitudinal Bars 12 1.46
0.20 207.00 Lateral ties 10 0.20
TOTAL

F. Filter Drain
Every 4 meters
V = 0.15 x 0.20 x 0.40 x ( 1 + 737.41 / 4 ) x 2
V= 4.45 cu.m.

G. 38 mm Weephole
l.m. = 0.30 x ( 1 + 737.41 / 4 ) x 2
111.21 l.m.
37.07 pcs.
order, = 38.00 pcs.
l.m. = 114.00 l.m.

Prepared by:
KIPALIKU RIS
Sto. Tomas, Davao del Norte

0 + 737.41 CANAL SECTION

0.10 0.40 0.10

0.50
0.63

7.41 } - ( 0.2 x 0.1 x 0.1 x 2 x 124 )

170 kg/sqcm 0.13

Gravel Blanket 0.10


0.60

SEE PLAN FOR COMPLETE


STRUT DETAIL
0.60 0.10

0.10 211 kg/sqcm 0.20

PLAN SECTION
BAR LENGTH NO. OF LENGTHS
Kgs.
( m. ) ( pcs. )
9.0 492.00 3,932.06
6.0 922.00 3,407.71

6.0 93.00 495.50


6.0 7.00 25.87
TOTAL 7,861.14

Checked by: Approved by:

JULIUS M. LIM NELSON L. SAHOT


Senior Engineer A Acting Division Manager