Task 3
Manage project
information and
communication
BSBPMG535
Student Declaration
To be filled out and submitted with assessment responses
◻ I declare that this task and any attached document related to the task is all my own work and I have not
cheated or plagiarised the work or colluded with any other student(s)
◻ I understand that if I am found to have plagiarised, cheated or colluded, action will be taken against me
according to the process explained to me
◻ I have correctly referenced all resources and reference texts throughout these assessment tasks.
◻ I have read and understood the assessment requirements for this unit
Unit Title
Unit Code
Student name
Student ID
number
Student Date
signature
Task Number
DNS
Did the student satisfactorily:
N
Y
The student has satisfactorily completed
and submitted the following:
DNS
Did the student satisfactorily:
N
Y
Screenshot – policy and procedures
subfolder in Task 3.2A
Screenshot – project document
subfolders in Task 3.2A
Post-Project Review Report –
information and communication in Task
3.2B
Peer-Review outcome in Task 3.2C
Demonstrated ability to:
Manage generation, gathering, storage,
retrieval, analysis and dissemination of
information by project staff and
stakeholders
Implement, modify, monitor and
control designated information-
validation processes to optimise quality
and accuracy of data
Implement and maintain appropriate
communication networks
DNS
Did the student satisfactorily:
N
Y
Addressing of the Case Study (3
scenarios) in Task 3.1C
DNS
Did the student satisfactorily:
N
Y
can be assessed individually for all the
requirements of this task.
Student Name:
Assessor Name:
Assessor Signature:
Date:
Table of Content
Student Declaration................................................................................................................................................2
Task 3 – Manage and evaluate project information and communication..........................7
Task 3.1 Implement project information and communication processes..........................................9
Task 3.2 Assess information and communication outcomes.................................................................18
References................................................................................................................................................................20
With your project team, set up Slack to manage the project communication: www.slack.com .
1. Use the tool (Slack) to consult the team about setting up project team meetings.
Consult the team about the preferred meeting day, time, venue (for example, virtual team Vs
team in the office).
Provide a screenshot of the conversation about setting up team meetings from Slack
as evidence of the consultation:
2. Attach the meeting procedures, agenda and meeting minutes template (you can find it
in the policy and procedures folder) to one of your Slack messages to the team. Provide the
screenshot of the message with the attachments:
3. Take a screenshot of the Files page where the meeting documents are now saved for the
team to find.
Take a screenshot of the Files page once all the documents have been uploaded:
5. Ask the team to choose and retrieve one of the policies they have uploaded and discuss the
selected policy content in Slack. Would they add anything to the policy? What are the key
parts of the policy? Are they clear about the policy?
7. Analyse the poll results and send an email to the Project Sponsor informing them about the
results and asking for the team's equipment.
Use the template below to write the email. Note: you don't need to send the email, write the
email using Template 1.
(40-80 words)
Template 1 - Email
8. You have prepared the weekly project status report- we provide an excerpt below:
Project Name:
Project Status G: Y: R:
Overall Timeline Budget Resources Scope Quality Risk
Status
MMI Project
Prepared by: John Smith
Date: 20 May 20XX
Attention to Taylor Varin - Project Sponsor
Executive Carpeting behind schedule with classroom furniture arriving in five days.
summary Quality requirements for carpeting and classroom furniture met.
report If we consider the savings achieved with carpeting, the overall project budget is
on track.
Project team is working effectively.
Project is in scope.
No variations to previous reporting.
Carpeting Behind
Schedule
Classroom On schedule
furniture
• AS/NZS 4443:1997
Office panel systems-
Workstations
• AS/NZS 4438:1997
Height adjustable
swivel chairs
• Worksafe Officewise
2006
• AFRDI Level 6
Severe Commercial,
Blue Tick or
equivalent;
Quality
10 year structural /
manufacturing
warranty – 5-year
fabric warranty
Sustainability
Traceability of supply
chain of supplier
Sustainable
product
certification
schemes:
o SMaRT 4.0
Platinum/Gold
o AFRDI Green Tick
Level A/Plantium or
Level B/Gold
o GECA FFM v3.0-
2017
o GreenRate Level A
o FSC Certified Timber
products
Save the report in a word document and share it with the team using Slack. Provide a screenshot
of the message with the report shared in Slack:
Analyse the report and engage the team in a conversation about the report: what can be
done to ensure that the carpeting is completed before the furniture arrive?
9. Based on the conversation with the team, complete a change request form to send to the
project sponsor:
Change
Requested
Reason for
change
Impact on the
project
Record
Complete the filing record below so that the project document can be saved in the project management record system.
C) Case Study
Scenario 1 –
The project team is frustrated with one of the sponsor's decision.
One of the team members sends an email out, in error, to all stakeholders in the project email
address book expressing his opinion on the decision and using rude language. Moreover, his email
contains some sensitive information that should be kept confidential by the project team.
Determine the key issues associated with this incident, identify the impact on the project and
outline your actions to resolve the situation (50-1oo words):
Scenario 2 –
Some of the data provided by your team in their progress reports are not accurate.
Outline your actions to improve the information-validation process to optimise the quality and
accuracy of the data reported. (30-50 words)
Scenario 3 –
A) Record keeping
SUBFOLDER -Organise the XYZ policies and procedures (provided in a separate file) in a logical
manner using a sub-folder.
Provide a screenshot of how you have organised the policy and procedure folder:
o The project information and communication plan (create a word document using your work in
Task 2.1)
o The project progress report from task 3.1B9
o The change form (create a word document) from Task 3.1B9
Provide screenshots to show the sub-folders you created to file those documents and the files
within each sub-folder:
Review your work in Task 2 and 3, including what happened in the scenarios in Task 3.1 C.
Based on your review:
Determine the effectiveness of the management information and communication processes
and procedures.
Identify, and document lessons learned, and recommend improvements for application in
future projects.
Complete a post-project review report (Template 3)
Name of project:
Worked well
Brief summary of what worked well (40-80 words)
Lessons learned (Identify 3-4 lessons learned with the recommendation for improvement):
Review the Post-Project Review Report of a classmate (not in your project team).