Professional Documents
Culture Documents
Section 1.2 Elements of Cost Estimating: Introduction/Learning Objectives
Section 1.2 Elements of Cost Estimating: Introduction/Learning Objectives
Introduction/Learning Objectives
Cost estimating is of integral importance to the quality of the cost and scheduling program on any project.
The integrity of the cost estimate is of paramount importance to the success of a project and this is
ensured by the use of the appropriate cost estimating methodology. The cost estimate becomes the basis
for setting up the cost budget, resources and the ensuing progress and schedule monitoring processes
during project execution. To achieve this, a cost estimating basis/framework is necessary. The key learning
objectives are:
Cost estimates are important indicators for the economic evaluation of potential projects. However,
expectations and understandings of the various parties involved vary widely with respect to the
information available to prepare those estimates, the various methods employed during the estimating
process, the accuracy level expected from estimates, and the level of risk associated with estimates. A
strong system for classification of cost estimates provides a means of unifying the expectations of the
various parties interested in the estimates.
The AACE system for classifying estimates is identified in RP 17R‐97, Cost Estimate Classification System,
shown in Table 1. It is typical that a series of estimates will be prepared for a project, beginning with
ones based on less project definition, and progressing through Classes 5 to 1 as the level of project
definition increases. An organization may not necessarily prepare all classes of estimates for a single
project. The Introduction to this Study Guide lists other RPs for Cost Estimate Classifications within
other industries. Each are unique to that industry, but all are based on common principles.
The primary parameter for the classification of estimates within all applicable RPs is the maturity level
of project definition upon which the estimate is based. Other characteristics associated with estimate
classes include the purpose of the estimate (anticipated end usage of the estimate), methodology used
in development of the estimate, the accuracy of the estimate, and the relative effort required to
produce the estimate.
The same exact activity can be performed in twenty projects and the resulting actual cost may be
twenty different numbers. This is the reason that it is called estimating and not “actualizing.”
Historical estimating databases are developed by normalizing the information from past projects and
identifying the “most likely value” by plotting a distribution curve. The value in the database is usually
the most likely occurrence, not necessarily the one that should be used in the estimate. To determine
the best number to use you need to understand what causes variability in estimates.
Additional variability can come from location, quantity, waste, overtime, spoilage, loss, market
competition, and even the type of contract. All of these considerations need to be taken into account
in an estimate. When developed and evaluated properly these variables should be included in the direct
cost estimate, not as contingency.
Project and life cycle costing take estimating into the fourth dimension of time. Simply put, life cycle
costs are the sum of every cost incurred for a particular item (project, product, etc.) over its lifetime
from inception through disposal. It is necessary to estimate these costs over time at an assumed
escalation rate and then convert it to a present‐day value for comparing with other options.
The estimate scope begins with the design, construction, and startup costs. In the next phase it is
necessary to determine the cost of operation including raw materials, labor, general and administrative
(G&A), and other factors. It must include anticipated maintenance and perhaps improvement costs
over the life of the plant. The final stage is the dismantling and salvage value of the remaining asset.
Terms to Know
• Accuracy
• Accuracy Range
• Allowance
• Basis of estimate
• Bid/Tender Estimate
• Budget Estimate
• Cash flow
• Code of accounts
• Concept Study
• Conceptual Estimate
• Constructability
• Control Estimate
• Cost Estimate Classification System
• Cost Estimating Relationship (CER)
• Costing
• Definitive Estimate
• Detailed Unit Costs
• Deterministic (Detailed)
• Escalation
• Feasibility
• Labor Productivity
• Learning Curve
• Location Factor
• Normal Curve
• Order of Magnitude (Conceptual) Estimate
• Overhead
1. From the contractor’s perspective, which of the following is not a scope change?
A. A prolonged labor strike
B. A force majeure event
C. An error in the concrete take‐off
D. A project delay by the owner
4. Which of the following is recognized as the primary characteristic used in classifying estimates.
A. End usage or purpose of estimate
B. Level of project definition
C. Estimating methodology used in preparation of estimate
D. Expected accuracy range of estimate
2. B. Class 5
3. D. Definitive estimate