Professional Documents
Culture Documents
VPO - SAFE.3.1.07.05. Energized Electrical Works Permit
VPO - SAFE.3.1.07.05. Energized Electrical Works Permit
WORK PERMIT
SAFETY
Complete Below During Pre-Planning Meeting by electrically qualified persons performing the work.
Limited approach Boundary- ___Ft ___ in __ Work will be conducted within this
boundary.
Restricted approach Boundary-
Prohibited approach boundary-
___Ft ___ in __ Work will be conducted within this
boundary.
3. Required PPE: ATPV rating (in N/A (Cat 0) 8 cal (Category 1& 2) 40 Cal
cal/cm2) for AR clothing: (Category 3 & 4)
________________________________________
5. Justification for live work _________
request:
Shut down is infeasible due to design or
operational limitations (specify):
________________________________________
____________________________________
All questions must be answered “Yes” or “N/A” before any work can be
YES N/A
completed. Additional controls may be required.
2. Kirk-Key Interlocks are involved and procedures for their use are
understood
3. Confined Space entry is required and procedures for such entry are
understood.
6. The Zone Power Group has been contacted and comments regarding this
work have been received.
7. All special tools required to safely conduct this task have been identified.
(List the tools in Additional Control Methods section)
8. All special precautions required to safely conduct this task have been
identified
(List precautions in the Additional Control Methods section.)
All questions must be answered “Yes” or “N/A” before any work can be
YES N/A
completed. Additional controls may be required.
2. Have personnel been properly trained in all aspects related to the task(s)
to be performed?
Certification that this permit has been reviewed and the work can be completed safely.
Electrically
Qualified
Persons
participant
participant
participant
participant
participant
Supervisor Date:
A copy of the completed permit must be kept available for review at the work location.
The permit is valid for one (1) shift
(SOP and OPL must be in place to extend permit beyond 1 shift for NFPA 130.2(B)(1))
PERMIT CLEARANCE/CANCELLATION
All work has been completed / cancelled and the personnel and equipment have been withdrawn
from the area identified in the permit. The work area has been cleaned, inspected and the area is
ready for normal use / all hazards are removed or controlled. (circle one)
This permit is hereby cancelled.
Name of ABI Representative: Date:
Upon completion of work, the AB Person responsible for the work must retain the completed
Energized Electrical Work Permit for 30 days.
This Contractor Last Check must be completed for all work conducted on
equipment/processes with potential Exposure to Hazardous Substances by contractor
employees.
A Last Check must be performed by both the Contractor Safety Supervisor &
the responsible ABI Person.
The purpose of the Last Check is to verify the Risk Assessment was properly
completed and that the work area was reviewed. Any “NO” Answers Prohibit Work and
Requires that Additional Control Methods be Implemented.
Are the ABI employees that are working in the same area made aware of the work
done by the contractor?
In case several (sub) contractors work at the same time in the same area:
Is there a proper coordination between the concerned parties so that everybody is aware
of each others’ activities & hazards?
Signature Of Contractor
Safety Supervisor