Professional Documents
Culture Documents
Gravity Base Foundations For The Thornton Bank Offshore Wind Farm Terra115 3
Gravity Base Foundations For The Thornton Bank Offshore Wind Farm Terra115 3
INTRODUCTION The article starts with the development of possible locations for offshore wind farm
the project together with the contract development is limited. Following an
Concrete caisson foundations for offshore strategy that has been adopted. evaluation of near-shore projects, public
wind turbines have traditionally been Subsequently, the geotechnical and decision-making resulted in the designation
applied for wind farms close to shore, in geophysical site investigations are discussed in 2004 of a zone for the production of
relatively shallow and sheltered waters. and the design of the foundations is briefly electricity from wind, water or currents.
Steel monopiles on the other hand have summarised. The various construction Within this zone, C-Power’s preference was
become the semi-standard solution for phases are dealt with in the following for a location outside the 12-mile zone. The
turbine support structures for North Sea sections, starting with the onshore Thornton Bank, one of the many sandbanks
offshore wind farm developments to date. construction of the concrete structures, characterising the Belgian section of the
followed by the offshore preparatory North Sea, turned out to be the most
The present article deals with the design foundation works consisting of the appropriate location for the development
and construction of the Gravity Base dredging of foundation pits and the of a distant offshore wind farm.
Foundations (GBFs) for the Thornton Bank installation of foundation beds made up
Offshore Wind Farm, located some 30 km of crushed rock. An Environmental Impact Study was
off the Belgian Coast. The project owner submitted and an application for a Domain
has opted for the latest generation Onshore transport, offshore transport and Concession was submitted. In 2003, both
5MW turbines. This first commercial installation on site of the GBFs are the necessary environmental permit and the
application at this exceptional scale discussed next, followed by the backfilling domain concession for the project on the
represents a significant leap for the of the dredged foundation pits, the ballast Thornton Bank were granted. The required
offshore wind industry and also requires infill of the structures and the installation of building permits for the cabling works
a different approach for the foundation scour protection to ensure that adequate onshore and offshore were subsequently
structures. backfill remains in place. The article obtained between 2003 and 2006.
concludes with a description of the
offshore levelling works of the transition The Thornton Bank is located approximately
Sub Area B
flange on top of which the turbine towers 30 km from Zeebruges. The distance to
Th
e
Be
are to be mounted, followed by conclusions Ostend along the 150kV export cables
et
lg
he
iu
Sub Area A D6
m
D5
from the experience gained during the trajectories is 38 km.
rla
D4
nd
D3
D2 In
construction of the first six foundations.
s
D1 Co ter
K nc con
B AN er
to
ne
cto C-Power has opted for a split location
ON
R NT So
ut
rG
as which does not conflict with the Navy’s
THO h Pip
1
Te
le
eli
ne PROJECT DEVELOPMENT anti-mine and target practice areas and
co
150kV Export
m
Ca
which maintains a minimum distance of
Cable bl The Thornton Bank Wind Farm is the first 500 metres from the nearby telecom cables
e
offshore wind farm in Belgian waters and gas pipelines and from individual sand
(Figure 1). The project has been developed concession areas.
Navigation Channel
Crossing by C-Power, a project development
company owned by a variety of This results in 2 sub-areas, A and B, across
Navigation Channel
shareholders with different backgrounds. which a total of 60 Wind Turbine
These shareholders are DEME, a Contractor Generators (WTGs) are planned. Sub-area A
Group specialising in the fields of dredging is intended to accommodate 24 WTGs
and marine construction, SRIW Ecotech (4 rows of 6 WTGs each), whilst sub-area B
Navigation Channel Finance, the Environmental Holding caters for 36 WTGs (6 rows of 6 WTGs
Company of Walloon Investment Company, each). Sub-area A is located to the West of
SOCOFE, the Investment Company of the the Concerto South 1 telecommunications
PEC Telecom
Cable Crossing public administrations of the Walloon cable and sub-area B to the East of the
Region, NUHMA, an Investment vehicle for Interconnector Gas Pipeline.
PEC Telecom Cable
the participation in electricity and utility
Wenduine ventures and EDF Energies Nouvelles, a During the first phase of the project,
private company in which EDF holds 50% 6 WTGs were built on row D of sub-area A.
De Haan of the shares. The distance between these WTGs is
500 metres. The selected WTG is the
Bredene
Owing to the relatively small area of Repower 5M model with a rotor diameter
Oostende Belgian territorial waters and the large of 126 m, one of the largest and most
Figure 1. Location map of the Thornton Bank Project. number of limiting factors, the range of powerful wind turbines in the world,
Gravity Base Foundations for the Thornton Bank Offshore Wind Farm 21
KENNETH PEIRE
graduated in 1995 as an MSc in Civil specifically designed for offshore and construction of the Gravity Base
Engineering and worked as a Project installation. The rated power of the WTG is Foundations (GBFs). Within the consortium,
Engineer on the master plan for 5MW, which is achieved at a rated wind Dredging International is in charge of all
safeguarding Venice before joining speed of 13.0 m/s. Cut-in wind speed (at marine infrastructure works, whilst the
DEME in 1997 as a Superintendent. which the WTG starts power production) is transformer station and cable works
He then became Project Manager for 3.5 m/s (Beaufort scale 3), whilst cut-out onshore are for account of Fabricom GTI.
offshore oil & gas projects and speed is 30.0 m/s (Beaufort scale 11).
coordinated tenders in a variety of The detailed design of the GBFs has been
disciplines and business areas. For the Power production is controlled by electrical performed on behalf of Dredging
realisation of the first phase of the blade angle adjustment, resulting in pitch International by the Danish engineering
Thornton Bank Offshore Wind Farm he and speed control. The rotor consists of consultancy COWI. It includes, among other
was Project Manager Marine Operations. 3 blades, each of 61.5 m vane length and things, the design of the concrete
At present he is Engineering Manager rotates at 6.9 – 12.1 rotations per minute. structures and appurtenances, the design
for the second phase of the project. 33kV in-field cables ensure the connection of the gravel beds on which the GBFs are
between the turbines; a 150kV cable placed and the design of the ballast infill of
ensures the connection to shore. the GBFs.
HENDRIK NONNNEMAN
graduated in 1992 as an MSc in Tropical The total investment for the first phase of The detailed design has been developed on
Agriculture working on African the project amounts to approximately the basis of the Final Design Basis (FDB) and
development and irrigation projects € 150 million, whilst the overall project is of the Basic Design (BD) prepared by the
before joining Dredging International in anticipated to require an investment of Owner’s Engineer (OE), in which the overall
1998 as a Project Engineer. His € 850 million. Part of the investment of layout and dimensions of the support
assignments were in dredging, the first phase is to be depreciated over structures were defined. The Owner’s
remediation, wreck removal and the entire project. The expected annual Engineer (OE) is a joint venture between
revetment works in Europe. He then generation capacity of the wind farm Technum and IMDC from Belgium and
joined the Research Method and matches 6% of the total Belgian household DONG Energy from Denmark.
Estimating Department, Benelux consumption.
Division. He was Tender Coordinator and Other parties involved in the project are
Design Coordination Manager for the DNV Danmark A/S. as the Project
first phase of the Thornton Bank CONTRACT STRATEGY Certification body and SECO (Technical
Offshore Wind Farm and is presently Control Bureau for construction) with
Project Coordinator for Design and Build A multi-contract strategy has been adopted regard to the ten-year liability insurance
Projects in general and for Offshore for the realisation of the first phase of the policy.
Wind Farm Projects in particular. project. This approach was the result of a
number of tendering exercises, cumulating The project was financed through a non-
into the award, in spring 2007, of three recourse project-financing scheme with
ERIC BOSSCHEM main contracts with following scope: DEXIA as Mandated Lead Arranger and
graduated as an MSc in Electro- - The first contract has been awarded to Rabobank as Mezzanine Lender. This
mechanical Engineering and joined Seawind, a consortium between approach resulted in the involvement of
DEME’s Technical Department in 1976 to Dredging Marine and Electrical Mott MacDonald as Lenders’ Engineer, to
manage maintenance and repair for Infrastructure Works (MEC) which C-Power reports on a monthly basis.
several dredgers. Since 1980 he has - Design, Supply, Transport and Installation
managed diverse projects. As General of the WTGs (WTC) The weather risk included in the contract
Project Manager for the Thornton Bank - Supply and connection of the marine price is based on average weather statistics
Offshore Wind Farm he is responsible for export (150kV) and in-field (33kV) power and workability criteria for the vessels
the construction of the Gravity Base cables (ABB) envisaged for the execution of the works.
Foundations and associated Electrical Actual reimbursement of weather
Infrastructure. He previously held similar International and Fabricom GTI, whilst the downtime is based on equipment day rates
positions for the New Doha International second and third contracts have been and effectively incurred weather delays. For
Airport platform project and marine awarded to REpower and ABB respectively. each major vessel, criteria have been
infrastructure works at Le Havre’s Port The Marine and Electrical Contract (MEC) established beyond which reimbursement
2000 container terminal development. between the Seawind consortium and of vessel downtime is granted, provided
C-Power is of an Engineering, Procurement that the vessel was operational and ready
and Construction (EPC) nature and to work and did indeed incur downtime as
includes, among others, the detailed design a result of inclement weather conditions.
22 Terra et Aqua | Number 115 | June 2009
SITE INVESTIGATIONS performed from a work vessel. An extensive A 3D geological model was established on
laboratory testing programme was the basis of the seismic results, calibrated
A thorough site investigation programme performed by the Geotechnical Division of using the data from the geotechnical
was performed in 2004, consisting of a the Ministry of Mobility and Public Works campaign. In general the following soil
geotechnical and a geophysical part. The six of the Flemish Government. layers can be distinguished (from top to
turbine locations of phase 1 were covered, bottom):
including the offshore transformer station The geophysical investigation consisted of - Coarse to medium dense sand with a
and the meteo-mast locations and the bathymetric surveys of the seabed using gravelly horizon at the bottom, thickness
cable trajectories offshore and onshore. Multi Beam Echosounder (MBE), Side Scan 10 metres
Sonar Surveys (SSS) to obtain a - Stiff clay (tertiary layer), at the bottom a
The geotechnical investigation comprised morphological image of the seabed and to transition to more silty or sandy material,
borings with undisturbed sampling, borings detect any obstacles present, Seismic thickness 10 metres
for pressure meter testing and cone Surveys to assess the subsoil’s Quaternary - Dense sand, slightly silty to clayey,
penetration tests with the measurement of and Tertiary layers and Magnetometric thickness 3 metres
pore water pressures (CPTU), all performed Surveys to detect any metallic objects - Very to extremely dense (aged) slightly
from a jack-up platform. In addition, (wrecks, anchors, UXO,…) at or below the silty to clayey fine sand with seams or
vibrocore borings and seabed CPTUs were seabed. pockets of clay, thickness 8 metres
- Stiff tertiary clay down to the end of the
boreholes.
DESIGN
The weight of each individual GBF varies These dimensions, combined with the INSTALLATION OF FOUNDATION BEDS
between 2,800 and 3,000 tonnes. Per GBF, orientation of the pits (heading +/- NE-SW
an average of 1,085 m³ of concrete was along the main axis), were inspired by the As one of the most important interfaces in
used and some 215 tonnes of reinforce- prevailing current directions. the project, the foundation bed ensures
ment steel. The concrete complies with that the stresses induced in the base plate
compression strength class C45/55, Dredging of the foundation pits was of the GBF remain within acceptable limits.
environment class ES4 and consistency class executed in two stages, using the recently The foundation bed also creates a first,
S3. Gravel used in the concrete has a 0-22 commissioned, state of the art trailing crucial level for achieving the specified
mm grading, whilst the cement type is Cem suction hopper dredger (TSHD) Brabo with verticality of the turbine towers and further
III HSR 42.5 LA. Cement was used at a an 11,650 m³ hopper capacity (Figure 4): ensures that the weight of each GBF is
ratio of 450 kg/m³, with a water/cement 1st stage: Bulk dredging: removal of the properly transferred to the subsoil.
factor of 0.36. Post-tensioning tendons, sand dunes and the top layer of the
32 pieces, each of 1770 MPa tensile foundation pit. The foundation beds consist of two layers:
strength, are applied between platform 2nd stage: Precision dredging: removal of a circular filter layer from the dredged level
level and anchorage blockouts on the bottom layer of the foundation pit up to 0.55 m below foundation level,
the lower part of the inner side of (a layer thickness of approximately 1 metre) followed by a circular gravel layer up to
the conical section. to realise a surface within specified vertical target foundation level. Specifications were
tolerances. as in Table II.
The construction of the GBFs was
performed by MBG as a sub-contractor to Precision dredging was only executed in The installation of the foundation beds was
Dredging International. An average of 135 favourable sea conditions in which the performed using the Dynamically Positioned
working days was required for completion vertical movement of the drag head of the Fallpipe Vessel (DPFV) Seahorse. The vessel
of each GBF. TSHD was limited. Multi-beam echosounder is a DP Class 2 vessel with a rock loading
(MBE) surveys, performed from a dedicated capacity of 18,000 tonnes.
survey launch, were scheduled at least once
DREDGING OF FOUNDATION PITS a day per foundation pit in order to closely
monitor progress and accuracy.
At each offshore turbine location, a
foundation pit was dredged to a depth of All dredged materials consisted of medium
some 7 metres below the surrounding loose to very dense sands, which were
seabed. The target level for these dredging disposed of within the concession area at
works was 1.30 metres below the target 3 disposal locations, each at some
foundation level, which in turn was 300 metres from the foundation pits. In
subsequently obtained through the order to limit dispersal of materials, these
construction of gravel foundation beds. disposal locations were defined between the
crests of the sand dunes that are present in
The foundation pits measured 50 m x 80 m the area. The identification of these Figure 5. Visualisation of D1 foundation bed level,
at the bottom and had slopes of 1:8 along locations was subject to approval of the 1.30 m above the surrounding bottom of the dredged
the main axis and of 1:5 across the width. authorities (MUMM) and duly considered pit (4x enhanced vertical scale)
Gravity Base Foundations for the Thornton Bank Offshore Wind Farm 25
Figure 7. Two views of the lowering of the GBF, in front of quay wall and on its way out to sea.
The weights of the GBFs just fit within the Prior to lift off, the GBFs were physically Backfill operations around the GBF
lifting capacity of the Rambiz. Once loaded, weighed with an accuracy of less than structures were performed with sands
and when the GBF was clear from the quay 0.5% in order to be sure that the weight dredged from the nearby disposal areas,
wall, the GBF was lowered below the water requirements for the Rambiz were met and which originated from the dredging of the
table prior to leaving the entrance channel to determine the structures’ Centre of foundation pits. Specifications for the
to the port of Ostend (Figure 7). As soon as Gravity (CoG). This allowed for a site backfill were as in Table III.
the vessel reached deeper waters, the GBF decision whether the GBFs would be
was further lowered down to 10 metres installed heading NW or SE. It was The requirement for a very low fines
below the water table. preferred to have the CoG nearer to the content was achieved by using sand that
Rambiz as this allowed for verticality has been dredged twice (once during the
On location, the Rambiz was brought and correction by means of the tugger lines. dredging of the foundation pits, and once
maintained into position by means of when dredging the same materials from
4 flipper delta anchors of 7 tonnes each. During the engineering phase, extensive the disposal areas for backfilling purposes)
To allow for sufficient and equal suspension physical model tests were carried out by by means of TSHDs. Each time the material
of the crane hooks and as such increasing the Danish Hydraulic Institute (DHI), whilst
stability during the lowering of the GBF, numerical modelling was performed by
the GBF was ballasted with water. MARIN. Dedicated current measurement
campaigns were performed prior to and
Highly accurate LRK positioning systems during the installation works in order to
were installed in both crane booms of the compare the actual conditions on site
Rambiz, whilst an electronic inclination against the models. The entire operation
measurement device was mounted at the has been scrutinised by DNV as Marine
top of the GBF. Four echo sounders near Warranty Surveyor for the project.
the base plate of the GBF allowed the
assessment of the position of the GBF
with respect to the gravel bed during BACKFILL OF FOUNDATION PITS
the lowering operations. The achieved
installation offsets from target centres were Backfill denotes the filling of the dredged
on average about 0.5 metres, whilst the foundation pits following the installation of
inclination of the installed structures the GBFs. The requirement for backfilling is
averaged 0.10° (Figure 8). dictated by the geotechnical stability of the
structures. As a result, erosion protection is
During the entire construction period, a equally important to ensure that the
detailed weight management system was required amount of backfill material can be
implemented, respecting both DNV and ISO guaranteed throughout the design life of
standards, in order to control weight the structures.
progress of the GBFs. Part of this operation
included 3D volume scans, material
weighing and listing, and so on. Figure 8. The GBF D1 in the water after installation.
Gravity Base Foundations for the Thornton Bank Offshore Wind Farm 27
is dredged and deposited in the hopper BALLAST INFILL The Vlaanderen XXI is a 1,750 m³ TSHD
well, the fines are being washed out by the that was recently converted for supplying
vessel’s overflow system. Samples taken The requirement for ballast infill of the GBF marine sand and aggregates for the
from inside the hopper well prior to the also originates from the geotechnical building materials market. As a result, it is
backfilling, confirmed compliance with design. The required amount of infill is provided with on board drainage pumps to
these specifications. closely linked with the design of the backfill drain the dredged mixture and with a
and, as a result, with the design of the materials handling crane for offloading the
The TSHD Jade River was deployed for erosion protection that covers the backfill. materials to shore or onto other vessels or
dredging the backfill materials. The dredged Design assumptions for the infill sands were barges. For the purposes of the hydraulic
materials were spread hydraulically in the unit weights of 15.80 and 19.24 kN/m³ for infill works, the Vlaanderen XXI moored
foundation pits by means of a purpose-built sand above, respectively below water level. alongside the Thornton 1, each time
spreader barge, the Thornton 1, which was Laboratory tests on dredged sand samples positioned adjacent to one of the GBF
also equipped for carrying out the ballast confirmed these assumptions to be structures, for transfer of the materials
infill and the scour protection works conservative. into the hold of the barge.
(Figure 9). The connection between
spreader barge and TSHD was done via The infill of the GBFs was executed in 2 Pumping of sand from the Thornton 1 into
a self-floating pipeline of approximately stages: the GBF was performed in a controlled
300 metres length, coupled to the TSHD 1. Hydraulic infill: Materials dredged at the way, limiting the pump flow. For structural
via a common bow connection system. disposal locations by means of the TSHD design reasons, the mixture density was to
Vlaanderen XXI were pumped into the be kept below 13 kN/m³. In order to bridge
The Thornton 1 is provided with a 12-metre GBF via a dedicated infill tower on board the difference in level between the deck of
wide diffuser spray pipe for spreading of of the Thornton 1. the Thornton 1 (level fluctuating with the
the sand across the foundation pits 2. Dry infill: Upon completion of the tidal range) and the top of the GBF
according to a controlled layer pattern. hydraulic infill and settlement of the (level +17 m TAW), an infill tower was
The outlet of this spray pipe was kept at a materials, dry infill was executed with conceived, reaching several meters above
fixed height of approximately 1 to 2 metres sands. the top of the GBF.
above the intended spraying level of the The hydraulic infill activities were separated
backfill layer, and was continuously and into two distinct phases: A total volume of approximately 2,000 m³
automatically corrected for tidal changes. 1. Dredging of the infill materials by means was required for the infill of each GBF. Two
of the TSHD Vlaanderen XXI, and hopper loads of the Vlaanderen XXI were
The tracks of the Thornton 1 are pre- 2. Subsequently the hydraulic pumping of required to achieve this.
defined, whilst hauling speeds are based the materials into the GBF using the The GBFs were filled hydraulically up to the
on multi-beam survey data collected multi-purpose barge Thornton 1, target level of +14.50 m TAW, following
immediately prior to sailing the relevant previously deployed for the backfilling which the infill mass was drained down to
tracks and on on-line velocity and works. MSL. When the water level inside the GBF
concentration measurements of the
mixture pumped by the TSHD.
had decreased and the sand had further bottom fill, whilst the remaining infill was The barge’s position-tracking features and
settled, dry infill (using dredged sand) was executed with dredged sands up to final automotive movements along pre-defined
used to make up for the loss of volume and level. All operations at GBF D6 were tracks are also available in “fallpipe mode”.
to complete the infill up to the design level performed from a jack-up platform. The A belt weighing device is included in the
of +14.50 m TAW. These dry infill works same infill approach was to a certain extent system, allowing the continuous monitoring
were performed as a separate activity using adopted at some of the other locations in of the rock quantities transferred and
the jack-up platform that was deployed at these instances, however, dictated by installed. This data serves as input for the
a later stage for the levelling and grouting operational priorities. computer-controlled movements of the
of the transition piece on each GBF. barge along pre-defined rock placement
tracks.
For GBF D6, the entire infill operation was SCOUR PROTECTION
performed using “dry materials”. This
approach was adopted since, as a result of Around each GBF, a scour protection GBF COMPLETION WORKS
slightly less favourable underlying soil system has been conceived, providing
conditions, the geotechnical design called protection for the backfill materials against The transition level for installation of the
for part of the infill to be performed with the impact of currents and waves. The wind turbine towers was to be provided
heavy minerals. Infill with these heavy design consists of a filter and armour layer within a tolerance of 0.25° from horizontal
ballast materials was performed first as of quarried rock materials (Figure 10). level which is the specified vertical
Gravity Base Foundations for the Thornton Bank Offshore Wind Farm 29
conceived to correct any inclination of the Figure 10. General scour protection lay-out.
GBF (Figure 12).
2m
33/150kV cable
the WTG supplier, following which the backfill
REFERENCES