Professional Documents
Culture Documents
WORK SCHEDULE - Final Work Schedule of Phase 1 - 9132023
WORK SCHEDULE - Final Work Schedule of Phase 1 - 9132023
WORK SCHEDULE - Final Work Schedule of Phase 1 - 9132023
TALAMPAS
LOCATION B1 L15 PHASE 8, AYALA GREENFIELDS ESTATES, CALAMBA, LAGUNA SUBJECT WORK SCHEDULE - PHASE 1
1 2 3 4 5 6 7 8
NO. DESCRIPTIONS WT%
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29
1.0 General Requirement
1.1 Mobilization/ Demobilization 0.88% 0.44% 0.44%
1.2 Transportation of workers, Supervisions and Site Inspection 1.95% 0.24% 0.24% 0.24% 0.24% 0.24% 0.24% 0.24% 0.24%
1.3 Temporary Facilities 0.60% 0.60%
Safety & Health, Personal Protective Equipment, and
1.4 0.47% 0.24% 0.24%
Housekeeping
1.5 Utilities, Water and Electrical Bill 0.12% 0.02% 0.02% 0.02% 0.02% 0.02% 0.02% 0.02%
2.0 Site Development - 0.00%
2.1 Surveying, Gridline, Structural & Masonry Layout 0.16% 0.08% 0.08%
2.2 Excavation 2.21% 0.44% 0.44% 0.44% 0.44% 0.44%
2.3 Backfill and Compaction 1.21% 0.40% 0.40% 0.40%
2.4 3/4" Gravel Bedding on soil surfaces 1.53% 0.77% 0.77%
2.5 Soil Poisoning & Termites Treatment 0.96% 0.96%
2.6 Disposal of Construction Debris 0.98% 0.12% 0.12% 0.12% 0.12% 0.12% 0.12% 0.12% 0.12%
2.7 Retaining Wall and Shear Wall - 0.00%
2.7.1 Reinforcement 5.38% 0.00% 2.69% 2.69%
2.7.2 Formworks 0.40% 0.00% 0.20% 0.20%
2.7.3 Concrete Works (Class A; 3000psi) 0.96% 0.00% 0.96%
2.7.4 Plastering 0.29% 0.00% 0.15% 0.15%
2.7.5 Waterproofing 0.00% 0.00% 0.00%
2.7.6 Skim Coating of Walls 0.17% 0.00% 0.17%
3.0 Main Structure - 0.00%
3.1 Structural Works - 0.00%
3.1.1 Reinforcement - 0.00%
3.1.1.1 Footing 1.19% 0.00% 0.60% 0.60%
3.1.1.2 Footing Tie beam 2.65% 0.00% 1.32% 1.32%
3.1.1.3 Column 6.94% 0.00% 2.31% 2.31% 2.31%
3.1.1.4 Beam 6.07% 0.00% 2.02% 2.02% 2.02%
3.1.1.5 Slab 2.41% 0.00% 1.20% 1.20%
3.1.1.6 Stairs 0.34% 0.00% 0.17% 0.17%
3.1.2 Formworks - 0.00%
3.1.2.1 Footing Tie beam 0.46% 0.00% 0.46%
3.1.2.2 Column 2.50% 0.00% 0.83% 0.83% 0.83%
3.1.2.3 Beam 3.26% 0.00% 1.09% 1.09% 1.09%
3.1.2.4 Slab 0.18% 0.00% 0.09% 0.09%
3.1.2.5 Stairs 0.77% 0.00% 0.39% 0.39%
3.1.3 Concreting (Class A; 3000psi) - 0.00%
3.1.3.1 Footing 1.61% 0.00% 1.61%
3.1.3.2 Footing Tie beam 0.93% 0.00% 0.93%
3.1.3.3 Column 2.32% 0.00% 1.16% 1.16%
3.1.3.4 Beam 2.73% 0.00% 0.91% 0.91% 0.91%
3.1.3.5 Slab 4.51% 0.00% 2.26% 2.26%
3.1.3.6 Stairs 0.79% 0.00% 0.39% 0.39%
3.4 Vapor Barrier Installation 0.22% 0.00% 0.22%
3.5 Steel Framing on roof - 0.00%
3.5.1 Roof Framing 5.76% 0.00% 2.88% 2.88%
3.5.2 Painting 0.45% 0.00% 0.45%
3.6 Masonry Works - 0.00%
3.6.1 6" CHB 5.22% 0.00% 0.87% 0.87% 0.87% 0.87% 0.87% 0.87%
3.6.2 Plastering 9.19% 0.00% 1.02% 1.02% 1.02% 1.02% 1.02% 1.02% 1.02% 1.02% 1.02%
3.7 Exterior Paved Area (Driveway, Stairs, Lanai & Utility) - 0.00%
3.7.1 Reinforcement 0.39% 0.00% 0.19% 0.19%
3.7.2 Formworks 0.28% 0.00% 0.14% 0.14%
3.7.3 Concrete Works (Class A; 3000psi) 0.58% 0.00% 0.29% 0.29%
3.8 Elevator / Lift -
3.8.1 Excavation 0.01% 0.01%
3.8.2 3/4" Base Coarse 0.00% 0.00%
3.8.3 Reinforcement 0.36% 0.36%
3.8.4 Formworks 0.11% 0.11%
3.8.5 Concreting 0.30% 0.30%
3.8.6 Structural Frame 0.94% 0.94%
3.8.7 Steel Frame Painting 0.04% 0.04%
3.8.8 CHB Laying 0.33% 0.16% 0.16%
3.8.9 Plastering 0.54% 0.18% 0.18% 0.18%
4.0 Electrical Works - 0.00%
4.1 Roughing Ins and Boxes (Emerald Brand) - 0.00%
4.1.1 Conduit and Fittings 2.79% 0.00% 0.56% 0.56% 0.56% 0.56% 0.56%
4.1.2 Boxes 0.25% 0.00% 0.13% 0.13%
4.2 Panel Board, ECB, & MTS - (SCHNEIDER CIRCUIT BREAKER BRAND) - 0.00%
MCCB: PANEL 'MDP', 1-PHASE, 2-WIRES + GROUND, 230V,
4.2.1 0.61% 0.00% 0.61%
60HZ
4.2.2 MCCB: PANEL 'DP', 1-PHASE, 2-WIRES + GROUND, 230V, 0.47% 0.00% 0.47%
MCCB: PANEL 'PP', 1-PHASE, 2-WIRES + GROUND, 230V,
4.2.3 0.41% 0.00% 0.41%
60HZ
MCCB: PANEL 'LP', 1-PHASE, 2-WIRES + GROUND, 230V,
4.2.4 0.39% 0.00% 0.39%
60HZ
MCCB: PANEL 'EP', 1-PHASE, 2-WIRES + GROUND, 230V,
4.2.5 0.61% 0.00% 0.61%
60HZ (ATS TYPE)
4.2.6 ECB 2P-600AT, 35KAIC, 230V, 60HZ NEMA 4X ENCLOSURE 0.20% 0.00% 0.20%
4.2.7 ECB 2P-50AT, 14KAIC, 230V, 60HZ NEMA 3R ENCLOSURE 0.08% 0.00% 0.08%
4.2.8 ECB 2P-40AT, 14KAIC, 230V, 60HZ NEMA 3R ENCLOSURE 0.42% 0.00% 0.42%
4.2.9 ECB 2P-30AT, 14KAIC, 230V, 60HZ NEMA 3R ENCLOSURE 0.53% 0.00% 0.53%
4.4.4 INSTALLATION AND POWER TAPPING OF GENERATOR SET 0.39% 0.00% 0.39%
Prepared by:
Submitted by:
Conforme: