STOP
Revision # 0
Issue Date 2023-10-16
Next Revision Date TBD
PV-P-PRM-001-0 Page 1 of 4
Assigned Dept: 110 (PM2) PV area: 6163 Main Work Center: 10ET-TAI
(PRTECH)
Frequency: 3MON Time to Complete: 4 hours Shutdown Required: YES
□ An open work permit Open Permit #: ____________
This work is covered by:
□ A new work permit Permit Board #: ____________
Acceptance:
I have reviewed the work permit and carried out the required risk assessment. I have received the
necessary training and have been deemed competent to accomplish safely and correctly the required
tasks associated with this work instruction.
Document Register
Register identification Type Location Retention period
Maintenance Planning Permanent.
Process Plant MWI Register Copy/filing cabinet
office Latest version is kept.
Permanent:
Livelink Electronic IT server
All versions are kept.
Permanent
RCMCost Electronic IT server
Latest version is kept
Revision History
Task Details
PV9-6163-PPP005B (PUMP #2 FEED CCD WASH WATER)
Not Not
Task Description OK
OK Complete
Observations
Verifique la guarda del acoplamiento y del abanico del
motor, si presenta daño o falta de pernos. Reparar y
completar tornillería debidamente torqueada si es □ □ □
necesario.
Verifique que el eje gire libremente, el elemento de rejilla, el
hub por desgaste y cover del acople. Cambiar si es necesario. □ □ □
Verifique el gap de los hub, los liner o suplemento del motor
y la alineación de los ejes bomba-motor. Usando □ □ □
comparador de reloj o equipo de alineación laser.
Asegúrese que el sello mecánico se encuentre en buen
estados y que no haya obstrucción en la línea de agua del □ □ □
sello.
Maintenance Work Instruction Code: 6163 3M PPP005B MECH
STOP
Revision # 0
Issue Date 2023-10-16
Next Revision Date TBD
PV-P-PRM-001-0 Page 4 of 4
Additional Resources: