Annexure I - Price Schedule

"Rate card for Erection of PV Module & Tracker System for Renewable Energy Park" near village
Khavda, Taluka - Bhuj, District - Kutch, Gujarat.

Quantity Amount
Sr. No Standard Item Description Unit 1 Block Rate
1 Block
(12.5 MW)

Loading and transporting from store to site and


Erection of Mounting Mounting structure in proper
alignment and level as per detailed drawing
including Columns, Rafters, C-Channels/ Purlins,
Tortube, Nuts and Bolts, Fastners, Shim Plates, Cleat,
Clips, Bearing assembly and Motor assembly,
Aluminium clamps etc as applicable and in such a
1.00 way that the installed modules are not under any
kind of stress including essential appropriate
transports, labours required tools and machines etc
complete for installtion in all respect as per
Technical Specification and Direction of Engineer in
Charge.
Average Distance of transportation from Store shall
be 4 Km

1.01 Fabricated Module supporting structures MT 554 3,300 18,28,200

Loading and transporting from store to site, erection


and installation of PV Module, fixing of all parts in
proper alignment and in proper level in accordance
with “Installation Manual” of module manufacturer
and ensuring that the installed modules are not
2.00 under any kind of stress, including skilled labors,
tightening of fasteners with required tools,
machines etc for complete for installtion in all
respect as per Technical Specification and
Directions of Engineer in Charge.
Modules shall be placed at one location in the block.

2.01 Solar Module (Approx.) Nos 30,045 33 9,91,489

Total Basic Price (in Rs.) 28,19,689

Note:
1) Module shall be provided at one location in the block by Employer.
2) MMS shall be loaded, transported & unloaded by Contractor from employer store and average lead
distance of 4 km to be considered
"Rate card for Erection of PV Module & Tracker System for Renewable Energy Park" near
village Khavda, Taluka - Bhuj, District - Kutch, Gujarat.

Tracker Erection

Schedule of Manpower and machinery for Installation of Tracker for One (01)
(A)
Block. (Completion Period - 20 Days)

Sr. No. Description UoM Resource Required

Engineers, supervisor, skilled & semi-skilled


1 Nos 60
labour and helper

2 Tractor with Trolley Nos 2

3 Crane / Farana - New Generation type only Nos 1

Module Erection

Schedule of Manpower and machinery for Installation of Modules for One (01)
(B)
Block (Completion Period - 15 Days)

Sr. No. Contractor Manpower UoM Resource Required

Engineers, supervisor, skilled & semi-skilled


1 Nos 60
labour and helper

2 Tractor with Trolley Nos 1

3 Fork Lift Nos 2