EMPLOYER’S REPRESENTATIVE

700 MW ZUNGERU HYDROELECTRIC POWER PROJECT


WEEKLY SITE ACTIVITY REPORT INCLUDING PHOTOS (ATTACHMENT 3)

Date Range: 22- 28 JAN, 2023 Week No.: 04 Project Commencement Date: 27-Sep-13

Weather : Sunning Precipitation Range: Temperature Range: 27 to 37

CONSTRUCTION CHALLENGE & TECHNICAL ISSUE FACED

ACTIVITY CHALLENGE/ISSUE
ITEM Section Head/ Engineer in Charge
(PROGRESS STATUS) (QUALITY OF WORK, SPEED CORRECTIVE ACTION
OF WORK, METHOD OF PROPOSED/TAKEN
WORK)
1.0 General
Release of Water from the Reservior for the Safety of the Dam:
Water release commenced on 10th January 2022, Initially used the bottom outlet
gate , then the spillway radial gate#3. All the gates have been completely closed but
so far the water released is about (3,734.0 x 10 6 m³) through bottom outlet and
Spillway towards the tailrace channel. - See attachment 2 (Att2 - Discharge
Calculation) for details.

Dam Performance:
Mohamed/Charles/Dayo
As at the end of this reporting week, the water storage in the reservoir is at about
99.61%. The maximum dam water leakage, according to the design and
specification for this dam, is 120 litres/sec. Currently the Dam Total water leakage
is at 10.71 litre/sec :- (1.898 litres/sec from ACRD righbank, 1.649litres/sec from
upstream construction joints and 3.694litre/sec from downstream bedrock
drainage system), which is about 7.5% of the design value.
With this, the Dam is performing excellently well. However, the repairs works are
still ongoing on the leakage holes to further reduce the water leakage.

1.1 DAM CONSTRUCTION

1.1 RCC DAM

1.1.1 Bottom Outlet (Block 23)

The permanent bottom outlet is incorporated inside Dam Block 23 at El 155 with a
4m diameter steel liner. The steel liner was already fully encased with reinforced
concrete.
Kunle/Banjo/Dimeji
Below is the activitiy during the week under review
- casting of columns and parapet of the permanent bottom hole hoist room

1.1.2 Diversion Channel Plugging

The concrete plugging of the diversion channel work commenced with the
submittal of necessary documents including the drawings and method statements
of both the concreteing and the various grouting procedures by the CSC, which was
appoved with status A by the ER with letter number ZUN-2021-05-21- ER 2037. Self- Kunle/Banjo/Dimeji
compacting concrete is used for the last lifts of each sections. The plugging work
commenced and reported as follows.
CONSTRUCTION CHALLENGE & TECHNICAL ISSUE FACED

ACTIVITY CHALLENGE/ISSUE
ITEM Section Head/ Engineer in Charge
(PROGRESS STATUS) (QUALITY OF WORK, SPEED CORRECTIVE ACTION
OF WORK, METHOD OF PROPOSED/TAKEN
WORK)

Block 26

- Completed Kunle/Banjo/Dimeji

Block 27

- Completed
Kunle/Banjo/Dimeji
For further concrete casting details refer to Attachment 1, Table 12.

1.1.4 Dam Impoundment (Water Level Monitoring)

Dam impoundment continued this week under review, measures were taken to
ensure the safety of the dam through daily observation of the installed instruments.
An electric water level meter is being used to monitor the changes in the water
level. During this week, the water level increased by 0.48 with an average rate of
(0.069m/day) due to the closure of all spill-way gate sand bottom outlet. The water Mohamed/Charles/Dayo
level is currebtly at elevation 228.65m. The volume of the reservoir is at 9353.7
(10⁶ m³), while the specific area capacity is 377.09 km2. The present percentage
storage volume is at 99.61%. See Att 2 - Impoundment for details

1.1.5 Instrumentation, Monitoring & Installation

Routine dam foundation monitoring and observation was carried out during the
week by observing the various installed instruments such as jointmeter, rod
extensometer, multiple point extensometer, thermometer, Crackmeter,
piezometer, pressure and stress cell at block 12 , 20, 33,39, power house & Right
abutment Rock fill Dam upstream and downstream to check the situation of the
dam. The V-notch weir in the gallery are checked weekly to accurately measure the Mohamed/Charles/Dayo
flow of water leakages in the gallery. The main inspection part include dam body,
dam foundation and dam abutment.The pendulum systems (hanging and
inverted),and the wire alignment instrument is faulty and under repair. During the
week under review, no new instrument was installed

1.1.6 Consolidation n Grouting

Achievement rate is at 100%


Mohamed/Charles/Dayo

1.1.7 Curtain Grouting

A-RCC Dam Curtain Grouting :- Achievement rate is 100%.

B-ACRD- Curtain Grouting :- Achievement rate is 100%. Mohamed/Charles/Dayo

1.1.8 Drainage system (Bedrock Drainage/Pressure relief holes)

Drilling of bedrock drainage hole has been completed. achievement rate is 100%.
See attachment 2 of bedrock drainage holes for details. Mohamed/Charles/Dayo

1.1.9 Roller-Compacted Concrete (RCC) and General Dam CVC activities


CONSTRUCTION CHALLENGE & TECHNICAL ISSUE FACED

ACTIVITY CHALLENGE/ISSUE
ITEM Section Head/ Engineer in Charge
(PROGRESS STATUS) (QUALITY OF WORK, SPEED CORRECTIVE ACTION
OF WORK, METHOD OF PROPOSED/TAKEN
WORK)

1.1.9.1 RCC Placement and Related Activities

RCC placement is being continued sequentially in all RCC blocks since 22 January
2018.
RCC was placed in the following list of blocks during the week under review;
RCC placement for the whole dam has been completed since February 2021.
CVC casting at dam crest at both left bank and right bank have been relatively
completed from El 231.00 to 232.90m.
Banjo/kunle/Dimeji
The following activities were done during this reporting week

- Casting of drainage ditch around Water treatment equipment room at the


downstream of block 47#

For further concrete casting details refer to Attachment 1, Table 12.

1.1.9.2 Dam Crest Parapet wall and Floor Finishing

The construction of Dam crest parapet wall commenced on the 10th of


January,2022 compliance with the submitted and revised respective drawing
letters: CSC-CSLT-ZP-3955-2022 (Pavement Layer Structure of Dam Crest), CSC-CSLT-
ZP-3095-2020 ( Dam Crest Railings and Lighting Reserved Pit Layout for RCC Dam),
CSC-CSLT-ZP-3892-2021 (Dam Crest Railing Layout of Asphaltic Core Rockfill Dam).

The following activties were executed during this week under review;

- No concreting Dimeji

Other preliminary activites continues, such as;


- Installation of reinforcement, construction joint and PVC waterstop in between
the construction joints
- Cleaning and installation of formworks
- Curing

1.2.1 Foundation Excavation


Foundation excavation of the Rockfill Dam at the (right & left ) Abutment is 100%
completed Amande

1.2.2 EMBANKMENT GALLERY and Concrete Plinth WORKS

Casting of concrete plinth and gallery is 100% completed for both left and right
ACRD. Amande

1.2.3 Rockfill Embankment Construction (ACRD) Right-Bank

Placement of Rock-fill at the Right-bank area of the dam was completed to


EL234.00m in January 2022.

Sequel the heavy down pour on the 8th of April, 2022 at the 700MW Zungeru
Hydro-Electric power project site accompanied with a wind of 24.7m/s, some part
Amande/ David
of the upstream riprap surface was swept off.
Reference to the submitted letter CSC-CSLT-ZP-3999-2022
Within this reporting week, the riprap repair activity within El. 228.00 - 234.500m
has been completed
CONSTRUCTION CHALLENGE & TECHNICAL ISSUE FACED

ACTIVITY CHALLENGE/ISSUE
ITEM Section Head/ Engineer in Charge
(PROGRESS STATUS) (QUALITY OF WORK, SPEED CORRECTIVE ACTION
OF WORK, METHOD OF PROPOSED/TAKEN
WORK)

1.2.4 Rockfill Embankment Construction (ACRD) Left-Bank

During this reporting week the following activities were done;

-Placement, spreading and compaction of phyllite ballast ≤40cm spanning RCC


block 60# through leftbank ACRD block D8# from El.233.900 - 234.500m. Amande/ David
-Placement, spreading and compaction of granite ballast ≤50mm spanning RCC
block 60# through leftbank ACRD block D8# from El.234.500 - 234.800m.

1.2.5 ASPHALT CORE

(Right-Bank) ASPHALT CORE


Placement of asphalt core at the right bank for the project was completed on 22nd
May, 2021 from RCC block7 spanning through to ACRD block B37 at EL. 234.00m

(Left-Bank) ASPHALT CORE


Placement of asphalt core at the left bank for the project was completed on 7th
Amande/David
April, 2021 from RCC block60 spanning through to ACRD block D8 at EL. 234.00m

NOTE : Placement of asphalt core for the project is 100% completed.

1.2.6 BACKFILLING BETWEEN RCC DAM AND POWER HOUSE

Backfilling between RCC Dam and Power House with phyllite(rockfill) commenced
on 12th June 2021.
Work has being executed as follows :
1. Between LHS slope and penstock No.1,
from EL 158.250 to 159.000m................................completed
2. Between pentstock No.1 & 2,
from EL 157.000 to 159.000m................................completed Amande/ David
3. Between penstock No.2 & 3,
from EL 158.250 to 159.000m............................... completed
4. Between penstock No. 3 & 4,
from EL 158.250 to 159.000m............................... completed
5. Between penstock No. 4 and RHS slope,
from EL 157.000 to 159.000m................................completed

2.0. POWERHOUSE

2.1 Concrete Work

The civil work construction is being carried out at Power House since mid of
November 2018. Currently first stage concrete for draft tube foundation below El
123.5 and concrete for tail water gate piers is being cast for all Power House Units.
The seepage collection pit was also under construction.
Civil work design drawings below El. 159.3 was reviewed by ER and then
construction work above El. 123.5 was commenced accordingly at Unit 1, Unit 2,
Kunle/Banjo
Unit 3 and Unit 4.
For ease of casting concrete, each Unit is subdivided into three zones separated by
construction joints.
Zone I - from upstream rock face to DH 0+123.325(First stage concrete)
Zone ll - The Middle part (second stage concrete)
Zone III - from DH 0+123.325 to 0+146.000(First stage concrete)
CONSTRUCTION CHALLENGE & TECHNICAL ISSUE FACED

ACTIVITY CHALLENGE/ISSUE
ITEM Section Head/ Engineer in Charge
(PROGRESS STATUS) (QUALITY OF WORK, SPEED CORRECTIVE ACTION
OF WORK, METHOD OF PROPOSED/TAKEN
WORK)

1. Unit #1
The following main activities were carried out during the week under review;

- No concreting activities Kunle/Banjo


For further concrete casting detail refer Attachment 1, Table 13.

2. Unit #2
The following main civil work activities was performed during the week under
review.
- No concreting activities Kunle/Banjo
For further concrete casting detail refer Attachment 1, Table 13.

3. Unit #3

The following main activities were carried out during the week under review;

- No concreting
Kunle/Banjo/Dimeji
- Formwork and reinforcement was being fixed for other part of the Unit in
preparation for casting.
For further concrete casting detail refer Attachment 1, Table 13.

4. Unit #4

The following main activities were performed during the week under review;

- Casting of generator floor leveling course concrete from El. 143.450 – 143.500m Kunle/Banjo/Dimeji

For further concrete casting detail refer Attachment 1, Table 13.

5. Seepage Collection Pit -

Seepage and drainage collection pit is located at the right end of the Power House
Building where DV:1+588.35 ~ 1+598.85; DH: 0+097.50 ~ 0+125.00 and invert level
Kunle/Banjo
is at El. 106.00
This activity has been completed since June 2019.

6a. Erection Bay, Central Control Building


Erection Bay is located on the left side of Unit 1 where is DV: 1+699.76 ~ 1+742.35;
DH: 0+099.00 ~ 0+125.00 and at floor level is 159.25m.
The following activities was carried out during the week under review.

- No concreting Kunle/Banjo

- For further concrete casting detail refer Attachment 1, Table 13

6b. Power house layout and Dam structures(Turbine oil tank room, Transformer
oil building, Cable trench and diesel generator building,)
General layout structural drawing of power house area revision 3 was submitted in
July 2021 with drawing numbers D-HS-PT-765 R3 to D-HS-PT-767 R3 and all the
associated structural works has commenced since August 2021.
The following activities was carried out during the week under review.

- Casting of 37nos. of concrete cover plate of the diesel generator room Kunle/Banjo/Dimeji

- For further concrete casting detail refer Attachment 1, Table 13


CONSTRUCTION CHALLENGE & TECHNICAL ISSUE FACED

ACTIVITY CHALLENGE/ISSUE
ITEM Section Head/ Engineer in Charge
(PROGRESS STATUS) (QUALITY OF WORK, SPEED CORRECTIVE ACTION
OF WORK, METHOD OF PROPOSED/TAKEN
WORK)

7. Tailrace Apron

Construction of Tailrace Apron was commenced mid of March 2019. The following
activities were performed during the week under review;
- Concrete activities has been completed 100% on tailrace walls and Apron in the Kunle/Banjo
previous week.
For further concrete casting detail refer Attachment 1, Table 13.

8. Intake l-1 (Penstock)


Construction of Penstock was commenced on the 24th October 2019.
A revised drawing R1 for concrete lift of the encased concrete of penstock of RCC
blocks 31 to 34 was submitted with a letter CSC-2944 dated on 11 December 2019.
The following activities were performed during the week under review;
- Casting has been completed here during the previous week, except for zone B, Kunle/Banjo
lift B-10.
For further concrete casting detail refer Attachment 1, Table 13.

9. Intake I-2 (Penstock)


Construction of Penstock was commenced on the 24th October 2019.
A revised drawing R1 for concrete lift of the encased concrete of penstock of RCC
blocks 31 to 34 was submitted with a letter CSC-2944 dated on 11 December 2019.
The following activities were performed during the week under review;
- Casting has been completed here during the previous week, except for zone B,
lift B-10. Kunle/Banjo
- Inspection of internal surface repair in preparation for wet testing.
- Formwork and reinforcement fixing is ongoing on the upper bend of the penstock
zone C, in preparation for casting.
For further concrete casting detail refer Attachment 1, Table 13.

10. Intake l-3 (Penstock)


Construction of Penstock was commenced on the 24th October 2019.
A revised drawing R1 for concrete lift of the encased concrete of penstock of RCC
blocks 31 to 34 was submitted with a letter CSC-2944 dated on 11 December 2019.
The following activities were performed during the week under review;
- Casting of penstock l-3, lift C - 8 from elevation 205.2m - 209.5m. Kunle/Banjo
- Casting of penstock l-3, lift C - 9 from elevation 209.5m - 213.0m.
For further concrete casting detail refer Attachment 1, Table 13.

11. Intake l-4 (Penstock)


Construction of Penstock was commenced on the 24th October 2019.
A revised drawing R1 for concrete lift of the encased concrete of penstock of RCC
blocks 31 to 34 was submitted with a letter CSC-2944 dated on 11 December 2019.
The following activities were performed during the week under review;
- Casting of penstock l-4, lift C - 3 from elevation 192.0m - 195.0m.
For further concrete casting detail refer Attachment 1, Table 13. Kunle/Banjo

4.0 Spillway
Construction activities of the Spillway Structure has been completed on the 12th of
December 2021.
A revised drawing R5 for concrete lift and zone was submitted with a letter CSC-
2965 dated on 22 December 2019. Referring to the drawing, the side piers in block
18 and 22 are tagged as Pier #1 and Pier #5 respectively and the middle piers in
block 19, block 20 and block 21 are also tagged as Pier #2, Pier #3 and Pier #4
respectively.

The construction activities of the spillway structure from Pier 5, pier 4, pier 3, pier
2 and pier 1 respectively (RCC Dam block 22# through block 17#) has been
Kunle/Banjo/Dimeji
completed.

- on the 12th of August, 2022 CSC submitted a letter - CSC-CSLT-ZP-4053-2022 with


a subject: Submit of Inspection Report of Spillway chutes and bottom outlet
concrete and Method statement of repairing the spillway chutes and bottom outlet
concrete.

- In compliance to the submitted method statement the spillway chute defect hole
was casted.
CONSTRUCTION CHALLENGE & TECHNICAL ISSUE FACED

ACTIVITY CHALLENGE/ISSUE
ITEM Section Head/ Engineer in Charge
(PROGRESS STATUS) (QUALITY OF WORK, SPEED CORRECTIVE ACTION
OF WORK, METHOD OF PROPOSED/TAKEN
WORK)

5.1 Powerhouse - Hydro-Mechanical Works

Unit #1
Presently, the load wet commisionninng test of unit 1# is ongoing.

During this week under review unit 2#, 3# and 4# are at halt after the no-load wet
commissioning tests and awaiting load tests.

Unit 4#:
No activity during the week of reporting. Amanuel, Gbenga, Aremu, Rotimi

A- Distributor Assembly:
Access to the distributor area has been locked and no activity during the week of
reporting.

B- Bearings:
No activity during the week of reporting.

Powerhouse Central Control Room

No hydro-mechanical activities during the week reporting. Amanuel, Gbenga, Aremu, Rotimi

Powerhouse -

Routine general cleaning continues to be carried out at:


- Powerhouse Wall
The interior and exterior parts of the powerhouse wall were cleaned.
Amanuel, Gbenga, Aremu, Rotimi
- Powerhouse Equipment
Dusting and cleaning were carefully carried out on some of the equipment inside
the powerhouse.

Installation and Status of Gates - HM


A- Spillway:
Spillway service gate no. 1# is in open position and while service gates 2#, 3# & 4#
are in the closed position. The contractor are expected resume and complete the
anti-corossion activities of service gates 1# (upstream side).

B- Bottom Outlet:
The bottom outlet maintenance gate and service gate are in the closed position.

D. Quick - Acting Emergency Intake Gates of Unit1 - Unit4: Amanuel, Gbenga, Aremu, Rotimi
Quick acting emergency intake gates no. 2#-4# are in the closed position. While,
gate 1# is in the open position purposely for conveying water to the runner.

E- Tailrace Gate:
Tailrace gates no. 1#- 4# are in the open position.

5.2 Shipment of Hydro-electromechanical equipment

Amanuel, Defar, Gbenga, Adeolu,


During the week of the report, no hydro-electromechanical equipment delivery has
Aremu, Rotimi
been reported by the EPC Contractor.
Isaac and Femi
CONSTRUCTION CHALLENGE & TECHNICAL ISSUE FACED

ACTIVITY CHALLENGE/ISSUE
ITEM Section Head/ Engineer in Charge
(PROGRESS STATUS) (QUALITY OF WORK, SPEED CORRECTIVE ACTION
OF WORK, METHOD OF PROPOSED/TAKEN
WORK)

5.3 Unit Auxiliary


A. IPB Welding Activity:
No activity during the week of reporting.

B. Water and Oil Pipes:


Unit 1# - 4#:
Installation of oily - wastewater separation Purifier has been completed.

C. Compressed Air System:


i. Unit 1#- 4#:
No activity during the week of reporting.

D. Firefighting System: Amanuel, Gbenga, Aremu, Rotimi


Units fire-fighting system pipes installation and their colour making at the
powerhouse area is being continued.

E. Main Transformer:
No activity during the week of reporting.

F. Heating, Ventilation, and Air Conditioning System (HVAC):


Fabrication and assembly of HVAC pipes at the floors El. 152.5, and El. 143.5 are
ongoing. Thus, assembly of air ducts at all floors are being continued.

5.8 Overhead Traveling Crane and Gantry Crane

i. Powerhouse overhead ( 250/50T + 250/50T) bridge crane:


The crane is in operation. Platform construction in preparation for the power intake
gate gantry crane painting in progress.

ii. Intake 500kN/ 2*160kN Gantry Crane:


No-load operational tests of the gantry crane are already completed. The
contractor is expected to conduct load tests. Now, anti-corossion of power intake
gantry cane is ongoing. Amanuel, Gbenga, Aremu, Rotimi

iii. Spillway 1600kN Gantry Crane:


No-load operational tests of the crane are already completed. The contractor is
expected to conduct load tests

iv. Tailrace 2* 500KN Gantry Crane:


The crane is in operation.
CONSTRUCTION CHALLENGE & TECHNICAL ISSUE FACED

ACTIVITY CHALLENGE/ISSUE
ITEM Section Head/ Engineer in Charge
(PROGRESS STATUS) (QUALITY OF WORK, SPEED CORRECTIVE ACTION
OF WORK, METHOD OF PROPOSED/TAKEN
WORK)

6.1 Powerhouse - Hydro-Electrical Works and & commissioning Tests

- Unit 1 #
A. Unit 1 Load Test commissioning:
The following test were carry out during the connection to the grid commissioning

i. Synchronization of Generator with power grid (Auto and manual


Synchronization).
Before and during the synchronization test; the voltage phases (338kV - 340kV) and
frequency ( 50Hz) of the unit and that of the grid were checked and valve were in
normal range .
a. Auto synchronize test; Unit started in no load state, governor system in electric
manual mode and the generation command was sent via LCU and the synchronism
started. In addition, the unit voltage and frequency were adjusted automatically
and when the voltage different, phase angel value and frequency are less than the
setting value the GCB closed automatically.

b Manual Synchronization test; When the voltage value, phase angel value and
frequency value difference are more than the setting value, the voltage and
frequency values were adjusted manually. Also, when the voltage amplitude value,
frequency value and phase value difference between the unit and the power grid
were less than the fixed values , the GCB was manually closed to enable its
connection to the grid.

ii. Load increase test (From 0% to 100%). Defar/Adeolu/Sunny/Isaac/Femi/N


Unit start up, Auto synchronized to close GCB and it was connected with the grid, urudeen
during this process Governor changed to electric manual mode, and guide vanes
was slowly open to increase load to 30%, thus the guide vane decreased load
minimum value and changed to auto mode.
Likewise load increase test 0% - 100% controlled by SCADA by 10% increase for each
step, every step run for each 15 min, Record for the vibration and swing were also
taken.

iii. Unit heat running at rated output;


When the water level was at rated water head, the heat running test was carried
out, the unit was running for 2 hour and bearing pad temperature was recorded for
every half hour until value of temperature rising is less than 1 Celsius in one hour.

iv. Load rejection test at 25%, 50%, 75% and 100%; The Unit Automatic start to
connect with the grid by sending command from SCADA to open the GCB, The unit
is subjected to load rejection test at P= 25%, 50%, 75% and 100% were done
respectively; the unit run for 15min in each load point, 1GCB was used to reject
load. Thus, record was taken before, during and after the rejection, Also Run out
and vibration data during the load rejection test were recorded.

6.2
Grounding system

No activities during the week of reporting. Defar/Adeolu/Sunny/Isaac/Femi/N


urudeen
6.3 Auxilairy Electrical Equipment Installation
No activity of cubicle during the week of this report.
Defar/Adeolu/Sunny/Isaac/Femi/N
6.4 Pipes - (Conduit Pipes ) Hydro-Electrical
Defar, Adeolu, Isaac,
No activity of cubicle during the week of this report.
Femi/Nurudeen

7.0 Transmission Lines and Switchyard

7.1.1 Switchyard (Zungeru)/L2 Road - Civil works

Civil works
i. 132kV / 330kv Zungeru Switchyard:
- Cleaning and cable trenches slope correction Banjo/Kunle /Dimeji
- For further concrete casting detail refer Attachment 1, Table 13

7.1.2 Switchyard (Zungeru) - Electrical works & Test:


Zungeru Switchyard: 330kv side
No major activity
Sunny/Defar/Adeolu/Isaac
Zungeru Switchyard: 132kv side /Femi/Ozigi
No hydro-mechanical activities during the week of reporting.
CONSTRUCTION CHALLENGE & TECHNICAL ISSUE FACED

ACTIVITY CHALLENGE/ISSUE
ITEM Section Head/ Engineer in Charge
(PROGRESS STATUS) (QUALITY OF WORK, SPEED CORRECTIVE ACTION
OF WORK, METHOD OF PROPOSED/TAKEN
WORK)
Zungeru Switchyard: 330kv side
i.Preparation for commissioning on going Sunny/Defar/Adeolu/Isaac
Zungeru Switchyard: 132kv side /Femi/Ozigi
i. Preparation for commissioning on going

7.2.1 Transmission lines - 330KV/132KV - CIVIL WORK

i. Backfilling of JB02 legs B and leg D.


Kunle/Banjo/Kabiru/
Dimeji
7.2.2 Transmission lines - 330KV - ELECTRICAL WORKS

i). Installation of conductors from tower JA1 to JA2 completed ii)


Installation of all lines accessories completed iii)
Replacement of conductors and lines accessories for the vandalized part completed
iv.) OPGW splicing and testing completed
Sunny/Defar/Adeolu/Isaac
v.) Earth Resistance of Towers completed vi)
/Femi/Ozigi
Energizing of the line from Triple Point to Zungeru was successful
vii) Installation of Towers JA11 and JA15 for Shiroro/Jebba Line 2 is on going.

7.3 Transmission lines - 132KV - ELECTRICAL WORKS


There is no work in the week in question
Sunny/Defar/Adeolu/Isaac
/Femi/Ozigi

7.4.1 Tripple Point Switchyard (Minna) - Civil Works


I. Tripple Point Switchyard located at Gusase, Maraba about 26km from Minna,
Niger state. Civil works commenced on the 18th of May,2021 with the submittal of
necessary documents including the drawings by CSC Under letters with Ref
numbers CSC-CSLT-ZP-3600, 3605, 3606, 3608, 3609, 3594.
Construction activities resumed on the 9th of May,2022. The contractor sent an
official letter to the Employers Representative under letter with refrence number
CSC-CSLT-ZP-4003-2022, dated 9th May, 2022. The following construction activities
were carried out during the week under review;
- Curing of road pavement from chainage K0+090m - K0+230m. Kunle/Banjo/Kabiru
- Filling of rip-rap for side slopes protection around inlet and outlet of culvert area
continued at chainage K0+220m - K0+250m.
- Installation of steel mesh fence countinued round maintenance workshop
building.
- landscaping ongoing for floor of septic tank of central control building.
- Casting of road pavement continued from chainage K0+000 - K0+100 from
El.274.800m - 275.000m.

7.4.2 Tripple Point Switchyard (Minna) - Electrical Works

Tripple Point Switchyard (Minna):


Sunny/Defar/Adeolu/Isaac
i. Shiroro/Jebba Transmission Line 1 commissioned
/Femi/Ozigi
ii Completed pre-commissioning test for Water Treatment Plant

8.0 Quality control of fresh concrete

During the week under review, the quality testing of CVC concrete was followed up
by checking the temperature, air content, unit weight, slump, wet density of fresh
concrete, (diffussion of self-compaction concrete). the Cubes were also cast in
order to determine their compressive strength at 7, 28 and 90 days respectively .
Dunni
Details are given in table 1 of the attachment 1. In the same vein, the compressive
strength of hardened concrete at their required age were also followed up as
shown in table 3 of the attachment 1. All test results for compressive strength
after 28 days for CVC within the specification limits
CONSTRUCTION CHALLENGE & TECHNICAL ISSUE FACED

ACTIVITY CHALLENGE/ISSUE
ITEM Section Head/ Engineer in Charge
(PROGRESS STATUS) (QUALITY OF WORK, SPEED CORRECTIVE ACTION
OF WORK, METHOD OF PROPOSED/TAKEN
WORK)

8.1 Equipment Calibration

No activity during the week under review Dunni

8.2 Reinforcement
During this weak New consignment of diameter 12 Reinforcement Steel were
collected from the steel yard. One group sample was taken to ascertain .The
physical and mechanical Properties of the material. Test conducted include bend
test, tensile strength And elongation at maximum stress. All tests result so far meet Dunni
technical requirements.

8.3 Cement/Flyash

Routine tests on cement such as fineness, standard consistency specific gravity,


soundness and setting time were carried out on Lafarge cement. In the same vein
nine number of cement mortar cubes were cast in order to determine their
Dunni
compressive strength at 3, 7 and 28 days. Also, the compressive strength of
hardened mortar cubes at their required age were follow up. Details are given in
the table 9 of the attachment 1.

8.4 Aggregates

Weekly tests on aggregate like sieve analysis, specific gravity, flakiness and
elongation were carried out on aggregate of various sizes ranging between (0-5mm,
5-20mm, 20-40mm and 40-80mm). The material was sourced from Shamuyambo Dunni
granite quarry and sampled at RCC crushing plant conveyor belt. All test results
comply with ASTM Standard.

9.0 Health, Safety and Environment (HSE)

i. ER and the Contractor conducted a joint safety inspection and potential hazards
were identified and corrective actions were also implemented.
ii. Proactive safety measures are being adopted by both the ER, CSC and the labour
force to duely observe COVID-19 protocol such as washing of hands, using of hand
The Contractor will continue to
sanitizer, wearing of nose mask and maintaining social distance where possible.
identify known and unknown
iii. Damaged and unsafe work tools and equipments were identified during safety
Daramola Charles/ Dayo Adesiyan hazards and make
walks and immediate replacement made by the contractor
improvements to any safety
iv. CSC have been adviced to ensure that all the working area at night are well
issues raised
illuminated and also, make available an anti-venom for snake bite in case of any
emergency.

v. The contractor continues to ensure appropriate safety awareness for workers at height at
the power house, erection bay, spillway and power intake structure. Also, during the week
under review, corrective actions were implemented immediately for observed potential
hazards.
vi. The Contractor continued to monitor improvement in safety measures at all other The contractor has since then
project locations. Daramola Charles/ Dayo Adesiyan clear the surrounding to forestall
vii. No case of life threatening accident was recorded during the week. further occurrence.
viii. There was an incidence of fire outbreak at CNEEC warehouse II, on saturday the 12 th of
februar 2022. The fire was emanated from magazine area up to the warehourse 2 where
some items was affected by the fire.
Attachment 1 - Conc & Earth Work
Ta+B2:N16ble 1: Follow up of CVC Fresh Concrete

Air Content
Slump Test (mm) Temperature (OC)
S/no Sample No. Casting Date Unit Location Elevation Concrete Grade Mix Design No:
Require Actual Air Con (%)

Road pavement of rockfill dam on the left


1 R-9336 13/06/2022 Dam
bank C-A-11
/ C25 PC-20 100-160 145 25.7 24.4 2.9

2 R-9337 13/06/2022 Comprehensive work area Prefabricated cover plate / C25 PC-24 100-160 155 28.6 26.2 3.0

Road pavement of rockfill dam on the left


3 R-9338 13/06/2022 Dam
bank C-10B
EL234.8~EL235.0 C25 PC-20 100-160 145 25.7 24.4 2.9

4 R-9339 13/06/2022 Dam Sand retaining sill A-8-9 wall / C20 CVC-67 50-100 65 32.4 27.1 2.6

Road pavement of rockfill dam on the left


5 R-9340 14/06/2022 Dam
bank C-3B-7B
/ C25 PC-20 100-160 150 27.4 26.0 2.9

6 R-9341 14/06/2022 Comprehensive work area Prefabricated cover plate / C25 PC-24 100-160 140 30.7 26.8 3.1

Phase Ⅱconcrete of plant 4# equipment


7 R-9342 14/06/2022 powerhouse EL136.91~EL137.96 C30 PC-25 100-160 150 26.4 26.0 3.2
foundation

8 R-9343 15/06/2022 Dam Dam crest pavement 19# / C30 PC-21 100-160 145 25.3 25.6 3.0

9 R-9344 15/06/2022 Dam Sand retaining sill A-7 wall / C20 CVC-67 50-100 65 25.6 22.4 2.6

Road pavement of rockfill dam on the left


10 R-9345 15/06/2022 Dam / C25 PC-20 100-160 140 30.6 24.1 2.9
bank C-10B、C-10D

11 R-9346 15/06/2022 Comprehensive work area Prefabricated cover plate / C25 PC-24 100-160 145 31.0 24.4 2.9

12 R-9347 16/06/2022 Dam Dam crest pavement 21# / C30 PC-21 100-160 140 27.6 26.3 3.1

Road pavement of rockfill dam on the left


13 R-9348 16/06/2022 Dam / C25 PC-20 100-160 135 27.9 26.0 3.0
bank B-2、B-4、B-6

14 R-9349 16/06/2022 Comprehensive work area L2 road drainage ditch wall / C25 PC-20 100-160 155 28.7 24.5 2.9

15 R-9350 16/06/2022 Comprehensive work area Prefabricated cover plate / C25 PC-24 100-160 145 29.1 23.7 3.1

Upper day section C-7 of powerhouse 3#


16 R-9351 16/06/2022 powerhouse
penstock
EL204.0~EL207.5 C25 PC-9 120-180 165 25.9 24.3 3.1

Upper day section C-7 of powerhouse 3#


17 R-9352 17/06/2022 powerhouse
penstock
EL204.0~EL207.5 C25 PC-9 120-180 165 21.9 23.6 3.0
18 R-9353 17/06/2022 Dam Wave wall of 21# EL232.9~EL234.0 C25 PC-20 100-160 135 23.0 24.2 2.9

19 R-9354 17/06/2022 Comprehensive work area Prefabricated cover plate / C25 PC-24 100-160 110 24.5 25.8 2.9

20 R-9355 18/06/2022 Dam Wave wall of 21# EL235.1~EL236.2 C25 PC-20 100-160 135 25.8 24.8 2.9

21 R-9356 18/06/2022 Dam Dam crest pavement 17#18# / C30 PC-21 100-160 130 26.0 25.4 3.2

Road pavement of rockfill dam on the left


22 R-9357 18/06/2022 Dam / C25 PC-20 100-160 135 26.1 24.9 2.9
bank B-8、C-10

23 R-9358 18/06/2022 Comprehensive work area Prefabricated cover plate / C25 PC-24 100-160 135 27.9 25.3 2.9

24 R-9359 19/06/2022 Dam Fire pool installation room fire buttress / C20 PC-19 100-160 155 25.8 25.1 2.6

25 R-9360 19/06/2022 Dam Dam crest pavement 20# / C30 PC-21 100-160 120 26.9 25.6 3.0

Road pavement of rockfill dam on the left


26 R-9361 19/06/2022 Dam
bank D-11
/ C25 PC-20 100-160 130 27.2 25.4 2.8

27 R-9362 19/06/2022 Comprehensive work area Prefabricated cover plate / C25 PC-24 100-160 140 28.9 26.0 3.0

Table 3 Follow-up of CVC Compressive Strength

S/no Sample No: Casting Date Unit Location Elevation Concrete Grade Mix Design No: Crushing Date Age (Days) Ave. Compressive strength (MPa)

1 R-9311 07/06/2022 Comprehensive work area Prefabricated cover plate / C25 PC-24 14/06/2022 7 20.1

Road pavement of rockfill dam on the left


2 R-9312 07/06/2022 Dam
bank 6#10#
/ C25 PC-20 14/06/2022 7 19.9

Cooler foundation of main machine room


3 R-9313 07/06/2022 powerhouse
of plant 2#
EL158.8~EL159.2 C30 PC-21 14/06/2022 7 22.7

4 R-9314 08/06/2022 Dam Wave wall of 18# dam section EL232.9~EL234.0 C25 PC-20 15/06/2022 7 22.4

5 R-9315 08/06/2022 Dam Sand retaining sill A-4 wall / C20 CVC-37 15/06/2022 7 22.2

6 R-9316 08/06/2022 Comprehensive work area Prefabricated cover plate / C25 PC-24 15/06/2022 7 24.8

Road pavement of rockfill dam on the left


7 R-9317 09/06/2022 Dam
bank
EL232.9~EL234.0 C25 PC-20 16/06/2022 7 23.1

8 R-9318 09/06/2022 Comprehensive work area Prefabricated cover plate / C25 PC-24 16/06/2022 7 22.5
9 R-9319 08/06/2022 Dam Sand retaining sill A-7 cushion / C20 CVC-67 15/06/2022 7 24.9

10 R-9320 09/06/2022 Comprehensive work area L2 floor of road drainage ditch / C25 PC-20 16/06/2022 7 23.4

11 R-9321 09/06/2022 Dam Sand retaining sill A-7 cushion / C20 CVC-64 16/06/2022 7 21.5

Road pavement of rockfill dam on the left


12 R-9322 10/06/2022 Dam / C25 PC-20 17/06/2022 7 21.6
bank A-9、A-12

13 R-9323 10/06/2022 Dam Sand retaining sill A-4 wall / C20 CVC-67 17/06/2022 7 23.4

14 R-9324 10/06/2022 Comprehensive work area Prefabricated cover plate / C25 PC-24 17/06/2022 7 23.6

Upper day section A-6 of powerhouse 3#


15 R-9325 11/06/2022 powerhouse
penstock
EL201.0~EL204.0 C25 PC-9 18/06/2022 7 23.3

Upper day section A-6 of powerhouse 3#


16 R-9326 11/06/2022 powerhouse
penstock
EL201.0~EL204.0 C25 PC-9 18/06/2022 7 21.8

17 R-9327 11/06/2022 Comprehensive work area Prefabricated cover plate / C25 PC-24 18/06/2022 7 27.4

18 R-9328 11/06/2022 Dam Sand retaining sill A-5 wall / C20 CVC-67 18/06/2022 7 23.0

Road pavement of rockfill dam on the left


19 R-9329 11/06/2022 Dam / C25 PC-20 18/06/2022 7 22.9
bankB-9、C-A-14

20 R-9330 11/06/2022 Comprehensive work area Switchyard station fire water pipe buttress / C20 PC-19 18/06/2022 7 20.0

21 R-9331 11/06/2022 Dam Sand retaining sill A-8 cushion / C20 CVC-67 18/06/2022 7 22.8

Upper day section A-6 of powerhouse 3#


22 R-9332 11/06/2022 powerhouse
penstock
EL201.0~EL204.0 C25 PC-9 18/06/2022 7 20.5

Road pavement of rockfill dam on the left


23 R-9333 12/06/2022 Dam
bank C-A-13
/ C25 PC-20 19/06/2022 7 18.8

24 R-9334 12/06/2022 Comprehensive work area Prefabricated cover plate / C25 PC-24 19/06/2022 7 24.6

25 R-9335 12/06/2022 powerhouse Plant 3# EL148.65~EL151.25 C25 PC-24 19/06/2022 7 24.7

Road pavement of rockfill dam on the left


26 R-9336 13/06/2022 Dam
bank C-A-11
/ C25 PC-20 20/06/2022 7 22.8

27 R-9337 13/06/2022 Comprehensive work area Prefabricated cover plate / C25 PC-24 20/06/2022 7 24.6
Road pavement of rockfill dam on the left
28 R-9338 13/06/2022 Dam
bank C-10B
EL234.8~EL235.0 C25 PC-20 20/06/2022 7 21.9

29 R-9339 13/06/2022 Dam Sand retaining sill A-8-9 wall / C20 CVC-67 20/06/2022 7 19.1

30 R-9216 17/05/2022 Dam Rockfill dam crest highway EL234.8~EL235.0 C25 CVC-29 14/06/2022 28 36.9

31 R-9217 17/05/2022 Dam Dam crest pavement 43#~48# EL232.9~EL233.0 C30 PC-21 14/06/2022 28 43.5

32 R-9218 17/05/2022 Comprehensive work area Prefabricated cover plate / C25 PC-24 14/06/2022 28 26.2

33 R-9219 18/05/2022 CSCEC Switchyard network room floor ramp / C25 PC-24 15/06/2022 28 28.5

34 R-9220 18/05/2022 Dam Dam crest pavement 40#~42# EL232.9~EL233.0 C30 PC-21 15/06/2022 28 41.3

35 R-9221 18/05/2022 Dam Fire pipeline pier / C20 PC-19 15/06/2022 28 25.3

36 R-9222 18/05/2022 Dam Dam crest pavement 17# EL232.9~EL234.0 C30 PC-21 15/06/2022 28 32.9

37 R-9223 18/05/2022 Comprehensive work area Prefabricated cover plate / C25 PC-24 15/06/2022 28 26.3

Upper day section C-9 of powerhouse 2# 29.4


38 R-9224 18/05/2022 powerhouse
penstock
EL210.0~EL213.0 C25 PC-9 15/06/2022 28

39 R-9225 19/05/2022 Dam Dam crest pavement 48#~50# EL232.9~EL233.0 C30 PC-21 16/06/2022 28 41.5

40 R-9226 19/05/2022 Dam Wave wall of 53# dam section EL232.9~EL234.0 C25 PC-20 16/06/2022 28 32.5

41 R-9227 19/05/2022 Dam Wave wall of 59# dam section EL232.9~EL234.0 C25 PC-20 16/06/2022 28 32.8

42 R-9228 19/05/2022 Comprehensive work area Prefabricated cover plate / C25 PC-24 16/06/2022 28 26.0

43 R-9229 19/05/2022 Dam Fire pipeline pier / C20 PC-19 16/06/2022 28 26.4

44 R-9230 19/05/2022 Comprehensive work area Switchyard T5-T7 brick wall / C25 PC-20 16/06/2022 28 28.0

45 R-9231 20/05/2022 Dam Dam crest pavement 38#~40# EL232.9~EL233.0 C30 PC-21 17/06/2022 28 40.8

46 R-9232 20/05/2022 Dam Dam crest pavement 38#~40# EL232.9~EL233.0 C30 PC-21 17/06/2022 28 42.9
47 R-9233 20/05/2022 Comprehensive work area Prefabricated cover plate / C25 PC-24 17/06/2022 28 25.1

48 R-9234 20/05/2022 Dam Fire pipeline pier / C20 PC-19 17/06/2022 28 23.0

49 R-9235 21/05/2022 Dam Dam crest pavement 39#~41# EL232.9~EL233.0 C30 PC-21 18/06/2022 28 40.2

50 R-9236 21/05/2022 Dam Dam crest pavement 55#~56# EL232.9~EL233.0 C30 PC-21 18/06/2022 28 42.0

51 R-9237 21/05/2022 Dam Rockfill dam crest highway EL234.8~EL235.0 C25 CVC-29 18/06/2022 28 32.5

52 R-9238 21/05/2022 Comprehensive work area Prefabricated cover plate / C25 PC-24 18/06/2022 28 26.0

Brick wall at the bottom of transformer in 30.2


53 R-9239 21/05/2022 Comprehensive work area
switchyard
/ C25 PC-20 18/06/2022 28

54 R-9240 22/05/2022 Dam Dam crest pavement 40#~42# EL232.9~EL233.0 C30 PC-21 19/06/2022 28 42.0

55 R-9241 22/05/2022 Dam Dam crest pavement 50#~51# EL232.9~EL233.0 C30 PC-21 19/06/2022 28 40.6

56 R-9242 22/05/2022 Comprehensive work area Prefabricated cover plate / C25 PC-24 19/06/2022 28 26.2

57 R-9243 22/05/2022 Dam Fire pipeline pier / C20 PC-19 19/06/2022 28 24.2

58 R-9244 23/05/2022 Dam Dam crest pavement 35#43# EL232.9~EL233.0 C30 PC-21 20/06/2022 28 36.7

59 R-9245 23/05/2022 Dam Dam crest pavement 49#52#57# EL232.9~EL233.0 C30 PC-21 20/06/2022 28 37.8

60 R-9246 23/05/2022 Dam Fire pipeline pier / C20 PC-19 20/06/2022 28 23.8

61 R-9247 23/05/2022 Dam Wave wall of 19# dam section EL232.9~EL234.0 C25 PC-20 20/06/2022 28 32.9

62 R-9248 23/05/2022 Dam Fire water pipe anchor block a-23 / C20 PC-19 20/06/2022 28 25.6

63 R-9249 23/05/2022 Comprehensive work area Prefabricated cover plate / C25 PC-24 20/06/2022 28 36.8

Air conditioning base of 152 floor of 30.4


64 R-9250 23/05/2022 powerhouse
auxiliary plant 4# unit
EL152.75~EL153.0 C25 PC-20 20/06/2022 28

Table 4 Follow-up of RCC Compressive Strength

S/no Sample No: Casting Date Location Chainage Elevation Concrete Grade Mix Design No: Crushing Date Age (Days) Ave. Compressive strength (MPa)

Table 6: Compressive Strength Test Results of CVC Concrete (C25) at 28 Days

1 Number of Test Minimum (Mpa) Maximum (Mpa) Average(Mpa) Standard Deviation (Mpa) Requirement
2 51 25.1 36.9 29.8 For 28 days=25mpa

Note: Practice for Evaluation of Strength Test of Concrete ACI 214-77 tableau 3.5), The Results of concrete Excellent (σ <2.81 MPA)

Table 7: Compressive Strength Test Results of CVC Concrete (C30) at 28 Days

1 Number of Test Minimum (Mpa) Maximum (Mpa) Average(Mpa) Standard Deviation (Mpa) Requirement

2 36 32.9 43.5 40.2 For 28 days=30mpa

Note: Practice for Evaluation of Strength Test of Concrete ACI 214-77 tableau 3.5), The Results of concrete Excellent (σ <2.81 MPA)

Table 8 Compressive Strength Test Results of CVC Concrete (C35)at 28Days

1 Number of Test Minimum (Mpa) Maximum (Mpa) Average(Mpa) Standard Deviation (Mpa) Requirement

2 For 90 days=35mpa

Note: Practice for Evaluation of Strength Test of Concrete ACI 214-77 tableau 3.5), The Results of concrete Excellent (σ <2.81 MPA)

Table 11 Cement and flyash Test Record

Setting Time(Minuts) Average


Standard Specific Gravity
S/no Sample no Date cast Date crushed Fineness (%) Soundness (mm) Cement type Age Compressive
consistency(%) (g/cm3)
Initial Final Strength (Mpa)

1 B-394 17/05/2022 14/06/2022 99.06 28.2 1 3.08 200 277 Lafarge 28 52.2

2 B-396 08/06/2022 15/06/2022 99.14 28.6 1 3.09 194 261 Lafarge 7 35.1

Table 12 - Concrete Volume Report for CVC in Dam

S/N Date Location (Block - Zone) Concrete Type Elevation (m) Volume (m³)

1 12/06/2022 The left ACRD crest road CVC 234.8 ' 235.00 12

The left ACRD crest road


2 13/06/2022 CVC 234.8 ' 235.00 20
L-A-10A and L-A-11A

3 16/06/2022 Pavement layer block 21#- C CVC 232.900 ' 233.00 6

The left ACRD crest road


4 14/06/2022 CVC 234.8 ' 235.00 21
L-A-8B and L-A-12B

5 15/06/2022 Pavement layer block 19#- C CVC 232.900 ' 233.00 7.5
The left ACRD crest road
6 15/06/2022 CVC 234.8 ' 235.00 24
L-A-5B, L- A-10D

The left ACRD crest road


7 16/06/2022 CVC 234.8 ' 235.00 18
L-A-9B, L- A-11B

8 17/06/2022 Parapet wall Block 21# -C CVC 232.90 ' 234.00 9.2

The left ACRD crest road


9 17/06/2022 CVC 234.8 ' 235.00 10
L-A-13B

10 18/06/2022 Parapet wall of the right ACRD Block 7 CVC 234.8 ' 235.00 10.5

11 18/06/2022 Pavement layer block 17#-2A, 17#-4A, 18#-1B CVC 232.9 ' 233.00 12

12 18/06/2022 The left ACRD crest road CVC 234.8 ' 235.00 28.5

Total Concrete Volume 178.7

Table 13 Concrete Volume Report for Power House , Power Intake, Erection bay and Central Control Building.

No Date Location (Unit - Zone-Lift) Concrete Type Elevation (m)/Chainage Volume (m³)

1 12/06/2022 3# stair CVC 148.65 ' 151.25 3.5

2 13/06/2022 Dissipation basin side weir A-8 CVC 144.00 ' 146.0 71

Second stage concrete of 4# unit stator


3 14/06/2022 CVC 136.91 ' 137.96 7
foundation

4 15/06/2022 Dissipation basin side weir A - 7 CVC 144.00 ' 146.0 64

5 2022/6/16~2022/6/17 Penstock l-3, lift C-7 CVC 204 - 207.5 302

6 16/06/2022 L2 road drainage ditch CVC 19.5

7 2022/6/12~2022/6/18 Precast concrete L2 road CVC 32

8 2022/6/12~2022/6/18 Triple-point Switchyard concrete CVC 0

Total concrete Volume 499


ATTACHMENT 2 - ACRD, - Week 04
Summary for progress of RCC consolidation grouting at 28 - 01-2023
WPT (LU)

Completed
Description
Total drilling Grout quantity Average

Sequence
Block No.
Location
Hole Hole (NO.) Result for P *(Primary hole )

(%)
(NO.) finished

recovery
&
Inside 0-3 LU 3-15 LU > 15 LU

Core
Inside Con-

(%)
Required grouting Littre Kg L/m Kg/m
crete (m) Rock(m) (hole no.) (hole no.) (hole no.)
P 236.0 236.0 523.5 1,327.0 74.0 95.0 67.0 76,705.7 60,384.0 57.8 45.5
7 S 253.0 253.0 573.5 1,469.0 NA NA NA 19,074.6 14,615.2 13.0 9.9 100.0%
CH 29.0 29.0 108.2 163.0 29.0 0.0 0.0 112.9 86.3 0.7 0.5 5.9%
P 98.0 98.0 300.3 541.0 40.0 33.0 25.0 23,965.9 18,464.4 44.3 34.1
8 S 85.0 85.0 273.6 470.0 NA NA NA 3,045.4 2,294.3 6.5 4.9 100.0%
CH 14.0 14.0 87.2 73.0 14.0 0.0 0.0 10.2 7.7 0.1 0.1 7.7%
P 94.0 94.0 455.8 518.0 41.0 29.0 24.0 36,038.7 29,070.7 69.6 56.1
9 S 96.0 96.0 514.3 537.0 NA NA NA 4,424.8 3,335.4 8.2 6.2 100.0%
CH 12.0 12.0 89.7 72.0 12.0 0.0 0.0 12.3 9.3 0.2 0.1 6.3%
P 75.0 75.0 362.3 411.0 25.0 36.0 14.0 16,368.8 12,638.8 39.8 30.8
10 S 86.0 86.0 496.3 472.0 NA NA NA 3,924.4 2,958.3 8.3 6.3 100.0%
None-Over flow section ( Bill No.10).

CH 13.0 13.0 89.6 77.0 13.0 0.0 0.0 29.7 22.4 0.4 0.3 8.1%
P 84.0 84.0 223.6 420.0 28.0 37.0 19.0 8,943.1 6,741.0 21.3 16.1
11 S 71.0 71.0 211.0 355.0 NA NA NA 1,852.8 1,395.5 5.2 3.9 100.0%
CH 11.0 11.0 29.0 55.0 11.0 0.0 0.0 244.3 184.1 4.4 3.3 7.1%
Right Bank

P 84.0 84.0 118.9 420.0 50.0 21.0 13.0 6,293.3 4,744.2 15.0 11.3
12 S 77.0 77.0 121.9 385.0 NA NA NA 1,602.1 1,207.3 4.2 3.1 100.0%
CH 10.0 10.0 17.1 50.0 10.0 0.0 0.0 179.5 135.4 3.6 2.7 6.2%
P 72.0 72.0 191.7 360.0 30.0 24.0 18.0 16,105.0 12,462.6 44.7 34.6
13 S 77.0 77.0 208.1 385.0 NA NA NA 3,835.1 2,891.3 10.0 7.5 100.0%
CH 13.0 13.0 56.0 65.0 13.0 0.0 0.0 165.2 124.6 2.5 1.9 8.7%
P 84.0 84.0 355.2 462.0 29.0 32.0 23.0 31,551.6 25,294.4 68.3 54.7
14 S 66.0 66.0 291.5 366.0 NA NA NA 4,938.7 3,720.1 13.5 10.2 100.0%
CH 14.0 14.0 95.7 76.0 14.0 0.0 0.0 85.0 64.1 1.1 0.8 9.3%
P 84.0 84.0 156.8 462.0 31.0 21.0 32.0 46,767.0 38,367.1 101.2 83.0
15 S 77.0 77.0 141.4 427.0 NA NA NA 3,485.0 2,625.6 8.2 6.1 100.0%
CH 9.0 9.0 19.2 51.0 9.0 0.0 0.0 87.5 65.9 1.7 1.3 5.6%
P 72.0 72.0 189.2 396.0 27.0 27.0 18.0 22,034.5 16,869.0 55.6 42.6
16 S 82.0 82.0 208.1 452.0 NA NA NA 2,923.3 2,204.1 6.5 4.9 100.0%
CH 10.0 10.0 29.5 53.0 10.0 0.0 0.0 123.1 92.7 2.3 1.7 6.5%
P 87.0 87.0 433.4 477.0 52.0 23.0 12.0 17,128.6 13,554.9 35.9 28.4
17 S 84.0 84.0 442.5 462.0 NA NA NA 5,073.1 3,823.8 11.0 8.3 100.0%
CH 12.0 12.0 87.6 72.0 12.0 0.0 0.0 205.7 154.9 2.9 2.2 7.0%
P 91.0 91.0 237.6 476.0 53.0 24.0 14.0 10,401.5 7,840.9 21.9 16.5
18 S 84.0 84.0 213.3 438.0 NA NA NA 2,517.1 1,893.6 5.7 4.3 100.0%
CH 12.0 12.0 39.0 66.0 12.0 0.0 0.0 273.4 206.2 4.1 3.1 6.9%
Over flow section ( Bill No.12).

P 78.0 78.0 264.7 408.0 40.0 25.0 13.0 9,875.7 7,432.1 24.2 18.2
19 S 98.0 98.0 340.2 511.0 NA NA NA 1,756.0 1,323.8 3.4 2.6 100.0%
CH 13.0 13.0 52.7 68.0 13.0 0.0 0.0 162.5 122.6 2.4 1.8 7.4%
Right Bank

P 98.0 98.0 104.3 511.0 51.0 33.0 14.0 10,011.3 7,845.8 19.6 15.4
20 S 78.0 78.0 80.1 390.0 NA NA NA 1,754.2 1,321.9 4.5 3.4 100.0%
CH 13.0 13.0 15.4 65.0 13.0 0.0 0.0 87.6 66.1 1.3 1.0 7.4%
P 72.0 72.0 100.6 378.0 41.0 21.0 10.0 9,846.9 7,416.1 26.1 19.6
21 S 71.0 71.0 116.5 355.0 NA NA NA 2,732.1 2,060.1 7.7 5.8 100.0%
CH 10.0 10.0 53.1 50.0 10.0 0.0 0.0 35.4 26.7 0.7 0.5 7.0%
P 93.0 93.0 517.7 486.0 42.0 34.0 17.0 13,739.5 10,493.9 28.3 21.6
22 S 83.0 83.0 668.8 430.0 NA NA NA 3,712.4 2,798.0 8.6 6.5 100.0%
CH 14.0 14.0 200.1 73.0 14.0 0.0 0.0 115.7 87.1 1.6 1.2 8.0%
Right Bank P 81.0 81.0 135.2 441.0 30.0 28.0 23.0 17,695.5 13,345.7 40.1 30.3
Bottom
23 S 86.0 86.0 166.4 466.0 NA NA NA 2,985.7 2,249.3 6.4 4.8 100.0%
Outlet
( Bill No.7). CH 12.0 12.0 21.6 69.0 12.0 0.0 0.0 78.3 59.0 1.1 0.9 7.2%
P 80.0 80.0 483.0 442.0 53.0 18.0 9.0 5,402.5 3,717.3 12.2 8.4
24 S 68.0 68.0 448.6 376.0 NA NA NA 607.9 458.3 1.6 1.2 100.0%
CH 8.0 8.0 54.1 46.0 8.0 0.0 0.0 46.0 34.7 1.0 0.8 5.4%
P 82.0 82.0 329.4 452.0 39.0 38.0 5.0 5,111.3 3,852.1 11.3 8.5
25 S 77.0 77.0 300.8 427.0 NA NA NA 926.5 697.7 2.2 1.6 100.0%
Diversion channel section ( Bill No.10).

CH 8.0 8.0 33.1 46.0 8.0 0.0 0.0 85.2 64.2 1.9 1.4 5.0%
P 96.0 96.0 246.3 248.2 86.0 8.0 2.0 1,388.4 1,218.6 5.6 4.9
26 S 104.0 104.0 544.9 284.1 NA NA NA 562.0 496.5 2.0 1.7 100.0%
CH 13.0 13.0 35.6 65.3 13.0 0.0 0.0 20.1 15.6 0.3 0.2 5.6%
Left Bank
Diversion channel section ( Bill No.10).
Left Bank
P 96.0 96.0 239.4 487.7 43.0 49.0 4.0 6,348.8 6,194.1 13.0 12.7
27 S 104.0 104.0 255.6 524.2 NA NA NA 2,837.4 2,767.1 5.4 5.3 100.0%
CH 10.0 10.0 27.2 50.2 10.0 0.0 0.0 190.5 186.3 3.8 3.7 5.0%
P 66.0 66.0 415.1 330.0 8.0 38.0 20.0 13,836.6 13,521.3 41.9 41.0
28 S 73.0 73.0 450.1 365.3 NA 30.0 NA 2,492.1 2,437.0 6.8 6.7 100.0%
CH 7.0 7.0 45.2 35.2 7.0 0.0 0.0 75.0 73.4 2.1 2.1 5.0%
P 77.0 77.0 109.9 385.0 48.0 26.0 3.0 2,493.7 2,438.2 6.5 6.3
29 S 60.0 60.0 90.7 300.0 NA NA NA 1,181.8 1,155.8 3.9 3.9 100.0%
CH 7.0 7.0 24.2 35.0 7.0 0.0 0.0 82.7 80.7 2.4 2.3 5.1%
P 66.0 66.0 144.5 366.0 46.0 15.0 5.0 6,142.4 4,810.6 16.8 13.1
30 S 70.0 70.0 143.1 392.0 NA NA NA 341.4 257.1 0.9 0.7 100.0%
CH 7.0 7.0 14.3 38.0 7.0 0.0 0.0 37.1 27.9 1.0 0.7 5.1%
P 105.0 105.0 388.7 1,239.0 64.0 37.0 4.0 20,729.6 16,586.1 16.7 13.4
31 S 92.0 92.0 373.4 1,100.0 NA NA NA 1,137.9 857.4 1.0 0.8 100.0%
CH 11.0 11.0 55.1 128.0 11.0 0.0 0.0 16.6 12.5 0.1 0.1 5.6%
P 96.0 96.0 146.8 1,104.0 50.0 33.0 13.0 13,636.9 10,249.6 12.4 9.3
Intake section ( Bill No.13).

32 S 108.0 108.0 176.2 1,305.0 NA NA NA 7,491.2 5,630.9 5.7 4.3 100.0%


CH 14.0 14.0 140.6 152.0 14.0 0.0 0.0 98.8 74.6 0.7 0.5 6.9%
Left Bank

P 96.0 96.0 149.6 1,104.0 59.0 28.0 9.0 16,115.7 12,121.3 14.6 11.0
33 S 96.0 96.0 166.7 1,160.0 NA NA NA 4,918.3 3,707.7 4.2 3.2 100.0%
CH 10.0 10.0 64.4 122.0 10.0 0.0 0.0 111.6 84.1 0.9 0.7 5.2%
P 108.0 108.0 147.1 1,256.0 57.0 44.0 7.0 13,515.3 10,188.8 10.8 8.1
34 S 96.0 96.0 132.3 1,160.0 NA NA NA 2,453.4 1,849.4 2.1 1.6 100.0%
CH 11.0 11.0 16.2 137.0 11.0 0.0 0.0 39.0 29.5 0.3 0.2 5.4%
P 80.0 80.0 452.0 913.0 47.0 29.0 4.0 9,698.9 7,427.0 10.6 8.1
35 S 80.0 80.0 648.7 920.0 NA NA NA 2,734.1 2,060.7 3.0 2.2 100.0%
CH 10.0 10.0 149.3 115.0 10.0 0.0 0.0 211.2 159.6 1.8 1.4 6.3%
P 90.0 90.0 59.9 860.0 62.0 27.0 1.0 2,028.8 1,529.8 2.4 1.8
Unit # 1 S 72.0 72.0 120.6 639.0 NA NA NA 429.0 323.7 0.7 0.5 100.0%
CH 9.0 9.0 24.0 86.0 9.0 0.0 0.0 104.8 76.1 1.2 0.9 5.6%
Powerhouse (Bill No.11).

P 72.0 72.0 65.0 688.0 50.0 21.0 1.0 2,368.4 1,785.3 3.4 2.6
Unit # 2 S 72.0 72.0 133.2 639.0 NA NA NA 655.6 494.3 1.0 0.8 100.0%
Left Bank

CH 8.0 8.0 21.7 85.0 8.0 0.0 0.0 26.2 19.9 0.3 0.2 5.6%
Powerhouse (Bill No.11).
Left Bank
P 81.0 81.0 66.3 774.0 55.0 26.0 0.0 1,993.8 1,503.1 2.6 1.9
Unit # 3 S 64.0 64.0 111.8 568.0 NA NA NA 777.4 586.9 1.4 1.0 100.0%
CH 9.0 9.0 29.3 79.0 9.0 0.0 0.0 52.1 39.4 0.7 0.5 6.2%
P 95.0 95.0 96.0 886.0 65.0 26.0 4.0 4,042.8 3,079.1 4.6 3.5
Unit # 4 S 94.0 94.0 167.4 822.0 NA NA NA 956.2 720.2 1.2 0.9 100.0%
CH 10.0 10.0 39.5 80.0 10.0 0.0 0.0 81.2 61.3 1.0 0.8 5.3%
P 41.0 41.0 308.5 235.0 13.0 19.0 9.0 6,943.4 5,343.8 29.5 22.7
36 S 45.0 45.0 337.3 243.0 NA NA NA 1,893.4 1,427.7 7.8 5.9 100.0%
CH 7.0 7.0 79.2 38.0 7.0 0.0 0.0 183.8 138.5 4.8 3.6 8.1%
P 48.0 48.0 135.4 216.0 12.0 15.0 9.0 4,872.4 3,672.6 22.6 17.0
37 S 35.0 35.0 92.1 140.0 NA NA NA 647.7 488.3 4.6 3.5 100.0%
CH 2.0 0.0 2.6 10.0 2.0 0.0 0.0 16.8 12.6 1.7 1.3 2.4%
P 48.0 48.0 221.5 276.0 28.0 17.0 3.0 1,931.1 1,456.9 7.0 5.3
38 S 49.0 49.0 229.7 266.0 NA NA NA 584.7 440.7 2.2 1.7 100.0%
CH 6.0 6.0 37.6 33.0 6.0 0.0 0.0 140.2 105.6 4.2 3.2 6.2%
P 56.0 56.0 109.8 322.0 33.0 14.0 9.0 5,087.8 3,834.8 15.8 11.9
39 S 42.0 42.0 80.5 228.0 NA NA NA 810.1 610.6 3.6 2.7 100.0%
CH 7.0 7.0 30.1 41.0 7.0 0.0 0.0 9.0 6.8 0.2 0.2 7.1%
P 49.0 49.0 221.2 287.0 25.0 16.0 8.0 5,209.7 3,925.9 18.2 13.7
40 S 46.0 46.0 249.3 251.0 NA NA NA 1,831.5 1,380.4 7.3 5.5 100.0%
CH 7.0 7.0 88.9 38.0 7.0 0.0 0.0 47.4 35.8 1.2 0.9 7.4%
P 36.0 36.0 163.7 216.0 13.0 17.0 6.0 1,705.1 1,285.5 7.9 6.0
41 S 39.0 39.0 189.7 216.0 NA NA NA 559.6 420.7 2.6 1.9 100.0%
CH 4.0 4.0 46.5 23.0 4.0 0.0 0.0 14.8 11.2 0.6 0.5 5.3%
P 42.0 42.0 98.9 252.0 18.0 18.0 6.0 3,229.5 2,433.9 12.8 9.7
42 S 30.0 30.0 59.8 168.0 NA NA NA 326.6 246.3 1.9 1.5 100.0%
CH 5.0 5.0 9.9 31.0 5.0 0.0 0.0 22.8 17.2 0.7 0.6 6.9%
P 36.0 36.0 140.3 222.0 19.0 15.0 2.0 1,291.6 973.4 5.8 4.4
43 S 32.0 32.0 142.6 181.0 NA NA NA 244.1 183.8 1.3 1.0 100.0%
CH 4.0 4.0 15.1 23.0 4.0 0.0 0.0 28.3 21.5 1.2 0.9 5.9%
P 27.0 27.0 60.1 171.0 23.0 3.0 1.0 388.2 292.6 2.3 1.7
44 S 28.0 28.0 53.4 160.7 NA NA NA 138.5 104.3 0.9 0.6 100.0%
CH 3.0 3.0 11.2 18.0 3.0 0.0 0.0 10.6 8.1 0.6 0.5 5.5%
section ( Bill No.10).
t Bank
P 28.0 28.0 76.6 182.0 22.0 5.0 1.0 932.8 703.1 5.1 3.9
45 S 23.0 23.0 67.9 133.0 NA NA NA 274.2 206.6 2.1 1.6 100.0%
CH 4.0 4.0 7.9 23.0 4.0 0.0 0.0 31.4 23.7 1.4 1.0 7.8%
P 28.0 28.0 56.6 182.0 15.0 13.0 0.0 793.8 598.4 4.4 3.3
46 S 21.0 21.0 49.0 126.0 NA NA NA 118.9 89.8 0.9 0.7 100.0%
None-Over flow section ( Bill No.10). CH 4.0 4.0 16.5 23.0 4.0 0.0 0.0 13.7 10.2 0.6 0.4 8.2%
P 24.0 24.0 32.2 156.0 1.0 22.0 1.0 1,253.7 945.1 8.0 6.1
47 S 21.0 21.0 26.8 126.0 NA NA NA 98.3 74.1 0.8 0.6 100.0%
CH 3.0 3.0 4.9 15.0 3.0 0.0 0.0 6.6 5.0 0.4 0.3 6.7%
28.0 28.0 50.6 182.0 1,182.0 891.5
Left Bank

P 14.0 12.0 2.0 6.5 4.9


48 S 18.0 18.0 31.1 108.0 NA NA NA 88.4 66.6 0.8 0.6 100.0%
CH 3.0 3.0 6.0 15.0 3.0 0.0 0.0 3.0 2.2 0.2 0.1 6.5%
P 28.0 28.0 46.4 182.0 21.0 7.0 0.0 348.6 262.7 1.9 1.4
49 S 21.0 21.0 38.2 126.0 NA NA NA 42.1 31.8 0.3 0.3 100.0%
CH 3.0 3.0 7.9 15.0 3.0 0.0 0.0 0.6 0.5 0.0 0.0 6.1%
P 24.0 24.0 34.6 156.0 16.0 7.0 1.0 545.2 410.9 3.5 2.6
50 S 21.0 21.0 29.9 126.0 NA NA NA 74.2 56.2 0.6 0.4 100.0%
CH 3.0 3.0 4.5 18.0 3.0 0.0 0.0 9.6 7.3 0.5 0.4 6.7%
P 28.0 28.0 33.0 182.0 25.0 3.0 0.0 298.1 224.7 1.6 1.2
51 S 18.0 18.0 22.1 108.0 NA NA NA 29.9 22.5 0.3 0.2 100.0%
CH 3.0 3.0 3.9 18.0 3.0 0.0 0.0 26.8 20.1 1.5 1.1 6.5%
P 22.0 22.0 33.7 152.0 7.0 15.0 0.0 996.5 751.4 6.6 4.9
52 S 21.0 21.0 31.3 126.0 NA NA NA 29.9 22.6 0.2 0.2 100.0%
CH 3.0 3.0 5.0 18.0 3.0 0.0 0.0 13.5 10.2 0.8 0.6 7.0%
P 18.0 18.0 33.8 126.0 8.0 10.0 0.0 927.5 699.6 7.4 5.6
53 S 21.0 21.0 46.4 126.0 NA NA NA 52.4 39.5 0.4 0.3 100.0%
CH 3.0 3.0 11.8 18.0 3.0 0.0 0.0 17.3 13.1 1.0 0.7 7.7%
P 21.0 21.0 33.6 147.0 12.0 7.0 2.0 1,249.2 942.1 8.5 6.4
54 S 18.0 18.0 25.5 108.0 NA NA NA 50.7 38.1 0.5 0.4 100.0%
CH 3.0 3.0 13.5 18.0 3.0 0.0 0.0 1.0 0.7 0.1 0.0 7.7%
P 21.0 21.0 37.3 147.0 4.0 17.0 0.0 1,188.5 896.1 8.1 6.1
55 S 21.0 21.0 35.8 126.0 NA NA NA 82.2 61.9 0.7 0.5 100.0%
CH 3.0 3.0 14.1 21.0 3.0 0.0 0.0 8.1 6.1 0.4 0.3 7.1%
P 18.0 18.0 30.5 126.0 2.0 14.0 2.0 1,037.3 777.6 8.2 6.2
56 S 21.0 21.0 36.4 126.0 NA NA NA 8.7 6.7 0.1 0.1 100.0%
CH 3.0 3.0 15.0 18.0 3.0 0.0 0.0 4.0 3.0 0.2 0.2 7.7%
P 21.0 21.0 90.3 147.0 15.0 5.0 1.0 1,346.4 1,014.6 9.2 6.9
57 S 18.0 18.0 77.0 108.0 NA NA NA 214.4 161.5 2.0 1.5 100.0%
CH 3.0 3.0 13.5 21.0 3.0 0.0 0.0 12.9 9.8 0.6 0.5 7.7%
P 24.0 24.0 58.7 144.0 17.0 6.0 1.0 937.2 706.8 6.5 4.9
58 S 22.0 22.0 45.8 140.0 NA NA NA 85.0 64.2 0.6 0.5 100.0%
CH 3.0 3.0 5.6 18.0 3.0 0.0 0.0 40.6 30.6 2.3 1.7 6.5%
P 35.0 35.0 58.5 217.0 23.0 12.0 0.0 800.3 603.3 3.7 2.8
59 S 35.0 35.0 58.3 205.0 NA NA NA 188.0 141.7 0.9 0.7 100.0%
CH 5.0 5.0 40.3 31.0 5.0 0.0 0.0 9.7 7.3 0.3 0.2 7.1%
P 50.0 50.0 102.9 328.0 39.0 9.0 2.0 951.2 717.1 2.9 2.2
60 S 66.0 66.0 163.8 420.0 NA NA NA 445.7 336.1 1.1 0.8 100.0%
CH 8.0 8.0 59.3 49.0 8.0 0.0 0.0 26.8 20.3 0.5 0.4 6.9%
Total 7,861.0 7,859.0 24,445.1 51,616.9 2,416.0 1,334.0 513.0 656,817.5 514,575.6 12.7 10.0 100.0%
ATTACHMENT 2, - RCC Curtain Grouting - Week 04
Summary for progress of RCC Curtain grouting 28 - 01-2023

Completed
WPT (LU)
Description

Design finished grouting Total drilling Grout quantity Average

Sequence
Block No.

(%)
Location

Result for P *(Primary hole )


&

Hole (NO.) Stage(NO.) Stage (NO.) Depth Inside Con- Inside 0-3 LU 3-15 LU > 15 LU
Depth (m) Hole (NO.) (m) Littre Kg L/m Kg/m
Required Required crete (m) Rock(m) (hole no.) (hole no.) (hole no.)
P/Pr 17.0 107.0 690.4 17.0 107.0 690.4 155.4 535.0 76.0 25.0 6.0 16,809.4 13,148.6 31.4 24.6
S 18.0 108.0 698.1 18.0 108.0 698.1 158.1 540.0 NA NA NA 4,909.8 3,771.9 9.1 7.0
7~ 11 T 36.0 216.0 1,396.2 36.0 216.0 1,396.2 316.2 1,080.0 NA NA NA 3,479.0 2,622.8 3.2 2.4 100.0%
Q 6.0 6.0 165.8 72.4 93.4 NA NA NA 127.6 96.2 1.4 1.0
CH 8.0 41.0 278.6 68.7 209.9 41.0 0.0 0.0 1,382.2 1,041.5 6.6 5.0
P/Pr 7.0 45.0 258.0 7.0 46.0 258.0 28.0 230.0 34.0 9.0 3.0 23,136.1 18,940.0 100.6 82.3
Right Bank S 6.0 36.0 204.0 6.0 36.0 204.0 24.0 180.0 NA NA NA 7,800.0 6,656.7 43.3 37.0
None-Over
11~ 14 T 12.0 72.0 408.0 12.0 72.0 408.0 48.0 360.0 NA NA NA 563.7 424.9 1.6 1.2 100.0%
flow section
( Bill No.10). Q
CH 3.0 18.0 102.0 12.0 90.0 18.0 0.0 0.0 113.0 85.5 1.3 1.0
P/Pr 10.0 63.0 358.5 10.0 63.0 358.5 43.5 315.0 58.0 5.0 0.0 3,467.3 2,612.9 11.0 8.3
S 10.0 60.0 346.0 10.0 60.0 346.0 46.0 300.0 NA NA NA 1,325.9 999.3 4.4 3.3
14~ 17 T 20.0 120.0 691.7 20.0 120.0 691.7 91.7 600.0 NA NA NA 1,741.9 1,312.8 2.9 2.2 100.0%
Q
CH 4.0 22.0 128.9 19.1 109.8 22.0 0.0 0.0 67.7 51.0 0.6 0.5
P/Pr 12.0 100.0 558.5 12.0 100.0 558.5 58.5 500.0 99.0 1.0 0.0 596.2 449.1 1.2 0.9
Right Bank S 12.0 96.0 581.8 13.0 104.0 581.8 55.8 480.0 NA NA NA 383.0 288.4 0.8 0.6
Over flow T 26.0 208.0 1,119.6 25.0 200.0 1,119.6 125.6 1,040.0 NA NA NA 623.8 470.5 0.6 0.5
18~ 22 100.0%
section
Q
( Bill No.12).
CH 3.0 27.0 154.2 17.2 137.0 3.0 0.0 0.0 30.5 23.0 0.2 0.2

P/Pr 3.0 25.0 137.3 3.0 25.0 137.3 12.3 125.0 25.0 0.0 0.0 439.0 331.5 3.5 2.7
Right Bank S 2.0 16.0 88.7 2.0 16.0 88.7 8.7 80.0 NA NA NA 20.9 15.9 0.3 0.2
Bottom
23 T 5.0 40.0 220.9 5.0 40.0 220.9 20.9 200.0 NA NA NA 17.8 13.3 0.1 0.1 100.0%
Outlet
( Bill No.7). Q
CH 1.0 11.0 58.6 4.5 54.1 11.0 0.0 0.0 22.5 17.1 0.4 0.3
P/Pr 5.0 32.0 185.0 5.0 32.0 185.0 25.0 160.0 32.0 0.0 0.0 163.4 123.1 1.0 0.8
S 5.0 30.0 173.2 5.0 30.0 173.2 23.2 150.0 NA NA NA 50.3 37.8 0.3 0.3
24~25 T 10.0 60.0 347.6 10.0 60.0 347.6 47.6 300.0 NA NA NA 81.0 61.1 0.3 0.2 100.0%
Q
CH 2.0 16.0 95.3 8.9 86.4 3.0 0.0 0.0 22.3 16.7 0.3 0.2
P/Pr 6.0 38.0 226.5 6.0 38.0 226.5 36.5 190.0 32.0 6.0 0.0 1,903.2 1,434.1 10.0 7.5
Left Bank
Diversion S 6.0 36.0 216.3 6.0 36.0 216.3 36.3 180.0 6.0 0.0 0.0 142.0 105.0 0.8 0.6
channel 26~27 T 12.0 72.0 432.8 12.0 72.0 432.8 162.8 270.0 12.0 0.0 0.0 95.9 72.7 0.4 0.3 100.0%
section Q
( Bill No.10).
CH 4.0 38.0 88.9 25.2 63.7 4.0 0.0 0.0 4.1 88.1 0.1 1.4
P/Pr 7.0 44.0 249.7 7.0 45.0 254.7 29.7 225.0 45.0 0.0 0.0 24.2 18.3 0.1 0.1
S 8.0 48.0 274.3 8.0 48.0 302.8 34.3 268.5 NA NA NA 50.7 38.2 0.2 0.1
28~30 T 15.0 90.0 514.6 15.0 90.0 514.6 64.6 450.0 NA NA NA 44.1 39.7 0.1 0.1 100.0%
Q
CH 3.0 23.0 124.5 13.2 111.3 23.0 0.0 0.0 2.4 1.8 0.0 0.0
P/Pr 13.0 96.0 592.9 13.0 96.0 592.9 110.9 482.0 96.0 0.0 0.0 114.1 86.2 0.2 0.2
Left Bank S 12.0 84.0 528.2 12.0 84.0 528.2 108.2 420.0 NA NA NA 52.3 39.8 0.1 0.1
Intake
31~34 T 27.0 193.0 1,191.0 27.0 193.0 1,191.0 227.0 964.0 NA NA NA 92.0 69.0 0.1 0.1 100.0%
section
( Bill No.13). Q
CH 4.0 32.0 194.9 39.7 155.2 32.0 0.0 0.0 16.3 12.3 0.1 0.1
P/Pr 12.0 79.0 456.8 12.0 79.0 456.8 59.8 397.0 79.0 0.0 0.0 202.1 152.9 0.5 0.4
S 12.0 75.0 432.1 12.0 75.0 432.1 56.1 376.0 NA NA NA 362.3 272.9 1.0 0.7
T 24.0 150.0 875.4 24.0 150.0 875.4 118.4 757.0 NA NA NA 523.3 381.9 0.7 0.5
35~39 100.0%
Q

CH 4.0 32.0 177.7 18.6 159.1 32.0 0.0 0.0 29.0 21.9 0.2 0.1

P/Pr 13.0 83.0 493.4 1.0 7.0 39.5 4.5 35.0 7.0 0.0 0.0 14.3 10.8 0.4 0.3
S 12.0 72.0 432.4 0.0 0.0 0.0 0.0 0.0 NA NA NA 0.0 0.0 0.0 0.0
T 25.0 150.0 901.1 1.0 6.0 34.0 4.0 30.0 NA NA NA 49.2 36.9 1.6 1.2
40~44 100.0%
Q

CH 4.0 36.0 195.4 27.2 185.0 36.0 0.0 0.0 33.4 26.1 1.2 1.0

Left Bank P/Pr 15.0 69.0 416.1 10.0 49.0 292.7 47.2 245.5 41.0 8.0 0.0 15,513.7 12,817.1 63.2 52.2
None-Over
S 15.0 65.0 395.7 9.0 36.0 223.4 43.4 180.0 NA NA NA 6,041.3 4,810.6 33.6 26.7
flow section
45~50 T 30.0 129.0 791.1 18.0 78.0 474.9 84.9 390.0 NA NA NA 1,480.5 1,140.5 3.8 2.9 100.0%
( Bill No.10).
Q
CH
Left Bank
None-Over
flow section
( Bill No.10).

P/Pr 12.0 52.0 317.2 12.0 54.0 327.2 57.2 270.0 46.0 8.0 0.0 9,873.4 7,777.2 36.6 28.8
S 13.0 52.0 321.7 13.0 53.0 326.7 61.7 265.0 NA NA NA 5,816.6 5,417.0 21.9 20.4
51~55 T 25.0 100.0 620.1 25.0 100.0 620.1 120.1 525.0 NA NA NA 1,257.0 947.7 2.4 1.8 100.0%
Q
CH
P/Pr 14.0 60.0 389.4 3.0 13.0 78.4 13.4 65.0 12.0 1.0 0.0 707.8 533.4 10.9 8.2
S 14.0 56.0 368.7 2.0 8.0 50.0 10.0 40.0 NA NA NA 401.2 302.4 10.0 7.6
56~60 T 29.0 116.0 7,632.0 5.0 20.0 123.3 23.3 100.0 NA NA NA 173.8 131.0 1.7 1.3 100.0%
Q
CH 6.0 6.0 202.7 45.3 215.4 NA NA NA 186.4 150.5 0.5 0.3
P/Pr 14.0 66.0 586.9 14.0 71.0 611.9 223.9 388.0 50.0 18.0 2.0 4,922.5 3,738.6 12.7 9.6
S 12.0 53.0 480.1 12.0 52.0 416.0 169.9 246.1 4.0 0.0 0.0 314.6 206.8 1.1 0.7
DV 2360 ~
T 24.0 106.0 961.1 24.0 106.0 961.1 278.6 682.5 16.0 0.0 0.0 871.7 692.0 1.3 1.1 100.0%
2460
Q
CH 7.0 7.0 195.9 39.8 195.9 NA NA NA 168.3 126.7 0.9 0.6
Total 637.0 3,668.0 29,561.1 571.0 3,402.0 20,073.2 3,847.2 17,286.9 979.0 81.0 11.0 118,689.7 94,493.0 6.9 5.5 100.0%
ATTACHMENT 2, Week 04
Summary for progress of RCC /Bedrock Drainage Holes at 28 - 01-2023
Design finished Quantity

Block No. Depth Depth

Completed
Hole (NO.) Inside Con- Inside Rock Inside Con- Inside Rock
(m) Hole (NO.) (m)

( %)
Required crete (m) crete (m)
Rock(m) Rock(m)

B7-B8 59.0 623.8 885.8 1509.5 59.0 623.8 885.8 1509.6 100.0%

B9-B12 71.0 594.2 1018.9 1613.1 71.0 594.2 1018.9 1613.1 100.0%

B13-B16 67.0 292.2 957.9 1250.1 67.0 292.2 957.9 1250.1 100.0%

B17-B19 47.0 177.1 700.8 877.9 47.0 177.1 711.2 888.3 100.0%

B20-B21 47.0 130.2 613.8 744.0 47.0 130.2 613.8 744.0 100.0%

B22-B24 58.0 271.3 789.8 1061.1 58.0 271.3 789.8 1061.1 100.0%

B25-B27 59.0 283.0 812.2 1095.2 59.0 242.4 710.9 953.3 100.0%

B28-B30 41.0 132.6 641.9 774.5 41.0 130.3 602.1 732.4 100.0%

B31-B34 91.0 806.6 1284.9 2091.5 91.0 806.6 1284.9 2091.5 100.0%

B35-B44 68.0 369.2 1408.0 1777.2 68.0 369.2 1408.0 1777.2 100.0%

B45-B54 70.0 346.5 1118.9 1465.4 70.0 346.5 1118.9 1465.4 100.0%

B55-B60 47.0 306.1 681.2 987.3 47.0 306.1 681.2 987.3 100.0%

Total 725.0 4,332.8 10,914.1 15,246.8 725.0 4,289.9 10,783.3 15,073.3 100.0%
ATTACHMENT 2, Week 04
Summary for progress of RCC/ Drainage Holes at 28 - 01-2023
Design finished Quantity (%)
Block No. Hole (NO.) Inside Con- Depth Inside Con- Depth
(m) Hole (NO.) (m) Completed
Required crete (m) crete (m)

B7-B11 66.0 2285.0 2285.0 66.0 2285.0 2285.0 100.0%

B12-B17 72.0 2623.0 2623.0 72.0 2623.0 2623.0 100.0%

B18-B22 50.0 1719.9 1719.9 50.0 1719.9 1719.9 100.0%

B23 4.0 162.2 162.2 4.0 162.2 162.2 100.0%

B24-B25 20.0 900.3 900.3 20.0 900.3 900.3 100.0%

B26-B27 32.0 1185.6 1185.6 32.0 1185.6 1185.6 100.0%

B28-B30 36.0 1300.1 1300.1 36.0 1300.1 1300.1 100.0%

B31-B34 32.0 1059.2 1059.2 32.0 1059.2 1059.2 100.0%

B35-B39 60.0 1666.6 1666.6 60.0 1666.6 1666.6 100.0%

B40-B48 59.0 1502.4 1502.4 59.0 1502.4 1502.4 100.0%

B49-B60 73.0 1235.5 1235.5 73.0 1235.5 1235.5 100.0%

Total 504.0 15,639.8 15,639.8 504.0 15,639.8 15,639.8 100.0%


EMPLOYER’S REPRESENTATIVE
COYNE ET BELLIER DE-CROWN (W.A.) CO. LTD.
Bureau d'Ingénieurs Conseils Consulting Engineers Ltd, Abuja - Nigeria

JOINT VENTURE
No. 6 Udi Street, Off Aso Drive, Maitama, Abuja

700 MW ZUNGERU HYDROELECTRIC POWER PROJECT


WEEKLY SITE ACTIVITY REPORT
Date Range 22- 28 JAN, 2023 Week No.: 2023- 04 PC Date: 27-Sep-13
Weather: Sunning Precipitation Range: Temperature Range: 27 to 37
(Summary) (Summary) (Summary)

ATTACHMENT 3, Week 04
PHOTOGRAPHS

Fire-fighting system pipes installation at machine hall in progress. Anti-corosion of Spillway 1600kN Gantry Crane in progress.

Showing SCADA display of unit 1# during load increase test (From 0% to 100%) at During generator synchronization unit 1# with the grid at powerhouse central control
powerhouse central control room room.
COYNE ET BELLIER DE-CROWN (W.A.) CO. LTD.
Bureau d'Ingénieurs Conseils Consulting Engineers Ltd, Abuja - Nigeria

Date Range 22- 28 JAN, 2023 Week No.: 2023- 04 PC Date: 27-Sep-13
Weather: Sunning Precipitation Range: Temperature Range: 27 to 37
(Summary) (Summary) (Summary)

ATTACHMENT 3, Week 04
PHOTOGRAPHS

During Unit 1# heat running at rated power output. Showing unit 1-4# emergency accident stop botton at powerhouse central control room

During the inspection of the drainage ditch around Water treatment equipment room at the During the inspection of the of 37nos. of concrete cover plate around the diesel generator
downstream of block 47# room

During the inspection of the drainage ditch around Water treatment equipment room at the TRIPLE POINT SWITCHYARD: Cleaning of floor around septic tank/chamber at central
downstream of block 47# control building before landscaping.
COYNE ET BELLIER DE-CROWN (W.A.) CO. LTD.
Bureau d'Ingénieurs Conseils Consulting Engineers Ltd, Abuja - Nigeria

Date Range 22- 28 JAN, 2023 Week No.: 2023- 04 PC Date: 27-Sep-13
Weather: Sunning Precipitation Range: Temperature Range: 27 to 37
(Summary) (Summary) (Summary)

ATTACHMENT 3, Week 04
PHOTOGRAPHS

TRIPLE POINT SWITCHYARD: Dressing of door frame at entrance of water treatment


TRIPLE POINT SWITCHYARD: Curing of concrete road at chainage K0+000m
building.