Date Range: 22- 28 JAN, 2023 Week No.: 04 Project Commencement Date: 27-Sep-13
ACTIVITY CHALLENGE/ISSUE
ITEM Section Head/ Engineer in Charge
(PROGRESS STATUS) (QUALITY OF WORK, SPEED CORRECTIVE ACTION
OF WORK, METHOD OF PROPOSED/TAKEN
WORK)
1.0 General
Release of Water from the Reservior for the Safety of the Dam:
Water release commenced on 10th January 2022, Initially used the bottom outlet
gate , then the spillway radial gate#3. All the gates have been completely closed but
so far the water released is about (3,734.0 x 10 6 m³) through bottom outlet and
Spillway towards the tailrace channel. - See attachment 2 (Att2 - Discharge
Calculation) for details.
Dam Performance:
Mohamed/Charles/Dayo
As at the end of this reporting week, the water storage in the reservoir is at about
99.61%. The maximum dam water leakage, according to the design and
specification for this dam, is 120 litres/sec. Currently the Dam Total water leakage
is at 10.71 litre/sec :- (1.898 litres/sec from ACRD righbank, 1.649litres/sec from
upstream construction joints and 3.694litre/sec from downstream bedrock
drainage system), which is about 7.5% of the design value.
With this, the Dam is performing excellently well. However, the repairs works are
still ongoing on the leakage holes to further reduce the water leakage.
The permanent bottom outlet is incorporated inside Dam Block 23 at El 155 with a
4m diameter steel liner. The steel liner was already fully encased with reinforced
concrete.
Kunle/Banjo/Dimeji
Below is the activitiy during the week under review
- casting of columns and parapet of the permanent bottom hole hoist room
The concrete plugging of the diversion channel work commenced with the
submittal of necessary documents including the drawings and method statements
of both the concreteing and the various grouting procedures by the CSC, which was
appoved with status A by the ER with letter number ZUN-2021-05-21- ER 2037. Self- Kunle/Banjo/Dimeji
compacting concrete is used for the last lifts of each sections. The plugging work
commenced and reported as follows.
CONSTRUCTION CHALLENGE & TECHNICAL ISSUE FACED
ACTIVITY CHALLENGE/ISSUE
ITEM Section Head/ Engineer in Charge
(PROGRESS STATUS) (QUALITY OF WORK, SPEED CORRECTIVE ACTION
OF WORK, METHOD OF PROPOSED/TAKEN
WORK)
Block 26
- Completed Kunle/Banjo/Dimeji
Block 27
- Completed
Kunle/Banjo/Dimeji
For further concrete casting details refer to Attachment 1, Table 12.
Dam impoundment continued this week under review, measures were taken to
ensure the safety of the dam through daily observation of the installed instruments.
An electric water level meter is being used to monitor the changes in the water
level. During this week, the water level increased by 0.48 with an average rate of
(0.069m/day) due to the closure of all spill-way gate sand bottom outlet. The water Mohamed/Charles/Dayo
level is currebtly at elevation 228.65m. The volume of the reservoir is at 9353.7
(10⁶ m³), while the specific area capacity is 377.09 km2. The present percentage
storage volume is at 99.61%. See Att 2 - Impoundment for details
Routine dam foundation monitoring and observation was carried out during the
week by observing the various installed instruments such as jointmeter, rod
extensometer, multiple point extensometer, thermometer, Crackmeter,
piezometer, pressure and stress cell at block 12 , 20, 33,39, power house & Right
abutment Rock fill Dam upstream and downstream to check the situation of the
dam. The V-notch weir in the gallery are checked weekly to accurately measure the Mohamed/Charles/Dayo
flow of water leakages in the gallery. The main inspection part include dam body,
dam foundation and dam abutment.The pendulum systems (hanging and
inverted),and the wire alignment instrument is faulty and under repair. During the
week under review, no new instrument was installed
Drilling of bedrock drainage hole has been completed. achievement rate is 100%.
See attachment 2 of bedrock drainage holes for details. Mohamed/Charles/Dayo
ACTIVITY CHALLENGE/ISSUE
ITEM Section Head/ Engineer in Charge
(PROGRESS STATUS) (QUALITY OF WORK, SPEED CORRECTIVE ACTION
OF WORK, METHOD OF PROPOSED/TAKEN
WORK)
RCC placement is being continued sequentially in all RCC blocks since 22 January
2018.
RCC was placed in the following list of blocks during the week under review;
RCC placement for the whole dam has been completed since February 2021.
CVC casting at dam crest at both left bank and right bank have been relatively
completed from El 231.00 to 232.90m.
Banjo/kunle/Dimeji
The following activities were done during this reporting week
The following activties were executed during this week under review;
- No concreting Dimeji
Casting of concrete plinth and gallery is 100% completed for both left and right
ACRD. Amande
Sequel the heavy down pour on the 8th of April, 2022 at the 700MW Zungeru
Hydro-Electric power project site accompanied with a wind of 24.7m/s, some part
Amande/ David
of the upstream riprap surface was swept off.
Reference to the submitted letter CSC-CSLT-ZP-3999-2022
Within this reporting week, the riprap repair activity within El. 228.00 - 234.500m
has been completed
CONSTRUCTION CHALLENGE & TECHNICAL ISSUE FACED
ACTIVITY CHALLENGE/ISSUE
ITEM Section Head/ Engineer in Charge
(PROGRESS STATUS) (QUALITY OF WORK, SPEED CORRECTIVE ACTION
OF WORK, METHOD OF PROPOSED/TAKEN
WORK)
Backfilling between RCC Dam and Power House with phyllite(rockfill) commenced
on 12th June 2021.
Work has being executed as follows :
1. Between LHS slope and penstock No.1,
from EL 158.250 to 159.000m................................completed
2. Between pentstock No.1 & 2,
from EL 157.000 to 159.000m................................completed Amande/ David
3. Between penstock No.2 & 3,
from EL 158.250 to 159.000m............................... completed
4. Between penstock No. 3 & 4,
from EL 158.250 to 159.000m............................... completed
5. Between penstock No. 4 and RHS slope,
from EL 157.000 to 159.000m................................completed
2.0. POWERHOUSE
The civil work construction is being carried out at Power House since mid of
November 2018. Currently first stage concrete for draft tube foundation below El
123.5 and concrete for tail water gate piers is being cast for all Power House Units.
The seepage collection pit was also under construction.
Civil work design drawings below El. 159.3 was reviewed by ER and then
construction work above El. 123.5 was commenced accordingly at Unit 1, Unit 2,
Kunle/Banjo
Unit 3 and Unit 4.
For ease of casting concrete, each Unit is subdivided into three zones separated by
construction joints.
Zone I - from upstream rock face to DH 0+123.325(First stage concrete)
Zone ll - The Middle part (second stage concrete)
Zone III - from DH 0+123.325 to 0+146.000(First stage concrete)
CONSTRUCTION CHALLENGE & TECHNICAL ISSUE FACED
ACTIVITY CHALLENGE/ISSUE
ITEM Section Head/ Engineer in Charge
(PROGRESS STATUS) (QUALITY OF WORK, SPEED CORRECTIVE ACTION
OF WORK, METHOD OF PROPOSED/TAKEN
WORK)
1. Unit #1
The following main activities were carried out during the week under review;
2. Unit #2
The following main civil work activities was performed during the week under
review.
- No concreting activities Kunle/Banjo
For further concrete casting detail refer Attachment 1, Table 13.
3. Unit #3
The following main activities were carried out during the week under review;
- No concreting
Kunle/Banjo/Dimeji
- Formwork and reinforcement was being fixed for other part of the Unit in
preparation for casting.
For further concrete casting detail refer Attachment 1, Table 13.
4. Unit #4
The following main activities were performed during the week under review;
- Casting of generator floor leveling course concrete from El. 143.450 – 143.500m Kunle/Banjo/Dimeji
Seepage and drainage collection pit is located at the right end of the Power House
Building where DV:1+588.35 ~ 1+598.85; DH: 0+097.50 ~ 0+125.00 and invert level
Kunle/Banjo
is at El. 106.00
This activity has been completed since June 2019.
- No concreting Kunle/Banjo
6b. Power house layout and Dam structures(Turbine oil tank room, Transformer
oil building, Cable trench and diesel generator building,)
General layout structural drawing of power house area revision 3 was submitted in
July 2021 with drawing numbers D-HS-PT-765 R3 to D-HS-PT-767 R3 and all the
associated structural works has commenced since August 2021.
The following activities was carried out during the week under review.
- Casting of 37nos. of concrete cover plate of the diesel generator room Kunle/Banjo/Dimeji
ACTIVITY CHALLENGE/ISSUE
ITEM Section Head/ Engineer in Charge
(PROGRESS STATUS) (QUALITY OF WORK, SPEED CORRECTIVE ACTION
OF WORK, METHOD OF PROPOSED/TAKEN
WORK)
7. Tailrace Apron
Construction of Tailrace Apron was commenced mid of March 2019. The following
activities were performed during the week under review;
- Concrete activities has been completed 100% on tailrace walls and Apron in the Kunle/Banjo
previous week.
For further concrete casting detail refer Attachment 1, Table 13.
4.0 Spillway
Construction activities of the Spillway Structure has been completed on the 12th of
December 2021.
A revised drawing R5 for concrete lift and zone was submitted with a letter CSC-
2965 dated on 22 December 2019. Referring to the drawing, the side piers in block
18 and 22 are tagged as Pier #1 and Pier #5 respectively and the middle piers in
block 19, block 20 and block 21 are also tagged as Pier #2, Pier #3 and Pier #4
respectively.
The construction activities of the spillway structure from Pier 5, pier 4, pier 3, pier
2 and pier 1 respectively (RCC Dam block 22# through block 17#) has been
Kunle/Banjo/Dimeji
completed.
- In compliance to the submitted method statement the spillway chute defect hole
was casted.
CONSTRUCTION CHALLENGE & TECHNICAL ISSUE FACED
ACTIVITY CHALLENGE/ISSUE
ITEM Section Head/ Engineer in Charge
(PROGRESS STATUS) (QUALITY OF WORK, SPEED CORRECTIVE ACTION
OF WORK, METHOD OF PROPOSED/TAKEN
WORK)
Unit #1
Presently, the load wet commisionninng test of unit 1# is ongoing.
During this week under review unit 2#, 3# and 4# are at halt after the no-load wet
commissioning tests and awaiting load tests.
Unit 4#:
No activity during the week of reporting. Amanuel, Gbenga, Aremu, Rotimi
A- Distributor Assembly:
Access to the distributor area has been locked and no activity during the week of
reporting.
B- Bearings:
No activity during the week of reporting.
No hydro-mechanical activities during the week reporting. Amanuel, Gbenga, Aremu, Rotimi
Powerhouse -
B- Bottom Outlet:
The bottom outlet maintenance gate and service gate are in the closed position.
D. Quick - Acting Emergency Intake Gates of Unit1 - Unit4: Amanuel, Gbenga, Aremu, Rotimi
Quick acting emergency intake gates no. 2#-4# are in the closed position. While,
gate 1# is in the open position purposely for conveying water to the runner.
E- Tailrace Gate:
Tailrace gates no. 1#- 4# are in the open position.
ACTIVITY CHALLENGE/ISSUE
ITEM Section Head/ Engineer in Charge
(PROGRESS STATUS) (QUALITY OF WORK, SPEED CORRECTIVE ACTION
OF WORK, METHOD OF PROPOSED/TAKEN
WORK)
E. Main Transformer:
No activity during the week of reporting.
ACTIVITY CHALLENGE/ISSUE
ITEM Section Head/ Engineer in Charge
(PROGRESS STATUS) (QUALITY OF WORK, SPEED CORRECTIVE ACTION
OF WORK, METHOD OF PROPOSED/TAKEN
WORK)
- Unit 1 #
A. Unit 1 Load Test commissioning:
The following test were carry out during the connection to the grid commissioning
b Manual Synchronization test; When the voltage value, phase angel value and
frequency value difference are more than the setting value, the voltage and
frequency values were adjusted manually. Also, when the voltage amplitude value,
frequency value and phase value difference between the unit and the power grid
were less than the fixed values , the GCB was manually closed to enable its
connection to the grid.
iv. Load rejection test at 25%, 50%, 75% and 100%; The Unit Automatic start to
connect with the grid by sending command from SCADA to open the GCB, The unit
is subjected to load rejection test at P= 25%, 50%, 75% and 100% were done
respectively; the unit run for 15min in each load point, 1GCB was used to reject
load. Thus, record was taken before, during and after the rejection, Also Run out
and vibration data during the load rejection test were recorded.
6.2
Grounding system
Civil works
i. 132kV / 330kv Zungeru Switchyard:
- Cleaning and cable trenches slope correction Banjo/Kunle /Dimeji
- For further concrete casting detail refer Attachment 1, Table 13
ACTIVITY CHALLENGE/ISSUE
ITEM Section Head/ Engineer in Charge
(PROGRESS STATUS) (QUALITY OF WORK, SPEED CORRECTIVE ACTION
OF WORK, METHOD OF PROPOSED/TAKEN
WORK)
Zungeru Switchyard: 330kv side
i.Preparation for commissioning on going Sunny/Defar/Adeolu/Isaac
Zungeru Switchyard: 132kv side /Femi/Ozigi
i. Preparation for commissioning on going
During the week under review, the quality testing of CVC concrete was followed up
by checking the temperature, air content, unit weight, slump, wet density of fresh
concrete, (diffussion of self-compaction concrete). the Cubes were also cast in
order to determine their compressive strength at 7, 28 and 90 days respectively .
Dunni
Details are given in table 1 of the attachment 1. In the same vein, the compressive
strength of hardened concrete at their required age were also followed up as
shown in table 3 of the attachment 1. All test results for compressive strength
after 28 days for CVC within the specification limits
CONSTRUCTION CHALLENGE & TECHNICAL ISSUE FACED
ACTIVITY CHALLENGE/ISSUE
ITEM Section Head/ Engineer in Charge
(PROGRESS STATUS) (QUALITY OF WORK, SPEED CORRECTIVE ACTION
OF WORK, METHOD OF PROPOSED/TAKEN
WORK)
8.2 Reinforcement
During this weak New consignment of diameter 12 Reinforcement Steel were
collected from the steel yard. One group sample was taken to ascertain .The
physical and mechanical Properties of the material. Test conducted include bend
test, tensile strength And elongation at maximum stress. All tests result so far meet Dunni
technical requirements.
8.3 Cement/Flyash
8.4 Aggregates
Weekly tests on aggregate like sieve analysis, specific gravity, flakiness and
elongation were carried out on aggregate of various sizes ranging between (0-5mm,
5-20mm, 20-40mm and 40-80mm). The material was sourced from Shamuyambo Dunni
granite quarry and sampled at RCC crushing plant conveyor belt. All test results
comply with ASTM Standard.
i. ER and the Contractor conducted a joint safety inspection and potential hazards
were identified and corrective actions were also implemented.
ii. Proactive safety measures are being adopted by both the ER, CSC and the labour
force to duely observe COVID-19 protocol such as washing of hands, using of hand
The Contractor will continue to
sanitizer, wearing of nose mask and maintaining social distance where possible.
identify known and unknown
iii. Damaged and unsafe work tools and equipments were identified during safety
Daramola Charles/ Dayo Adesiyan hazards and make
walks and immediate replacement made by the contractor
improvements to any safety
iv. CSC have been adviced to ensure that all the working area at night are well
issues raised
illuminated and also, make available an anti-venom for snake bite in case of any
emergency.
v. The contractor continues to ensure appropriate safety awareness for workers at height at
the power house, erection bay, spillway and power intake structure. Also, during the week
under review, corrective actions were implemented immediately for observed potential
hazards.
vi. The Contractor continued to monitor improvement in safety measures at all other The contractor has since then
project locations. Daramola Charles/ Dayo Adesiyan clear the surrounding to forestall
vii. No case of life threatening accident was recorded during the week. further occurrence.
viii. There was an incidence of fire outbreak at CNEEC warehouse II, on saturday the 12 th of
februar 2022. The fire was emanated from magazine area up to the warehourse 2 where
some items was affected by the fire.
Attachment 1 - Conc & Earth Work
Ta+B2:N16ble 1: Follow up of CVC Fresh Concrete
Air Content
Slump Test (mm) Temperature (OC)
S/no Sample No. Casting Date Unit Location Elevation Concrete Grade Mix Design No:
Require Actual Air Con (%)
2 R-9337 13/06/2022 Comprehensive work area Prefabricated cover plate / C25 PC-24 100-160 155 28.6 26.2 3.0
4 R-9339 13/06/2022 Dam Sand retaining sill A-8-9 wall / C20 CVC-67 50-100 65 32.4 27.1 2.6
6 R-9341 14/06/2022 Comprehensive work area Prefabricated cover plate / C25 PC-24 100-160 140 30.7 26.8 3.1
8 R-9343 15/06/2022 Dam Dam crest pavement 19# / C30 PC-21 100-160 145 25.3 25.6 3.0
9 R-9344 15/06/2022 Dam Sand retaining sill A-7 wall / C20 CVC-67 50-100 65 25.6 22.4 2.6
11 R-9346 15/06/2022 Comprehensive work area Prefabricated cover plate / C25 PC-24 100-160 145 31.0 24.4 2.9
12 R-9347 16/06/2022 Dam Dam crest pavement 21# / C30 PC-21 100-160 140 27.6 26.3 3.1
14 R-9349 16/06/2022 Comprehensive work area L2 road drainage ditch wall / C25 PC-20 100-160 155 28.7 24.5 2.9
15 R-9350 16/06/2022 Comprehensive work area Prefabricated cover plate / C25 PC-24 100-160 145 29.1 23.7 3.1
19 R-9354 17/06/2022 Comprehensive work area Prefabricated cover plate / C25 PC-24 100-160 110 24.5 25.8 2.9
20 R-9355 18/06/2022 Dam Wave wall of 21# EL235.1~EL236.2 C25 PC-20 100-160 135 25.8 24.8 2.9
21 R-9356 18/06/2022 Dam Dam crest pavement 17#18# / C30 PC-21 100-160 130 26.0 25.4 3.2
23 R-9358 18/06/2022 Comprehensive work area Prefabricated cover plate / C25 PC-24 100-160 135 27.9 25.3 2.9
24 R-9359 19/06/2022 Dam Fire pool installation room fire buttress / C20 PC-19 100-160 155 25.8 25.1 2.6
25 R-9360 19/06/2022 Dam Dam crest pavement 20# / C30 PC-21 100-160 120 26.9 25.6 3.0
27 R-9362 19/06/2022 Comprehensive work area Prefabricated cover plate / C25 PC-24 100-160 140 28.9 26.0 3.0
S/no Sample No: Casting Date Unit Location Elevation Concrete Grade Mix Design No: Crushing Date Age (Days) Ave. Compressive strength (MPa)
1 R-9311 07/06/2022 Comprehensive work area Prefabricated cover plate / C25 PC-24 14/06/2022 7 20.1
4 R-9314 08/06/2022 Dam Wave wall of 18# dam section EL232.9~EL234.0 C25 PC-20 15/06/2022 7 22.4
5 R-9315 08/06/2022 Dam Sand retaining sill A-4 wall / C20 CVC-37 15/06/2022 7 22.2
6 R-9316 08/06/2022 Comprehensive work area Prefabricated cover plate / C25 PC-24 15/06/2022 7 24.8
8 R-9318 09/06/2022 Comprehensive work area Prefabricated cover plate / C25 PC-24 16/06/2022 7 22.5
9 R-9319 08/06/2022 Dam Sand retaining sill A-7 cushion / C20 CVC-67 15/06/2022 7 24.9
10 R-9320 09/06/2022 Comprehensive work area L2 floor of road drainage ditch / C25 PC-20 16/06/2022 7 23.4
11 R-9321 09/06/2022 Dam Sand retaining sill A-7 cushion / C20 CVC-64 16/06/2022 7 21.5
13 R-9323 10/06/2022 Dam Sand retaining sill A-4 wall / C20 CVC-67 17/06/2022 7 23.4
14 R-9324 10/06/2022 Comprehensive work area Prefabricated cover plate / C25 PC-24 17/06/2022 7 23.6
17 R-9327 11/06/2022 Comprehensive work area Prefabricated cover plate / C25 PC-24 18/06/2022 7 27.4
18 R-9328 11/06/2022 Dam Sand retaining sill A-5 wall / C20 CVC-67 18/06/2022 7 23.0
20 R-9330 11/06/2022 Comprehensive work area Switchyard station fire water pipe buttress / C20 PC-19 18/06/2022 7 20.0
21 R-9331 11/06/2022 Dam Sand retaining sill A-8 cushion / C20 CVC-67 18/06/2022 7 22.8
24 R-9334 12/06/2022 Comprehensive work area Prefabricated cover plate / C25 PC-24 19/06/2022 7 24.6
27 R-9337 13/06/2022 Comprehensive work area Prefabricated cover plate / C25 PC-24 20/06/2022 7 24.6
Road pavement of rockfill dam on the left
28 R-9338 13/06/2022 Dam
bank C-10B
EL234.8~EL235.0 C25 PC-20 20/06/2022 7 21.9
29 R-9339 13/06/2022 Dam Sand retaining sill A-8-9 wall / C20 CVC-67 20/06/2022 7 19.1
30 R-9216 17/05/2022 Dam Rockfill dam crest highway EL234.8~EL235.0 C25 CVC-29 14/06/2022 28 36.9
31 R-9217 17/05/2022 Dam Dam crest pavement 43#~48# EL232.9~EL233.0 C30 PC-21 14/06/2022 28 43.5
32 R-9218 17/05/2022 Comprehensive work area Prefabricated cover plate / C25 PC-24 14/06/2022 28 26.2
33 R-9219 18/05/2022 CSCEC Switchyard network room floor ramp / C25 PC-24 15/06/2022 28 28.5
34 R-9220 18/05/2022 Dam Dam crest pavement 40#~42# EL232.9~EL233.0 C30 PC-21 15/06/2022 28 41.3
35 R-9221 18/05/2022 Dam Fire pipeline pier / C20 PC-19 15/06/2022 28 25.3
36 R-9222 18/05/2022 Dam Dam crest pavement 17# EL232.9~EL234.0 C30 PC-21 15/06/2022 28 32.9
37 R-9223 18/05/2022 Comprehensive work area Prefabricated cover plate / C25 PC-24 15/06/2022 28 26.3
39 R-9225 19/05/2022 Dam Dam crest pavement 48#~50# EL232.9~EL233.0 C30 PC-21 16/06/2022 28 41.5
40 R-9226 19/05/2022 Dam Wave wall of 53# dam section EL232.9~EL234.0 C25 PC-20 16/06/2022 28 32.5
41 R-9227 19/05/2022 Dam Wave wall of 59# dam section EL232.9~EL234.0 C25 PC-20 16/06/2022 28 32.8
42 R-9228 19/05/2022 Comprehensive work area Prefabricated cover plate / C25 PC-24 16/06/2022 28 26.0
43 R-9229 19/05/2022 Dam Fire pipeline pier / C20 PC-19 16/06/2022 28 26.4
44 R-9230 19/05/2022 Comprehensive work area Switchyard T5-T7 brick wall / C25 PC-20 16/06/2022 28 28.0
45 R-9231 20/05/2022 Dam Dam crest pavement 38#~40# EL232.9~EL233.0 C30 PC-21 17/06/2022 28 40.8
46 R-9232 20/05/2022 Dam Dam crest pavement 38#~40# EL232.9~EL233.0 C30 PC-21 17/06/2022 28 42.9
47 R-9233 20/05/2022 Comprehensive work area Prefabricated cover plate / C25 PC-24 17/06/2022 28 25.1
48 R-9234 20/05/2022 Dam Fire pipeline pier / C20 PC-19 17/06/2022 28 23.0
49 R-9235 21/05/2022 Dam Dam crest pavement 39#~41# EL232.9~EL233.0 C30 PC-21 18/06/2022 28 40.2
50 R-9236 21/05/2022 Dam Dam crest pavement 55#~56# EL232.9~EL233.0 C30 PC-21 18/06/2022 28 42.0
51 R-9237 21/05/2022 Dam Rockfill dam crest highway EL234.8~EL235.0 C25 CVC-29 18/06/2022 28 32.5
52 R-9238 21/05/2022 Comprehensive work area Prefabricated cover plate / C25 PC-24 18/06/2022 28 26.0
54 R-9240 22/05/2022 Dam Dam crest pavement 40#~42# EL232.9~EL233.0 C30 PC-21 19/06/2022 28 42.0
55 R-9241 22/05/2022 Dam Dam crest pavement 50#~51# EL232.9~EL233.0 C30 PC-21 19/06/2022 28 40.6
56 R-9242 22/05/2022 Comprehensive work area Prefabricated cover plate / C25 PC-24 19/06/2022 28 26.2
57 R-9243 22/05/2022 Dam Fire pipeline pier / C20 PC-19 19/06/2022 28 24.2
58 R-9244 23/05/2022 Dam Dam crest pavement 35#43# EL232.9~EL233.0 C30 PC-21 20/06/2022 28 36.7
59 R-9245 23/05/2022 Dam Dam crest pavement 49#52#57# EL232.9~EL233.0 C30 PC-21 20/06/2022 28 37.8
60 R-9246 23/05/2022 Dam Fire pipeline pier / C20 PC-19 20/06/2022 28 23.8
61 R-9247 23/05/2022 Dam Wave wall of 19# dam section EL232.9~EL234.0 C25 PC-20 20/06/2022 28 32.9
62 R-9248 23/05/2022 Dam Fire water pipe anchor block a-23 / C20 PC-19 20/06/2022 28 25.6
63 R-9249 23/05/2022 Comprehensive work area Prefabricated cover plate / C25 PC-24 20/06/2022 28 36.8
S/no Sample No: Casting Date Location Chainage Elevation Concrete Grade Mix Design No: Crushing Date Age (Days) Ave. Compressive strength (MPa)
1 Number of Test Minimum (Mpa) Maximum (Mpa) Average(Mpa) Standard Deviation (Mpa) Requirement
2 51 25.1 36.9 29.8 For 28 days=25mpa
Note: Practice for Evaluation of Strength Test of Concrete ACI 214-77 tableau 3.5), The Results of concrete Excellent (σ <2.81 MPA)
1 Number of Test Minimum (Mpa) Maximum (Mpa) Average(Mpa) Standard Deviation (Mpa) Requirement
Note: Practice for Evaluation of Strength Test of Concrete ACI 214-77 tableau 3.5), The Results of concrete Excellent (σ <2.81 MPA)
1 Number of Test Minimum (Mpa) Maximum (Mpa) Average(Mpa) Standard Deviation (Mpa) Requirement
2 For 90 days=35mpa
Note: Practice for Evaluation of Strength Test of Concrete ACI 214-77 tableau 3.5), The Results of concrete Excellent (σ <2.81 MPA)
1 B-394 17/05/2022 14/06/2022 99.06 28.2 1 3.08 200 277 Lafarge 28 52.2
2 B-396 08/06/2022 15/06/2022 99.14 28.6 1 3.09 194 261 Lafarge 7 35.1
S/N Date Location (Block - Zone) Concrete Type Elevation (m) Volume (m³)
1 12/06/2022 The left ACRD crest road CVC 234.8 ' 235.00 12
5 15/06/2022 Pavement layer block 19#- C CVC 232.900 ' 233.00 7.5
The left ACRD crest road
6 15/06/2022 CVC 234.8 ' 235.00 24
L-A-5B, L- A-10D
8 17/06/2022 Parapet wall Block 21# -C CVC 232.90 ' 234.00 9.2
10 18/06/2022 Parapet wall of the right ACRD Block 7 CVC 234.8 ' 235.00 10.5
11 18/06/2022 Pavement layer block 17#-2A, 17#-4A, 18#-1B CVC 232.9 ' 233.00 12
12 18/06/2022 The left ACRD crest road CVC 234.8 ' 235.00 28.5
Table 13 Concrete Volume Report for Power House , Power Intake, Erection bay and Central Control Building.
No Date Location (Unit - Zone-Lift) Concrete Type Elevation (m)/Chainage Volume (m³)
2 13/06/2022 Dissipation basin side weir A-8 CVC 144.00 ' 146.0 71
Completed
Description
Total drilling Grout quantity Average
Sequence
Block No.
Location
Hole Hole (NO.) Result for P *(Primary hole )
(%)
(NO.) finished
recovery
&
Inside 0-3 LU 3-15 LU > 15 LU
Core
Inside Con-
(%)
Required grouting Littre Kg L/m Kg/m
crete (m) Rock(m) (hole no.) (hole no.) (hole no.)
P 236.0 236.0 523.5 1,327.0 74.0 95.0 67.0 76,705.7 60,384.0 57.8 45.5
7 S 253.0 253.0 573.5 1,469.0 NA NA NA 19,074.6 14,615.2 13.0 9.9 100.0%
CH 29.0 29.0 108.2 163.0 29.0 0.0 0.0 112.9 86.3 0.7 0.5 5.9%
P 98.0 98.0 300.3 541.0 40.0 33.0 25.0 23,965.9 18,464.4 44.3 34.1
8 S 85.0 85.0 273.6 470.0 NA NA NA 3,045.4 2,294.3 6.5 4.9 100.0%
CH 14.0 14.0 87.2 73.0 14.0 0.0 0.0 10.2 7.7 0.1 0.1 7.7%
P 94.0 94.0 455.8 518.0 41.0 29.0 24.0 36,038.7 29,070.7 69.6 56.1
9 S 96.0 96.0 514.3 537.0 NA NA NA 4,424.8 3,335.4 8.2 6.2 100.0%
CH 12.0 12.0 89.7 72.0 12.0 0.0 0.0 12.3 9.3 0.2 0.1 6.3%
P 75.0 75.0 362.3 411.0 25.0 36.0 14.0 16,368.8 12,638.8 39.8 30.8
10 S 86.0 86.0 496.3 472.0 NA NA NA 3,924.4 2,958.3 8.3 6.3 100.0%
None-Over flow section ( Bill No.10).
CH 13.0 13.0 89.6 77.0 13.0 0.0 0.0 29.7 22.4 0.4 0.3 8.1%
P 84.0 84.0 223.6 420.0 28.0 37.0 19.0 8,943.1 6,741.0 21.3 16.1
11 S 71.0 71.0 211.0 355.0 NA NA NA 1,852.8 1,395.5 5.2 3.9 100.0%
CH 11.0 11.0 29.0 55.0 11.0 0.0 0.0 244.3 184.1 4.4 3.3 7.1%
Right Bank
P 84.0 84.0 118.9 420.0 50.0 21.0 13.0 6,293.3 4,744.2 15.0 11.3
12 S 77.0 77.0 121.9 385.0 NA NA NA 1,602.1 1,207.3 4.2 3.1 100.0%
CH 10.0 10.0 17.1 50.0 10.0 0.0 0.0 179.5 135.4 3.6 2.7 6.2%
P 72.0 72.0 191.7 360.0 30.0 24.0 18.0 16,105.0 12,462.6 44.7 34.6
13 S 77.0 77.0 208.1 385.0 NA NA NA 3,835.1 2,891.3 10.0 7.5 100.0%
CH 13.0 13.0 56.0 65.0 13.0 0.0 0.0 165.2 124.6 2.5 1.9 8.7%
P 84.0 84.0 355.2 462.0 29.0 32.0 23.0 31,551.6 25,294.4 68.3 54.7
14 S 66.0 66.0 291.5 366.0 NA NA NA 4,938.7 3,720.1 13.5 10.2 100.0%
CH 14.0 14.0 95.7 76.0 14.0 0.0 0.0 85.0 64.1 1.1 0.8 9.3%
P 84.0 84.0 156.8 462.0 31.0 21.0 32.0 46,767.0 38,367.1 101.2 83.0
15 S 77.0 77.0 141.4 427.0 NA NA NA 3,485.0 2,625.6 8.2 6.1 100.0%
CH 9.0 9.0 19.2 51.0 9.0 0.0 0.0 87.5 65.9 1.7 1.3 5.6%
P 72.0 72.0 189.2 396.0 27.0 27.0 18.0 22,034.5 16,869.0 55.6 42.6
16 S 82.0 82.0 208.1 452.0 NA NA NA 2,923.3 2,204.1 6.5 4.9 100.0%
CH 10.0 10.0 29.5 53.0 10.0 0.0 0.0 123.1 92.7 2.3 1.7 6.5%
P 87.0 87.0 433.4 477.0 52.0 23.0 12.0 17,128.6 13,554.9 35.9 28.4
17 S 84.0 84.0 442.5 462.0 NA NA NA 5,073.1 3,823.8 11.0 8.3 100.0%
CH 12.0 12.0 87.6 72.0 12.0 0.0 0.0 205.7 154.9 2.9 2.2 7.0%
P 91.0 91.0 237.6 476.0 53.0 24.0 14.0 10,401.5 7,840.9 21.9 16.5
18 S 84.0 84.0 213.3 438.0 NA NA NA 2,517.1 1,893.6 5.7 4.3 100.0%
CH 12.0 12.0 39.0 66.0 12.0 0.0 0.0 273.4 206.2 4.1 3.1 6.9%
Over flow section ( Bill No.12).
P 78.0 78.0 264.7 408.0 40.0 25.0 13.0 9,875.7 7,432.1 24.2 18.2
19 S 98.0 98.0 340.2 511.0 NA NA NA 1,756.0 1,323.8 3.4 2.6 100.0%
CH 13.0 13.0 52.7 68.0 13.0 0.0 0.0 162.5 122.6 2.4 1.8 7.4%
Right Bank
P 98.0 98.0 104.3 511.0 51.0 33.0 14.0 10,011.3 7,845.8 19.6 15.4
20 S 78.0 78.0 80.1 390.0 NA NA NA 1,754.2 1,321.9 4.5 3.4 100.0%
CH 13.0 13.0 15.4 65.0 13.0 0.0 0.0 87.6 66.1 1.3 1.0 7.4%
P 72.0 72.0 100.6 378.0 41.0 21.0 10.0 9,846.9 7,416.1 26.1 19.6
21 S 71.0 71.0 116.5 355.0 NA NA NA 2,732.1 2,060.1 7.7 5.8 100.0%
CH 10.0 10.0 53.1 50.0 10.0 0.0 0.0 35.4 26.7 0.7 0.5 7.0%
P 93.0 93.0 517.7 486.0 42.0 34.0 17.0 13,739.5 10,493.9 28.3 21.6
22 S 83.0 83.0 668.8 430.0 NA NA NA 3,712.4 2,798.0 8.6 6.5 100.0%
CH 14.0 14.0 200.1 73.0 14.0 0.0 0.0 115.7 87.1 1.6 1.2 8.0%
Right Bank P 81.0 81.0 135.2 441.0 30.0 28.0 23.0 17,695.5 13,345.7 40.1 30.3
Bottom
23 S 86.0 86.0 166.4 466.0 NA NA NA 2,985.7 2,249.3 6.4 4.8 100.0%
Outlet
( Bill No.7). CH 12.0 12.0 21.6 69.0 12.0 0.0 0.0 78.3 59.0 1.1 0.9 7.2%
P 80.0 80.0 483.0 442.0 53.0 18.0 9.0 5,402.5 3,717.3 12.2 8.4
24 S 68.0 68.0 448.6 376.0 NA NA NA 607.9 458.3 1.6 1.2 100.0%
CH 8.0 8.0 54.1 46.0 8.0 0.0 0.0 46.0 34.7 1.0 0.8 5.4%
P 82.0 82.0 329.4 452.0 39.0 38.0 5.0 5,111.3 3,852.1 11.3 8.5
25 S 77.0 77.0 300.8 427.0 NA NA NA 926.5 697.7 2.2 1.6 100.0%
Diversion channel section ( Bill No.10).
CH 8.0 8.0 33.1 46.0 8.0 0.0 0.0 85.2 64.2 1.9 1.4 5.0%
P 96.0 96.0 246.3 248.2 86.0 8.0 2.0 1,388.4 1,218.6 5.6 4.9
26 S 104.0 104.0 544.9 284.1 NA NA NA 562.0 496.5 2.0 1.7 100.0%
CH 13.0 13.0 35.6 65.3 13.0 0.0 0.0 20.1 15.6 0.3 0.2 5.6%
Left Bank
Diversion channel section ( Bill No.10).
Left Bank
P 96.0 96.0 239.4 487.7 43.0 49.0 4.0 6,348.8 6,194.1 13.0 12.7
27 S 104.0 104.0 255.6 524.2 NA NA NA 2,837.4 2,767.1 5.4 5.3 100.0%
CH 10.0 10.0 27.2 50.2 10.0 0.0 0.0 190.5 186.3 3.8 3.7 5.0%
P 66.0 66.0 415.1 330.0 8.0 38.0 20.0 13,836.6 13,521.3 41.9 41.0
28 S 73.0 73.0 450.1 365.3 NA 30.0 NA 2,492.1 2,437.0 6.8 6.7 100.0%
CH 7.0 7.0 45.2 35.2 7.0 0.0 0.0 75.0 73.4 2.1 2.1 5.0%
P 77.0 77.0 109.9 385.0 48.0 26.0 3.0 2,493.7 2,438.2 6.5 6.3
29 S 60.0 60.0 90.7 300.0 NA NA NA 1,181.8 1,155.8 3.9 3.9 100.0%
CH 7.0 7.0 24.2 35.0 7.0 0.0 0.0 82.7 80.7 2.4 2.3 5.1%
P 66.0 66.0 144.5 366.0 46.0 15.0 5.0 6,142.4 4,810.6 16.8 13.1
30 S 70.0 70.0 143.1 392.0 NA NA NA 341.4 257.1 0.9 0.7 100.0%
CH 7.0 7.0 14.3 38.0 7.0 0.0 0.0 37.1 27.9 1.0 0.7 5.1%
P 105.0 105.0 388.7 1,239.0 64.0 37.0 4.0 20,729.6 16,586.1 16.7 13.4
31 S 92.0 92.0 373.4 1,100.0 NA NA NA 1,137.9 857.4 1.0 0.8 100.0%
CH 11.0 11.0 55.1 128.0 11.0 0.0 0.0 16.6 12.5 0.1 0.1 5.6%
P 96.0 96.0 146.8 1,104.0 50.0 33.0 13.0 13,636.9 10,249.6 12.4 9.3
Intake section ( Bill No.13).
P 96.0 96.0 149.6 1,104.0 59.0 28.0 9.0 16,115.7 12,121.3 14.6 11.0
33 S 96.0 96.0 166.7 1,160.0 NA NA NA 4,918.3 3,707.7 4.2 3.2 100.0%
CH 10.0 10.0 64.4 122.0 10.0 0.0 0.0 111.6 84.1 0.9 0.7 5.2%
P 108.0 108.0 147.1 1,256.0 57.0 44.0 7.0 13,515.3 10,188.8 10.8 8.1
34 S 96.0 96.0 132.3 1,160.0 NA NA NA 2,453.4 1,849.4 2.1 1.6 100.0%
CH 11.0 11.0 16.2 137.0 11.0 0.0 0.0 39.0 29.5 0.3 0.2 5.4%
P 80.0 80.0 452.0 913.0 47.0 29.0 4.0 9,698.9 7,427.0 10.6 8.1
35 S 80.0 80.0 648.7 920.0 NA NA NA 2,734.1 2,060.7 3.0 2.2 100.0%
CH 10.0 10.0 149.3 115.0 10.0 0.0 0.0 211.2 159.6 1.8 1.4 6.3%
P 90.0 90.0 59.9 860.0 62.0 27.0 1.0 2,028.8 1,529.8 2.4 1.8
Unit # 1 S 72.0 72.0 120.6 639.0 NA NA NA 429.0 323.7 0.7 0.5 100.0%
CH 9.0 9.0 24.0 86.0 9.0 0.0 0.0 104.8 76.1 1.2 0.9 5.6%
Powerhouse (Bill No.11).
P 72.0 72.0 65.0 688.0 50.0 21.0 1.0 2,368.4 1,785.3 3.4 2.6
Unit # 2 S 72.0 72.0 133.2 639.0 NA NA NA 655.6 494.3 1.0 0.8 100.0%
Left Bank
CH 8.0 8.0 21.7 85.0 8.0 0.0 0.0 26.2 19.9 0.3 0.2 5.6%
Powerhouse (Bill No.11).
Left Bank
P 81.0 81.0 66.3 774.0 55.0 26.0 0.0 1,993.8 1,503.1 2.6 1.9
Unit # 3 S 64.0 64.0 111.8 568.0 NA NA NA 777.4 586.9 1.4 1.0 100.0%
CH 9.0 9.0 29.3 79.0 9.0 0.0 0.0 52.1 39.4 0.7 0.5 6.2%
P 95.0 95.0 96.0 886.0 65.0 26.0 4.0 4,042.8 3,079.1 4.6 3.5
Unit # 4 S 94.0 94.0 167.4 822.0 NA NA NA 956.2 720.2 1.2 0.9 100.0%
CH 10.0 10.0 39.5 80.0 10.0 0.0 0.0 81.2 61.3 1.0 0.8 5.3%
P 41.0 41.0 308.5 235.0 13.0 19.0 9.0 6,943.4 5,343.8 29.5 22.7
36 S 45.0 45.0 337.3 243.0 NA NA NA 1,893.4 1,427.7 7.8 5.9 100.0%
CH 7.0 7.0 79.2 38.0 7.0 0.0 0.0 183.8 138.5 4.8 3.6 8.1%
P 48.0 48.0 135.4 216.0 12.0 15.0 9.0 4,872.4 3,672.6 22.6 17.0
37 S 35.0 35.0 92.1 140.0 NA NA NA 647.7 488.3 4.6 3.5 100.0%
CH 2.0 0.0 2.6 10.0 2.0 0.0 0.0 16.8 12.6 1.7 1.3 2.4%
P 48.0 48.0 221.5 276.0 28.0 17.0 3.0 1,931.1 1,456.9 7.0 5.3
38 S 49.0 49.0 229.7 266.0 NA NA NA 584.7 440.7 2.2 1.7 100.0%
CH 6.0 6.0 37.6 33.0 6.0 0.0 0.0 140.2 105.6 4.2 3.2 6.2%
P 56.0 56.0 109.8 322.0 33.0 14.0 9.0 5,087.8 3,834.8 15.8 11.9
39 S 42.0 42.0 80.5 228.0 NA NA NA 810.1 610.6 3.6 2.7 100.0%
CH 7.0 7.0 30.1 41.0 7.0 0.0 0.0 9.0 6.8 0.2 0.2 7.1%
P 49.0 49.0 221.2 287.0 25.0 16.0 8.0 5,209.7 3,925.9 18.2 13.7
40 S 46.0 46.0 249.3 251.0 NA NA NA 1,831.5 1,380.4 7.3 5.5 100.0%
CH 7.0 7.0 88.9 38.0 7.0 0.0 0.0 47.4 35.8 1.2 0.9 7.4%
P 36.0 36.0 163.7 216.0 13.0 17.0 6.0 1,705.1 1,285.5 7.9 6.0
41 S 39.0 39.0 189.7 216.0 NA NA NA 559.6 420.7 2.6 1.9 100.0%
CH 4.0 4.0 46.5 23.0 4.0 0.0 0.0 14.8 11.2 0.6 0.5 5.3%
P 42.0 42.0 98.9 252.0 18.0 18.0 6.0 3,229.5 2,433.9 12.8 9.7
42 S 30.0 30.0 59.8 168.0 NA NA NA 326.6 246.3 1.9 1.5 100.0%
CH 5.0 5.0 9.9 31.0 5.0 0.0 0.0 22.8 17.2 0.7 0.6 6.9%
P 36.0 36.0 140.3 222.0 19.0 15.0 2.0 1,291.6 973.4 5.8 4.4
43 S 32.0 32.0 142.6 181.0 NA NA NA 244.1 183.8 1.3 1.0 100.0%
CH 4.0 4.0 15.1 23.0 4.0 0.0 0.0 28.3 21.5 1.2 0.9 5.9%
P 27.0 27.0 60.1 171.0 23.0 3.0 1.0 388.2 292.6 2.3 1.7
44 S 28.0 28.0 53.4 160.7 NA NA NA 138.5 104.3 0.9 0.6 100.0%
CH 3.0 3.0 11.2 18.0 3.0 0.0 0.0 10.6 8.1 0.6 0.5 5.5%
section ( Bill No.10).
t Bank
P 28.0 28.0 76.6 182.0 22.0 5.0 1.0 932.8 703.1 5.1 3.9
45 S 23.0 23.0 67.9 133.0 NA NA NA 274.2 206.6 2.1 1.6 100.0%
CH 4.0 4.0 7.9 23.0 4.0 0.0 0.0 31.4 23.7 1.4 1.0 7.8%
P 28.0 28.0 56.6 182.0 15.0 13.0 0.0 793.8 598.4 4.4 3.3
46 S 21.0 21.0 49.0 126.0 NA NA NA 118.9 89.8 0.9 0.7 100.0%
None-Over flow section ( Bill No.10). CH 4.0 4.0 16.5 23.0 4.0 0.0 0.0 13.7 10.2 0.6 0.4 8.2%
P 24.0 24.0 32.2 156.0 1.0 22.0 1.0 1,253.7 945.1 8.0 6.1
47 S 21.0 21.0 26.8 126.0 NA NA NA 98.3 74.1 0.8 0.6 100.0%
CH 3.0 3.0 4.9 15.0 3.0 0.0 0.0 6.6 5.0 0.4 0.3 6.7%
28.0 28.0 50.6 182.0 1,182.0 891.5
Left Bank
Completed
WPT (LU)
Description
Sequence
Block No.
(%)
Location
Hole (NO.) Stage(NO.) Stage (NO.) Depth Inside Con- Inside 0-3 LU 3-15 LU > 15 LU
Depth (m) Hole (NO.) (m) Littre Kg L/m Kg/m
Required Required crete (m) Rock(m) (hole no.) (hole no.) (hole no.)
P/Pr 17.0 107.0 690.4 17.0 107.0 690.4 155.4 535.0 76.0 25.0 6.0 16,809.4 13,148.6 31.4 24.6
S 18.0 108.0 698.1 18.0 108.0 698.1 158.1 540.0 NA NA NA 4,909.8 3,771.9 9.1 7.0
7~ 11 T 36.0 216.0 1,396.2 36.0 216.0 1,396.2 316.2 1,080.0 NA NA NA 3,479.0 2,622.8 3.2 2.4 100.0%
Q 6.0 6.0 165.8 72.4 93.4 NA NA NA 127.6 96.2 1.4 1.0
CH 8.0 41.0 278.6 68.7 209.9 41.0 0.0 0.0 1,382.2 1,041.5 6.6 5.0
P/Pr 7.0 45.0 258.0 7.0 46.0 258.0 28.0 230.0 34.0 9.0 3.0 23,136.1 18,940.0 100.6 82.3
Right Bank S 6.0 36.0 204.0 6.0 36.0 204.0 24.0 180.0 NA NA NA 7,800.0 6,656.7 43.3 37.0
None-Over
11~ 14 T 12.0 72.0 408.0 12.0 72.0 408.0 48.0 360.0 NA NA NA 563.7 424.9 1.6 1.2 100.0%
flow section
( Bill No.10). Q
CH 3.0 18.0 102.0 12.0 90.0 18.0 0.0 0.0 113.0 85.5 1.3 1.0
P/Pr 10.0 63.0 358.5 10.0 63.0 358.5 43.5 315.0 58.0 5.0 0.0 3,467.3 2,612.9 11.0 8.3
S 10.0 60.0 346.0 10.0 60.0 346.0 46.0 300.0 NA NA NA 1,325.9 999.3 4.4 3.3
14~ 17 T 20.0 120.0 691.7 20.0 120.0 691.7 91.7 600.0 NA NA NA 1,741.9 1,312.8 2.9 2.2 100.0%
Q
CH 4.0 22.0 128.9 19.1 109.8 22.0 0.0 0.0 67.7 51.0 0.6 0.5
P/Pr 12.0 100.0 558.5 12.0 100.0 558.5 58.5 500.0 99.0 1.0 0.0 596.2 449.1 1.2 0.9
Right Bank S 12.0 96.0 581.8 13.0 104.0 581.8 55.8 480.0 NA NA NA 383.0 288.4 0.8 0.6
Over flow T 26.0 208.0 1,119.6 25.0 200.0 1,119.6 125.6 1,040.0 NA NA NA 623.8 470.5 0.6 0.5
18~ 22 100.0%
section
Q
( Bill No.12).
CH 3.0 27.0 154.2 17.2 137.0 3.0 0.0 0.0 30.5 23.0 0.2 0.2
P/Pr 3.0 25.0 137.3 3.0 25.0 137.3 12.3 125.0 25.0 0.0 0.0 439.0 331.5 3.5 2.7
Right Bank S 2.0 16.0 88.7 2.0 16.0 88.7 8.7 80.0 NA NA NA 20.9 15.9 0.3 0.2
Bottom
23 T 5.0 40.0 220.9 5.0 40.0 220.9 20.9 200.0 NA NA NA 17.8 13.3 0.1 0.1 100.0%
Outlet
( Bill No.7). Q
CH 1.0 11.0 58.6 4.5 54.1 11.0 0.0 0.0 22.5 17.1 0.4 0.3
P/Pr 5.0 32.0 185.0 5.0 32.0 185.0 25.0 160.0 32.0 0.0 0.0 163.4 123.1 1.0 0.8
S 5.0 30.0 173.2 5.0 30.0 173.2 23.2 150.0 NA NA NA 50.3 37.8 0.3 0.3
24~25 T 10.0 60.0 347.6 10.0 60.0 347.6 47.6 300.0 NA NA NA 81.0 61.1 0.3 0.2 100.0%
Q
CH 2.0 16.0 95.3 8.9 86.4 3.0 0.0 0.0 22.3 16.7 0.3 0.2
P/Pr 6.0 38.0 226.5 6.0 38.0 226.5 36.5 190.0 32.0 6.0 0.0 1,903.2 1,434.1 10.0 7.5
Left Bank
Diversion S 6.0 36.0 216.3 6.0 36.0 216.3 36.3 180.0 6.0 0.0 0.0 142.0 105.0 0.8 0.6
channel 26~27 T 12.0 72.0 432.8 12.0 72.0 432.8 162.8 270.0 12.0 0.0 0.0 95.9 72.7 0.4 0.3 100.0%
section Q
( Bill No.10).
CH 4.0 38.0 88.9 25.2 63.7 4.0 0.0 0.0 4.1 88.1 0.1 1.4
P/Pr 7.0 44.0 249.7 7.0 45.0 254.7 29.7 225.0 45.0 0.0 0.0 24.2 18.3 0.1 0.1
S 8.0 48.0 274.3 8.0 48.0 302.8 34.3 268.5 NA NA NA 50.7 38.2 0.2 0.1
28~30 T 15.0 90.0 514.6 15.0 90.0 514.6 64.6 450.0 NA NA NA 44.1 39.7 0.1 0.1 100.0%
Q
CH 3.0 23.0 124.5 13.2 111.3 23.0 0.0 0.0 2.4 1.8 0.0 0.0
P/Pr 13.0 96.0 592.9 13.0 96.0 592.9 110.9 482.0 96.0 0.0 0.0 114.1 86.2 0.2 0.2
Left Bank S 12.0 84.0 528.2 12.0 84.0 528.2 108.2 420.0 NA NA NA 52.3 39.8 0.1 0.1
Intake
31~34 T 27.0 193.0 1,191.0 27.0 193.0 1,191.0 227.0 964.0 NA NA NA 92.0 69.0 0.1 0.1 100.0%
section
( Bill No.13). Q
CH 4.0 32.0 194.9 39.7 155.2 32.0 0.0 0.0 16.3 12.3 0.1 0.1
P/Pr 12.0 79.0 456.8 12.0 79.0 456.8 59.8 397.0 79.0 0.0 0.0 202.1 152.9 0.5 0.4
S 12.0 75.0 432.1 12.0 75.0 432.1 56.1 376.0 NA NA NA 362.3 272.9 1.0 0.7
T 24.0 150.0 875.4 24.0 150.0 875.4 118.4 757.0 NA NA NA 523.3 381.9 0.7 0.5
35~39 100.0%
Q
CH 4.0 32.0 177.7 18.6 159.1 32.0 0.0 0.0 29.0 21.9 0.2 0.1
P/Pr 13.0 83.0 493.4 1.0 7.0 39.5 4.5 35.0 7.0 0.0 0.0 14.3 10.8 0.4 0.3
S 12.0 72.0 432.4 0.0 0.0 0.0 0.0 0.0 NA NA NA 0.0 0.0 0.0 0.0
T 25.0 150.0 901.1 1.0 6.0 34.0 4.0 30.0 NA NA NA 49.2 36.9 1.6 1.2
40~44 100.0%
Q
CH 4.0 36.0 195.4 27.2 185.0 36.0 0.0 0.0 33.4 26.1 1.2 1.0
Left Bank P/Pr 15.0 69.0 416.1 10.0 49.0 292.7 47.2 245.5 41.0 8.0 0.0 15,513.7 12,817.1 63.2 52.2
None-Over
S 15.0 65.0 395.7 9.0 36.0 223.4 43.4 180.0 NA NA NA 6,041.3 4,810.6 33.6 26.7
flow section
45~50 T 30.0 129.0 791.1 18.0 78.0 474.9 84.9 390.0 NA NA NA 1,480.5 1,140.5 3.8 2.9 100.0%
( Bill No.10).
Q
CH
Left Bank
None-Over
flow section
( Bill No.10).
P/Pr 12.0 52.0 317.2 12.0 54.0 327.2 57.2 270.0 46.0 8.0 0.0 9,873.4 7,777.2 36.6 28.8
S 13.0 52.0 321.7 13.0 53.0 326.7 61.7 265.0 NA NA NA 5,816.6 5,417.0 21.9 20.4
51~55 T 25.0 100.0 620.1 25.0 100.0 620.1 120.1 525.0 NA NA NA 1,257.0 947.7 2.4 1.8 100.0%
Q
CH
P/Pr 14.0 60.0 389.4 3.0 13.0 78.4 13.4 65.0 12.0 1.0 0.0 707.8 533.4 10.9 8.2
S 14.0 56.0 368.7 2.0 8.0 50.0 10.0 40.0 NA NA NA 401.2 302.4 10.0 7.6
56~60 T 29.0 116.0 7,632.0 5.0 20.0 123.3 23.3 100.0 NA NA NA 173.8 131.0 1.7 1.3 100.0%
Q
CH 6.0 6.0 202.7 45.3 215.4 NA NA NA 186.4 150.5 0.5 0.3
P/Pr 14.0 66.0 586.9 14.0 71.0 611.9 223.9 388.0 50.0 18.0 2.0 4,922.5 3,738.6 12.7 9.6
S 12.0 53.0 480.1 12.0 52.0 416.0 169.9 246.1 4.0 0.0 0.0 314.6 206.8 1.1 0.7
DV 2360 ~
T 24.0 106.0 961.1 24.0 106.0 961.1 278.6 682.5 16.0 0.0 0.0 871.7 692.0 1.3 1.1 100.0%
2460
Q
CH 7.0 7.0 195.9 39.8 195.9 NA NA NA 168.3 126.7 0.9 0.6
Total 637.0 3,668.0 29,561.1 571.0 3,402.0 20,073.2 3,847.2 17,286.9 979.0 81.0 11.0 118,689.7 94,493.0 6.9 5.5 100.0%
ATTACHMENT 2, Week 04
Summary for progress of RCC /Bedrock Drainage Holes at 28 - 01-2023
Design finished Quantity
Completed
Hole (NO.) Inside Con- Inside Rock Inside Con- Inside Rock
(m) Hole (NO.) (m)
( %)
Required crete (m) crete (m)
Rock(m) Rock(m)
B7-B8 59.0 623.8 885.8 1509.5 59.0 623.8 885.8 1509.6 100.0%
B9-B12 71.0 594.2 1018.9 1613.1 71.0 594.2 1018.9 1613.1 100.0%
B13-B16 67.0 292.2 957.9 1250.1 67.0 292.2 957.9 1250.1 100.0%
B17-B19 47.0 177.1 700.8 877.9 47.0 177.1 711.2 888.3 100.0%
B20-B21 47.0 130.2 613.8 744.0 47.0 130.2 613.8 744.0 100.0%
B22-B24 58.0 271.3 789.8 1061.1 58.0 271.3 789.8 1061.1 100.0%
B25-B27 59.0 283.0 812.2 1095.2 59.0 242.4 710.9 953.3 100.0%
B28-B30 41.0 132.6 641.9 774.5 41.0 130.3 602.1 732.4 100.0%
B31-B34 91.0 806.6 1284.9 2091.5 91.0 806.6 1284.9 2091.5 100.0%
B35-B44 68.0 369.2 1408.0 1777.2 68.0 369.2 1408.0 1777.2 100.0%
B45-B54 70.0 346.5 1118.9 1465.4 70.0 346.5 1118.9 1465.4 100.0%
B55-B60 47.0 306.1 681.2 987.3 47.0 306.1 681.2 987.3 100.0%
Total 725.0 4,332.8 10,914.1 15,246.8 725.0 4,289.9 10,783.3 15,073.3 100.0%
ATTACHMENT 2, Week 04
Summary for progress of RCC/ Drainage Holes at 28 - 01-2023
Design finished Quantity (%)
Block No. Hole (NO.) Inside Con- Depth Inside Con- Depth
(m) Hole (NO.) (m) Completed
Required crete (m) crete (m)
JOINT VENTURE
No. 6 Udi Street, Off Aso Drive, Maitama, Abuja
ATTACHMENT 3, Week 04
PHOTOGRAPHS
Fire-fighting system pipes installation at machine hall in progress. Anti-corosion of Spillway 1600kN Gantry Crane in progress.
Showing SCADA display of unit 1# during load increase test (From 0% to 100%) at During generator synchronization unit 1# with the grid at powerhouse central control
powerhouse central control room room.
COYNE ET BELLIER DE-CROWN (W.A.) CO. LTD.
Bureau d'Ingénieurs Conseils Consulting Engineers Ltd, Abuja - Nigeria
Date Range 22- 28 JAN, 2023 Week No.: 2023- 04 PC Date: 27-Sep-13
Weather: Sunning Precipitation Range: Temperature Range: 27 to 37
(Summary) (Summary) (Summary)
ATTACHMENT 3, Week 04
PHOTOGRAPHS
During Unit 1# heat running at rated power output. Showing unit 1-4# emergency accident stop botton at powerhouse central control room
During the inspection of the drainage ditch around Water treatment equipment room at the During the inspection of the of 37nos. of concrete cover plate around the diesel generator
downstream of block 47# room
During the inspection of the drainage ditch around Water treatment equipment room at the TRIPLE POINT SWITCHYARD: Cleaning of floor around septic tank/chamber at central
downstream of block 47# control building before landscaping.
COYNE ET BELLIER DE-CROWN (W.A.) CO. LTD.
Bureau d'Ingénieurs Conseils Consulting Engineers Ltd, Abuja - Nigeria
Date Range 22- 28 JAN, 2023 Week No.: 2023- 04 PC Date: 27-Sep-13
Weather: Sunning Precipitation Range: Temperature Range: 27 to 37
(Summary) (Summary) (Summary)
ATTACHMENT 3, Week 04
PHOTOGRAPHS