MI CORPORATION

Ishmam & Brothers, Sea Beach Road, Patenga, Chittagong.


Phone no.: 01309062296 Email: micorp@gmail.com
Director-CEO: Ishmam Shahriar

Estimate

Estimate For:
PORT HARBOR INTERNATIONAL Estimate No.: 0031
301-302, CENTRAL PLAZA (3RD FLOOR), GEC, Date: 25-08-2023
CHITTAGONG. Time: 06:34 PM
Contact No.: +88 01819 315860
# Item name Quantity CFT Price/ unit Amount
CAST-IN-SITU CONCRETE BORED
PILE
1 5596.6 Mtr ৳ 820.00 ৳ 45,89,212.00
(Rate = 820 Taka (Per Running
Meter))

Total 5596.6
45,89,212.00

www.vyaparapp.in
Estimate Amount In Words: Amounts:
Forty Five Lakh Eighty Nine Thousand Two Hundred and Sub Total ৳ 45,89,212.00
Twelve only
Total ৳ 45,89,212.00
Description:
CAST IN SITU CONCRETE BORED PILE-

QUOTATION FOR ZONE 1,2,3

Dia= 600mm

Rate= 820 Tk (Per Running Meter)

ZONE 1-
Max. Length= 28.350 Meter
Total Pile= 60 Nos
Total Lenghth for Zone-1 (60 Nos)= 1701 Meter

Costing For (Zone 1)-


(820 × 1701)= 13,94,820/= Taka

ZONE 2-
Max. Length= 24.050 Meter
Total Pile= 71 Nos
Total Lenghth for Zone-2 (71 Nos)= 1707.55 Meter

Costing For (Zone 2)-


(820 × 1707.55)= 14,00,191/= Taka

ZONE 3-
Max. Length= 25.150 Meter
Total Pile= 87 Nos
Total Lenghth for Zone-3 (87 Nos)= 2188.05 Meter

Costing For (Zone 3)-


(820 × 2188.05)= 17,94,201/= Taka

TOTAL = 218 Nos (Pile)


TOTAL LENGTH FOR 218 Nos = 5596.6 Meter
TOTAL COST FOR 5596.6 METER PILE= 45,89,212/=
Taka

In Words= Fourty Five Lakhs Eighty Nine Thousands Two


Hundred Twelve Taka.

Terms and conditions:

www.vyaparapp.in
1.All the materials to be supplied by your company for
piling are given below-
Rod, cement, sand, stone, electricity, water, security
system.

2.Accomodation & Toilet for labours should be provided


by Port Harbor International.

3.If piling is stopped due to any problem, you will have to


pay 8000 Taka per day for labor salary.

If any problem occurs underground during boring, you


will solve it at your own responsibility.

4.The work will be done by 4 machines.

5.Bill payment is requested after every 20%.

Thanks & Regards


MI CORPORATION

For, MI CORPORATION

DIRECTOR-CEO MI CORPORATION

www.vyaparapp.in