1st Edition –
Supplier Quality Assurance Manual
Content
Management Message......................................................................... 5
Introduction .................................................................................... 6
1. Purpose .................................................................................. 6
2. Scope of Application................................................................... 7
3. Responsibility........................................................................... 7
4. Organization ............................................................................ 7
5. Language ................................................................................ 7
6. Terms and abbreviations.............................................................. 8
7. Definitions .............................................................................. 9
8. Advanced Supplier Quality Assurance..............................................10
Requirements ................................................................................ 27
1. General Requirements ............................................................. 30
1.1. Supplier Facility access............................................................30
1.2. Project management ..............................................................30
1.3. Carry-over ...........................................................................30
1.4. Sub- suppliers’ components management and qualification.................31
1.5. Product/Process changes management .........................................31
1.6. Traceability .........................................................................33
1.7. Document and product sample retention.......................................34
1.8. Contingency plan ...................................................................34
1.9. Tools Property ......................................................................34
1.10. Government Regulatory Compliance .........................................34
2. Process Requirements ............................................................. 36
2.1. Process Equipments/Lay out .....................................................36
2.2. Product/Process FMEA & Control Plans .........................................36
2.3. Machinery / Equipment ...........................................................37
2.4. Test Equipments....................................................................37
2.5. Preventive Maintenance...........................................................38
2.6. Manufacturing Start-Up Instructions.............................................38
2.7. Employees Qualification...........................................................38
2.8. Process Audits ......................................................................39
2.9. Production Capacity ...............................................................41
2.10. Run@Rate .........................................................................41
3. Product Requirements ............................................................. 43
3.1. Prototypes...........................................................................43
3.2. Special Characteristics ............................................................43
3.3. Product Audits ......................................................................43
3.4. Annual Revalidation................................................................44
3.5. Aesthetic parts .....................................................................44
3.6. Reliability Tests ....................................................................45
4. Environmental Requirements..................................................... 47
4.1. Environment Protection ...........................................................47
4.2. Banned and Regulated Substances (BRS) .......................................47
4.3. Product End of Life ................................................................47
4.4. End-of-life Vehicle/International Material Data System......................48
5. Logistic Requirements ............................................................. 50
5.1. Packaging and Labeling............................................................50
5.2. Logistic Contract ...................................................................50
5.3. Transportation/Storage ...........................................................50
5.4. Delivery Documents................................................................51
5.5. Safety Stock.........................................................................51
5.6. Consignment / VMI Stock..........................................................51
5.7. Logistic Incident ....................................................................51
Management message
We at Automotive Lighting are committed to producing high quality, reliable, cost
effective products that provide customer value, are shipped on time, and
contribute to a better environment. Our Quality Management System achieves
these objectives and embraces the principles of continuous improvement.
We are dedicated to being quality and technology leader in the design and
manufacturing of head and rear automotive lighting systems. We can only achieve
this goal by expecting the best from our suppliers. Indeed, we believe a strong
supplier base will assist us in providing world class products to our customers.
The purpose of the Supplier Quality Manual is to define the requirements and
procedures for Quality Assurance measures.
It may be confidentially diffused to inform Automotive Lighting Suppliers of the
expectations we have regarding quality systems, manufacturing process controls
and design requirements for the purpose of doing business with us.
Automotive Lighting requires that suppliers establish, document and implement
effective management systems based on the minimum requirements identified
within this manual.
Gianpiero Poncino
Quality Vice President
Roberto Minella
Purchasing Vice President
Laurent Borch
Corporate SQA Manager
Introduction
1. Purpose
Supplier Quality Assurance is one of the pillars of Automotive Lighting Purchasing Policy.
The present SQA Manual serves to define the requirements and procedures for Quality
Assurance measures.
It defines and sets out the Advanced Supplier Quality Assurance Approach at suppliers’
facilities and in Automotive Lighting which are necessary to assure the Quality of
Purchased parts.
The fundamental responsibility for the Quality of purchased parts lies with the supplier.
Automotive Lighting Advanced SQA is designed to work jointly with its suppliers in order
to reach Automotive Lighting Customer’s Satisfaction by:
• Defining interaction rules and formalities between Automotive Lighting and its
suppliers to guarantee appropriate quality and reliability levels of the purchased
components.
• Defining steps and activities to validate the supplier processes and products.
• Defining Automotive Lighting requirements of purchased parts, production
processes and technical inspections.
• Assessing the quality capability and quality performance of its suppliers.
• Being part of the Automotive Lighting standard Requirements to aware the
suppliers on their responsibilities and duties.
By implementing Advanced SQA, Automotive Lighting Purchasing department aims to:
• Standardize the processes related to suppliers in Automotive Lighting plants.
• Continuously improve Supplier Quality Performance and reduce Non Quality costs.
• Secure SOP of new projects, new suppliers, tools & processes transfers, processes
& parts carry-overs.
• Continuously improve supplier’s production processes.
• Manage all processes and products modifications.
• Adopt a preventive mindset.
6/60
Supplier Quality Assurance Manual
2. Scope of Application
Automotive Lighting Advanced Supplier Quality Assurance applies for all external
purchased production suppliers and parts.
3. Responsibility
Each supplier is requested to meet the Automotive Lighting Advanced Supplier Quality
Assurance requirements. Non achievement of requirements may result in consequences
such as loss of existing/future businesses with Automotive Lighting.
For each business, suppliers and their sub-suppliers shall ensure that they comply with
the requirements of ISO TS/16949, and adopt Zero Defects and 100% on time delivery
approach.
As widely accepted, suppliers shall understand that established Quality targets are not
accepted quality levels.
The requirement to all Automotive Lighting suppliers is the Zero Defect and Zero Rework
mindset and approach in all products, processes and services.
4. Organization
In Automotive Lighting, Supplier Quality Assurance teams are reporting to Purchasing.
In a spirit of efficiency and optimization, 2 specific functions are defined for Automotive
Lighting plants Supplier Quality Assurance teams:
Necessary resources have to be defined taking into account number of suppliers, number
of new components in Projects and the full application of the rules defined in the
present Supplier Quality Assurance manual.
5. Language
Worldwide located company, Automotive Lighting Official Language is English.
Every established communication, documents, electronic Data,…between Automotive
Lighting and its suppliers will be in the Automotive Lighting concerned plant language or
in English.
For documents displaying English and native language in parallel, English is the unique
valid version.
AIAG: Automotive Industry Action Group PPAP: Production Part Approval Process
7. Definitions
Supplier: Rank 1 for AL
Designer: Responsible for the design and supply of a function defined by AL.
The integrated supplier-designer participates in the development
and definition of the function with AL
To achieve its supplier quality performance targets, Automotive Lighting divided its
Advanced Supplier Quality Assurance approach into three main phases:
1. Supplier Selection.
Each phase includes standard steps and activities involving different Automotive Lighting
departments:
1. Target
To support Automotive Lighting in reaching purchasing excellence, Automotive Lighting
Advanced Supplier Quality Assurance procedure targets to:
• Work with suppliers from Automotive Lighting Supplier Target Panel duly
evaluated.
• Identify and submit all requirements to Automotive Lighting suppliers.
• Award new businesses to suppliers able to fulfill Automotive Lighting
requirements.
Supplier Evaluation
R: Buyer
Check Certifications System Quality Certificates
NOK
OK
AL SRE v1
Perform Supplier Risk
R: Buyer
Evaluation AL SRE v1 fulfilled
OK NOK
PPA ANFIA
Perform Pre-Process Audit
R: SQA
S: Buyer ANFIA PPA ANFIA
NOK
OK
Supplier
Supplier pre-
not pre-
selected
selected
Integrate
supplier into
panel
2.3. Certifications
As quality products are a requirement to suppliers, an efficient Quality management
system is necessary to:
• Guarantee the reliability of tasks performed.
• Drive continuous improvement.
• Ensure the continuity of the company’s know-how.
It is based on:
• Clearly defining and expressing the quality policy.
• Assuring quality at all stages of product’s life.
• Working in a partnership and progress spirit with AL.
As first activity of Supplier Evaluation step, Automotive Lighting checks Quality
management system certification of supplier and its validity.
Automotive Lighting recognizes Quality management system certifications in accordance
with Automotive Standards and issued by accredited certification body:
• ISO 9001
• ISO TS/16949
Automotive Lighting aims to work with suppliers certified ISO TS/16 949.
Minimum required Certification is ISO 9001.
Class B 70% ≤ Overall score < 80% AND No chapter score < 50%
Out of pre-selection Overall score < 70% OR At least one chapter score < 50%
In case SRE status is “Out of pre-selection”, and Purchasing wish to develop business with a
supplier, an action plan shall be implemented by the supplier to correct all negative points.
After implementation of the action plan, Automotive Lighting shall evaluate improvement by
performing a new evaluation with SRE.
If Pre Process Audit status is Class C, and Purchasing wish to develop business with the
supplier, an action plan shall be implemented by the supplier to correct all negative points.
After implementation of the action plan, Automotive Lighting shall evaluate improvement by
performing a new Pre Process Audit.
The supplier shall be informed about the intended use of the part
Requirement File shall content:
• Drawings and BOM (Bill of materials).
• Specifications.
• List of Standards.
• Drawings of subcomponents (for assembled parts).
• Special characteristics.
• Project planning with key milestones.
• Design validation Plan.
• Quality targets.
• PPAP Level submission (standard: PPAP level 3).
• ISIR definition.
• IS requirements.
• Packaging requirements.
• Logistic requirements.
• Contingency plan
• …
R: Responsible
S: Support
Process Flow - Supplier Input
I: Information Selection/Nomination Output
R: Buyer • AL SEDS
R: Purchasing manager SEDS fulfillement
• AL SEDS fulfilled and signed
Offers comparison
R: Buyer
1. Target
Advanced SQA phase 2 aims to ensure that purchased parts and components are designed
and produced in compliance to Automotive Lighting quality, quantity, and on time delivery
expectations.
Process and Product Qualification phase consists in the processing of steps and activities, so
as to make sure purchased products are qualified before Automotive Lighting internal
Process Audit and Run at Rate on complete systems (Head Lamp, Rear Lamp, …)
Automotive Lighting systematically informs the supplier about PPAp submission status.
Submission status are as follows:
R: Responsible
Process Flow - Input
S: Support
I: Information
ISIR/PPAP/Samples Output
R: Supplier
Delivery ISIR/PPAP/Samples to • ISIR/PPAP/Samples
S: SDE/SQE/QM* SDE/SQE/QM*
• ISIR/PPAP/Samples conformity
R: SDE/SQE/QM* checking
• Complete Report analysis
• ISIR/PPAP/Samples dispatching to • ISIR/PPAP/Samples
required departments
1. Target
After SOP, supplier shall permanently measure its process/product performance, and
implement continuous improvement towards Zero Defect target.
2. Scope of application
Continuous performance Improvement phase applies for serial production parts after SOP.
Automotive Lighting may not perform Technical incoming inspection for products under Skip
lots status.
In case of any incidents, Skip lots status shall be removed and a new Special Monitoring
Period shall start.
Category Description
Automotive Lighting shall define Quality targets for here above items during step 2
Requirements Definition. See “Requirements” Section 6.1 “Quality Targets”.
Any incident during Serial production after SOP shall be immediately notified to the supplier
by an official Non Conformity report clearly indicating the incident category, the problem
description, the requested containment actions, and the request for definitive actions with
dead lines.
For any IC1 and/or Warranty claimed by Automotive Lighting customer, Automotive Lighting
plant shall notify supplier through an official letter, addressed to supplier management.
All non quality costs generated shall be invoiced to the supplier
See Requirement” section 6.6 “Non Conformity and incidents management”.
QCD Evaluation
Principles
Chapter
Score
Criteria Scoring Resp. Frequency Evaluation
Quality
PPM • Supplier in targets: Green: In targets
See Items definitions Purchasing Quaterly Evaluation
Incidents - Warranty 50 and rules hereunder • Supplier out of targets:
Yellow: Significant improvement but out of targets
SQA
Reactivity on Incidents Monthly Evaluation Red: No improvement and Out of targets
Trend: See Overall Evaluation
Cost
Cost Level/Productivity/ • Supplier in targets: Green: In targets
See Items definitions Quaterly Evaluation
Competitivness 30 and rules hereunder
Purchasing
• Supplier out of targets:
Yellow: Significant improvement but out of targets
Monthly Evaluation Red: No improvement and Out of targets
Trend: See Overall Evaluation
Delivery
On Time - Right Qty • Supplier in targets: Green: In targets
See Items definitions Quaterly Evaluation
20 and rules hereunder
Logistic
• Supplier out of targets:
Yellow: Significant improvement but out of targets
Logistic Incidents
Monthly Evaluation Red: No improvement and Out of targets
Trend: See Overall Evaluation
Overall Evaluation Rules
Overall Evaluation is on 100 points: Q+C+D = 50+30+20 = 100
If at least 1 of the Items Quality, Cost or Delivery = 0 => RED (ex: Quality = 0/40, Cost 0/30,…)
If at least 1 of the Item Quality, Cost or Delivery < 50% => YELLOW (ex: Quality = 10/40, Delivery = 5/20,…)
0 ≤ Overall Evaluation < 50 => RED (ex: Overall = 45/100) => C
50 ≤ Overall Evaluation < 70 => YELLOW (ex: Overall = 60/100) => B
70 ≤ Overall Evaluation < 80 => GREEN (ex: Overall = 78/100) => AB
80 ≤ Overall Evaluation => GREEN (ex: Overall = 85/100) => A
Trend: Based on last 3 months performance: Improving: Stable: Degradating:
Item Definitions and Rules
Max.
Item Item Scoring rules Definitions Basis
Score
Quality
In targets=Max. score
1 to 20% worse than targets= Half
PPM 20 PPM level = ( Nb of Defective Parts / Nb of Delivered Parts )* 10^6 Monthly
score More than 20% worse than
target=0
No Incidents=Max score
1 to 3 incidents over target=half
score Incidents are reported by category: Warranty, IC1, IC2, IC3
Incidents - Warranty 20 Monthly
More than 3 incidents over If at least 1 IC1 or Warranty => Score = 0
target=0
If at least 1 IC1 or Warranty=0
Delivery
Always on time/right
Qty=Max.score Often
On Time - Right Qty 10 Number of deliveries delivered on time and right Qty according to AL requirements Monthly
late/wrong qty=Half score
Always late/wrong qty=0
No incidents=Max.score
Logistics Incidents 10 1 incident=Half sco re Number of logistic Incidents (damaged delivery, additionnal special transports,…) Monthly
More than 1 incident=0
R: Inc. Insp.
S: SQE Non conformity report
I: Buyer • NC report
R: Inc. Insp.
Containment actions at AL
S: SQE • Good parts available < 4
facility
hours
R: Supplier
Containment actions at
S: SQE • Good parts delivery < 24
supplier's facility
hours
Definitive actions at
R: Supplier
supplier's facility
R: Supplier / SQE
Closure of incident
Supplier shall provide detailed action plan using adequate problem solving (Automotive
Lighting expects 8D) method in order to eradicate the problem.
Requirements
1. General Requirements ..............................................................30
1.1. Supplier Facility access ................................................ 30
1.2. Project management ................................................... 30
1.3. Carry-over................................................................ 30
1.4. Sub- suppliers’ components management and qualification...... 31
1.5. Product/Process changes management.............................. 31
1.6. Traceability .............................................................. 33
1.7. Document and product sample retention ........................... 34
1.8. Contingency plan........................................................ 34
1.9. Tools Property ........................................................... 34
1.10. Government Regulatory Compliance .............................. 34
2. Process Requirements ..............................................................36
2.1. Process Equipments/Lay out .......................................... 36
2.2. Product/Process FMEA & Control Plans .............................. 36
2.3. Machinery / Equipment ................................................ 37
2.4. Test Equipments ........................................................ 37
2.5. Preventive Maintenance ............................................... 38
2.6. Manufacturing Start-Up Instructions ................................. 38
2.7. Employees Qualification ............................................... 38
2.8. Process Audits ........................................................... 39
2.9. Production Capacity .................................................... 41
2.10. Run@Rate.............................................................. 41
3. Product Requirements ..............................................................43
3.1. Prototypes................................................................ 43
3.2. Critical Characteristics ................................................. 43
3.3. Product Audits........................................................... 43
3.4. Annual Revalidation .................................................... 44
3.5. Aesthetic parts .......................................................... 44
3.6. Reliability Tests ......................................................... 45
4. Environmental Requirements .....................................................47
4.1. Environment Protection................................................ 47
4.2. Banned and Regulated Substances (BRS) ............................ 47
4.3. Product End of Life ..................................................... 47
4.4. End-of-life Vehicle/International Material Data System .......... 48
5. Logistic Requirements ..............................................................50
5.1. Packaging and Labeling ................................................ 50
5.2. Logistic Contract ........................................................ 50
5.3. Transportation/Storage ................................................ 50
5.4. Delivery Documents..................................................... 51
5.5. Safety Stock.............................................................. 51
5.6. Consignment / VMI Stock .............................................. 51
5.7. Logistic Incident......................................................... 51
1. General Requirements
1. General Requirements
1.3. Carry-over
Carry-over parts shall go through Advanced SQA from step 2 “Requirements Definition” to
step 7 ISIR/PPAP.
As a strict minimum, supplier and Automotive Lighting shall check and state on following
hereunder points:
• Check Tools and Processes lifetime
• New Requirement File including specific customer requirements
• Check Production capacity including sub-supplied parts and raw materials
• Update Process FMEA and Control Plans
• New Process Audit and Run@Rate
• New full ISIR/PPAP
• Update Quality targets
• Update IMDS
Supplier shall insure that critical processes of purchased parts are audited and managed to
prevent Automotive Lighting from being impacted by quality, quantity, or on time delivery
issues.
When necessary, supplier shall make possible for Automotive Lighting to audit critical
processes of sub-suppliers to assure that proper controls are in place throughout the entire
supply chain.
Suppliers shall have a management system that:
• Tracks and reports quality and delivery performances of sub-suppliers.
• Enables solving of quality issues through documented corrective actions and
verification activities.
Supplier Product/Process
Change Request
Accepted Status:
Rejected
ISIR/PPAP/Samples
R: Supplier to Automotive
Lighting
R: SQE/SDE/QM*
ISIR/PPAP for • ISIR/PPAP/Samples
qualification
Rejected
Status:
Accepted
Supplier is not allowed to launch any product/process change before Automotive Lighting
prior analysis of the requested change and official Automotive Lighting agreement for launch.
Supplier is not allowed to deliver modified products/processes prior to Automotive Lighting
official approval through ISIR/PPAP.
For modifications on components delivered to several Automotive Lighting plants, supplier is
not allowed to deliver prior to receiving official approval through ISIR/PPAP from each plant.
Supplier is requested to inform plant Purchasing/Logistic Department for the date of first
modified parts delivery.
Delivery shall be marked with a specific marking in accordance to Automotive Lighting
concerned plant requirements.
2. Process Requirements
2. Process Requirements
2.10. Run@Rate
Run@Rate should take place during the Process Audit.
Quantities to be produced and production time for Run@Rate shall be representative of
serial conditions, and shall be defined according to part type and Automotive Lighting daily
quantity needs in serial.
As a minimum, unless otherwise agreed, Automotive Lighting standard requirements for
Run@Rate are:
• Production time: 2 to 4 hours without any stops
And/or
• Quantity: minimum 300 parts
• Maximum scrap level in the defined and agreed limits between Automotive Lighting
and supplier.
Quantities to be produced and production time for Run@Rate shall be defined in Automotive
Lighting Requirements File, and shall be reminded in Process Audit agenda sent to the
supplier.
Run@Rate report shall be issued by Automotive Lighting and signed by both AL and supplier.
3. Product Requirements
3.1. Prototypes........................................................................... 43
3.2. Special Characteristics ............................................................ 43
3.3. Product Audits...................................................................... 43
3.4. Annual Revalidation ............................................................... 44
3.5. Aesthetic parts ..................................................................... 44
3.6. Reliability Tests .................................................................... 45
3. Product Requirements
3.1. Prototypes
According to Automotive Lighting defined quantities and delivery times, supplier shall
provide the prototypes with an attached report of:
• Material certificates.
• Dimensional checks.
• Functional inspections.
Supplier shall identify each prototype delivery with a specific marking/ label.
4. Environmental Requirements
To ensure compliance with the various legal and customer requirements, AL suppliers
shall report information on materials within their respective components by updating
IMDS data base.
Supplier shall submit the required End-of-Life Vehicle/IMDS data to AL as soon as possible
upon award of new business.
Submission and conformity of required End-of-Life Vehicle /IMDS data is mandatory for
final ISIR/PPAP release.
The supplier must fulfil the prohibitions of the GADSL and declare substances according
the GADSL by sending an IMDS material data sheet with respect of the IMDS
recommendations of the IMDS Steering Committee published on the EDS internet pages.
5. Logistic Requirements
5. Logistic Requirements
5.3. Transportation/Storage
When supplier is in charge of transportation, supplier shall validate the transport
company:
• Transport FMEA is requested, results have to be available upon Automotive
Lighting request.
• Transportation shall be included in contingency plan.
Only required quantities shall be produced, and intermediate storage of products shall be
avoided.
Production and inspection status of parts shall be recognizable by appropriate
identification.
Storage and transportation shall be efficiently coordinated along the entire supply chain,
and shall not damage the products.
Category Target
IC1 X
Total IC1+IC2+IC3 Y
PPM Z
Category Definition
Warranty Claim from car maker out of field, detected on car sold to final user, due
to supplier part.
IC1 Claim from car maker, detected in car maker plant during pre-assembly,
assembly or final test, due to supplier part.
IC2 Claim from AL, detected in AL plant during pre-assembly, assembly or final
test, due to supplier part.
IC3 Claim from AL, detected in AL plant during Incoming Inspection, due to
supplier part.
X parts with different failure on each part Yes Nb=X Yes Nb=1 or
X, if X
customer
claims
IC1
Information from Supplier: delivery of non conform No. Except if part assembled Yes Nb=1
batch, already in use on AL production line in HL/RL, then Nb=X No Incident
IC2 / IC3
assembled. fees
Not conform raw materials (granulates, resins,…) No. Except Nb of Yes Nb=1
transformed/involved
parts/semi finished parts.
Parts sorted/reworked in AL plant by Supplier (good No. Except Nb bad Parts Yes Nb=1
reactivity from Supplier: gives in time agreement for detected on line or Inc. Insp.
sorting/rework by ext. company / send people for
IC2 / IC3
rework / …)
Line reject on critical parts (ECU, Bulbs, Harnesses,…) Yes Nb=X Yes Nb=1
with potential customer risk of IC1 or Warranty (No
possible detection on AL line)
Regular Line Rejects: ≥ 1% NC parts per shift * Yes Nb=X Yes Nb=1
Batch of suspected parts sent back to Supplier for No. Except real qty of def. Yes Nb=1
sorting parts, origin of the claim
AL Stock: Batch of suspected parts sent to external No. Except real qty of Yes Nb=1
sorting company managed by AL defective parts, origin of the
claim + Bad parts out of
Sorting operation
Dirty packaging (e.g: plastic boxes if supplier resp. for No Yes Nb=1
dpt)
cleaning)
Nb=Number
PROBLEM
DETECTION
& LESSON LEARN
FIRST LEVEL
ANALYSIS
PROBLEM CHECK OF
DESCRIPTION DEFINITIVE
ACTIONS
CORRECTIVE PREVENTIVE
PHASE PHASE
CONTAINEMENT DEFINITIVE
ACTIONS AT AL ACTIONS
CONTAINMENT
ROOTCAUSES
ACTIONS AT
ANALYSIS
SUPPLIER
The above costs come in addition of the direct costs due to the incident.
* Maximum applicable costs.
Automotive Lighting shall invoice each month to all suppliers all generated non quality
costs.
Accepted Status:
Rejected
R: Supplier Delivery to AL
In case Automotive Lighting approves the Special Release, each delivery must be marked
by the jointly defined marking by Automotive Lighting and supplier.