The document outlines a program for assembling and installing a lid applicator machine that can apply lids to 800g tomato paste cans at a rate of 120 cans per minute. It involves 4 parts: 1) mechanical assembly of components like the lid rack and conveyor over 7 days, 2) electrical assembly including sensor installation and control panel wiring over 7 days, 3) control algorithm development and testing over 7 days, and 4) machine delivery, installation, and fine tuning at the customer site over 9 days, for a total of 42 days.
The document outlines a program for assembling and installing a lid applicator machine that can apply lids to 800g tomato paste cans at a rate of 120 cans per minute. It involves 4 parts: 1) mechanical assembly of components like the lid rack and conveyor over 7 days, 2) electrical assembly including sensor installation and control panel wiring over 7 days, 3) control algorithm development and testing over 7 days, and 4) machine delivery, installation, and fine tuning at the customer site over 9 days, for a total of 42 days.
The document outlines a program for assembling and installing a lid applicator machine that can apply lids to 800g tomato paste cans at a rate of 120 cans per minute. It involves 4 parts: 1) mechanical assembly of components like the lid rack and conveyor over 7 days, 2) electrical assembly including sensor installation and control panel wiring over 7 days, 3) control algorithm development and testing over 7 days, and 4) machine delivery, installation, and fine tuning at the customer site over 9 days, for a total of 42 days.
TOMATO PASTE 800G 99 MM DIAMETER SPEED OF 120 CAN PER MIN TO
CONNECT TO PICK AND PLACE MACHINE NEW WITH DOUBLE HEAD Part 1 – Mechanical Assembly xxTask Days Status Remarks Plan a) Lid Rack Assembly 2 Done Complete b) Lid |Dropdown Assembly 2 Done Complete c) Lid Application Rollers Assembly 2 Done Complete d) Conveyor Assembly 2 Done Complete e) Lid Pickup Assembly 2 Done Complete f) Lid Gripper Assembly 2 Done Complete g) Machine Frame Assembly 2 Done Complete Part 2 – Electrical Assembly Task Days Status Remarks Plan h) Sensor installation and mounting fabrication 2 Done Complete i) Output components (e.g. solenoid valves 2 Ongoing Incomplete and gear motors) installation and mounting fabrication j) Control panel layout and control 2 components installation k) Wiring of control panel 3 l) Operator panel wiring and installation 3 Part 3 – Control Algorithm Development Task Days Status Remarks Plan m) Control program development, machine 7 testing and algorithm debugging Part 4 – Machine Fine Tuning n) Machine delivery and installation to 2 customer o) Machine fine tuning on actual run 7 Total # of Days 42 days / 7 working weeks