INSTALLATION OF 2TPH BOILER STATUS REPORT 19-Oct-23

LOCATION : RAS AL KHAIMA

PROJECT ACTIVITIES

FEEDWATER LINE
BALANCE /
ITEM MAJOR TASK DESCRIPTION STATUS REMARKS
PENDING
1 Piping Works
1.a Feedwater Tank
1.a.1 Temperature Gauges
1.a.2 Level Switch / Sight Glass Level Indicator
1.b Water Softener / Brine / Chemical Dosing Line
1.b.1 Dosing Pump
1.b.2 Chemical Tank/ Softener / Brine Tank
1.c Feedwater Pump
1.c.1 Fittings, Valves & Gauges
FUEL OIL LINE
BALANCE /
ITEM MAJOR TASK DESCRIPTION STATUS REMARKS
PENDING
2 Piping Works Finished
2.a HSD Tank Finished
2.a.1 Level Switch / Sight Glass Level Indicator Finished
2.a.2 Diesel Flowmeter Finished
2.b Diesel Filter, Fine Mesh Bucket Filter Finished
2.c Diesel Pump Finished
2.d Diesel Solenoid Valve Finished
2.e Return Line Finished
BURNER
BALANCE /
ITEM MAJOR TASK DESCRIPTION STATUS REMARKS
PENDING
3 Finished
3.a Diesel Pressure Indicator Line Finished
3.b Modulation Assembly Finished
3.c Sensors to Seq. Controller Finished
3.d Flame Sight Glass Finished
MAIN BOILER
BALANCE /
ITEM MAJOR TASK DESCRIPTION STATUS REMARKS
PENDING
4 Piping Works Finished
4.a Safety Relief Valve Finished
4.b Main Valve Finished
4.c Main Pressure Gauge Finished

Mobrey Water Level Controller Assembly with Water


4.d Finished
Gauge , Sight Glass and Modulating Pressure Switch

COMBUSTION BLOWER
BALANCE /
ITEM MAJOR TASK DESCRIPTION STATUS REMARKS
PENDING
5 Installation works Finished
STEAM LINE
BALANCE /
ITEM MAJOR TASK DESCRIPTION STATUS REMARKS
PENDING
6 Piping Works Finished
6.a NRV Finished
6.b Main Header Finished
6.b.1 Valves & Fittings Finished
6.b.2 Drain Line Finished
BLOWDOWN LINE
BALANCE /
ITEM MAJOR TASK DESCRIPTION STATUS REMARKS
PENDING
7 Piping Works Finished
7.a Auto Blowdown with Timer Valve Line Finished
7.b Manual Blowdown Valve Line Finished
FLUE / CHIMNEY
BALANCE /
ITEM MAJOR TASK DESCRIPTION STATUS REMARKS
PENDING
8 Installation works Finished
ELECTRICAL SUPPLY/ PANEL WORKS
BALANCE /
ITEM MAJOR TASK DESCRIPTION STATUS REMARKS
PENDING
9 Installation works Finished
9.a Connection from Feedwater Line Instruments Finished
9.b Connection from Main Boiler Instruments Finished
9.c Connection from Burner Instruments Finished
9.d Connection from Diesel Fuel Line Instruments Finished
STRUCTURAL WORKS
BALANCE /
ITEM MAJOR TASK DESCRIPTION STATUS REMARKS
PENDING
10 Boiler House Finished
10.a Platfrom works Finished