The true cost

of building a house
An honest guide to the cost of building your own
home on your own land

January 2020

@greencorehomes

www.greencoreconstruction.co.uk

E
TE
N
RA ice
A pr
U ld de
G i
u i
CE fl -b s gu
I e hi
PR
s
r t
ou in
ED er se
X v i
FI co o
is pr
m
D
How do you get value and cost
assurance when building a house?

By Ian Pritchett
Managing Director, Greencore Construction

I often get asked how much it really costs to in Oxfordshire, which is where we have most
build a house. experience and local knowledge.
It’s a difficult question to answer as every build Design
has its own requirements. However, there are
some common factors that will influence the cost The design of a house can have a big impact
of any project. on its cost. Ideally you should use an architect
This guide aims to give you honest advice on who has a track record of designing houses that
how to best approach these factors, how to get suit your budget. It is also important that the
maximum value at each stage of your project architect understands your ambition for thermal
and how to eliminate unexpected costs. performance and carbon footprint.
You should also employ a builder who can target
5 things to consider when costing cost certainty for your project. Many builders
your project under-quote at the beginning of a project, but
introduce costly alterations to the design later on.
The cost of building a house depends on a
We believe it is essential that the design is
number of factors, including:
controlled from the outset and developed in
• Location enough detail to provide a clear specification,
including the quality of kitchens and bathrooms.
• Design
At Greencore, when a clear specification
• Size has been agreed, we can offer a fixed price
• Procurement route and project management guarantee on most of our projects.
• Construction type and quality We make sure the design is right from the
start. This means that once the design is done
we can quote you an accurate price that won’t
change during the project, unless you change the
specification.
We strongly believe having the right design from
the beginning will save you money in the long
run.

Size
The cost of building a house is normally
measured in pounds per square metre of floor
area. The larger the floor area, the higher the
Location total cost.

Construction costs vary from one part of Construction costs can vary from £1,250 to
the country to another, with central London £3,500 per square metre. Most new self-build
obviously being the most expensive. The houses fall into the range of £1,750 to £2,750 per
information in this guide is based on the costs square metre.
Procurement route and We advise our clients to prioritise the fabric of the
building (external walls, windows and doors, roof,
project management
foundations and floor slab).
The way you decide to build your house will also These are the elements of the building that
have a big impact on the cost. At one end of the provide the structure, insulation and air-tightness.
spectrum you could decide to do all the work They are the parts of the building that are going
yourself and save the cost of using a builder. At to be there for the whole life of the building.
the other end of the spectrum you may decide to
Our unique building system has been developed
use a main contractor. This makes life very easy,
and refined over the past few years to give you
but has a higher cost.
the best balance between performance, speed of
There are also numerous intermediate routes with construction and cost.
different price points. In general, you should get
what you pay for, but we have all heard stories Typical prices
where this hasn’t happened.
The table on the back of this guide shows typical
Whichever route you choose, someone has to build costs for a high performance, comfortable
manage the project from the design right through and sustainable home built to premium quality
to the construction. The project management role by Greencore in the Oxfordshire area, based on
is critical to a successful project. January 2020 costs.
If you employ Greencore, we will ensure that your In addition to these costs you will need to allow
project is properly managed by one of our expert a further 10% of the construction costs to cover
team. We offer a simple, low-risk solution to your your architect, engineer and other miscellaneous
construction project. consultants that will be required.
Please note that in some places – such as at
Graven Hill near Bicester – you can buy your plot
with the foundations, services and substructure
already in place. This is called a ‘Golden Brick’
solution and the costs charged may vary from the
costs stated in this guide.

Unexpected costs
In addition to the costs shown in this guide,
further costs may occur due to abnormal
conditions on your site. These could be:
Construction type and quality • Sloping ground
• Poor ground conditions
The choices you make about the type of
construction – such as timber frame or masonry • Contamination
– can have an impact on the final cost and the • Remote location
speed of construction. However the difference in
cost is not as large as you might think. If you’re facing these sorts of challenges, seek
professional advice at an early stage.
Remember that your new house should last a very
long time. So it is sensible to build to a standard
that exceeds current regulations on thermal
performance and emissions. Retrofitting these
features in the future is always going to be more
Make your self-build dream a reality
expensive. We recommend building to Passivhaus
thermal performance from the outset.
Request a free consultation:
Building a house involves thousands of decisions
about design and specification. And each choice enquiries@greencoreconstruction.co.uk
has a cost impact. If you choose the most www.greencoreconstruction.co.uk
expensive in every category, you will end up with
an expensive house.
At Greencore we work with our clients to prioritise
where money is spent in order to deliver the
best value.
Typical Typical % of
Item 100m2 2-3 bed 150m2 3-4 bed 200m2 3-4 bed 250m2 5-6 bed
£/m2 total budget
Pre-construction
Site investigation, £125 6% £12,500 £18,750 £25,000 £31,250
demolition, site clearance,
new utilities
Substructure
Foundations, drains, £150 7% £15,000 £22,500 £30,000 £37,500
insulation and floor slab
Superstructure
External walls, internal
walls, upper floors, roof £550 25% £55,000 £82,500 £110,000 £137,500
structure, insulation and
airtightness
External finishes
Roof tiles, doors and £350 16% £35,000 £52,500 £70,000 £87,500
windows, wall cladding,
gutters
Services and fit-out
Plumbing, heating,
ventilation, electrics,
plastering, decorations, £600 27% £60,000 £90,000 £120,000 £150,000
kitchen, bathrooms,
ceramic tiles, floor
finishes, doors and stairs
External works
Patios, paths, driveway, £125 6% £12,500 £18,750 £25,000 £31,250
planting, turfing
Prelims
Site management, £210 9% £21,000 £31,500 £42,000 £52,500
welfare, health and safety,
scaffolding and fencing
Contingency £90 4% £9,000 £13,500 £18,000 £22,500
Total £2,200 100% £220,000 £330,000 £440,000 £550,000
Typical prices for a turnkey Greencore project in Oxfordshire (updated January 2020).
Contact us for a more detailed quote and details of our fixed price guarantee.