Block 4 Primavera Project Planner Project Start 02-01-2021

Report Date 10-08-2020 08:07 Project Finish 02-04-2023

SR-01 Classic Schedule Report - Sort by ES, TF

Activity ID Activity Name Original Remaining Units % Start Finish Late Start Late Finish Total Float
Duration Duration Complete

A1000 Cleaning & Leveling 3d 3d 0% 02-01-2021 04-01-2021 02-01-2021 04-01-2021 0d


A3850 In Direct Cost 697d 697d 0% 02-01-2021 02-04-2023 02-01-2021 02-04-2023 0d
A1010 Fixing the Fence 2d 2d 0% 05-01-2021 06-01-2021 05-01-2021 06-01-2021 0d
A1020 Supply & Erection of Site offices 2d 2d 0% 05-01-2021 06-01-2021 05-01-2021 06-01-2021 0d
A1510 Steel Fixing RC Piles 35d 35d 0% 09-01-2021 18-02-2021 09-01-2021 18-02-2021 0d
A1030 Placing RC Piles 21d 21d 0% 26-01-2021 18-02-2021 26-01-2021 18-02-2021 0d
A1410 Construct Bentonite Piles 11d 11d 0% 26-01-2021 07-02-2021 07-02-2021 18-02-2021 10d
A1040 Shuttering the Beams of the Piles 6d 6d 0% 20-02-2021 25-02-2021 20-02-2021 25-02-2021 0d
A1050 Steel Fixing the Beams of the Piles 5d 5d 0% 22-02-2021 27-02-2021 22-02-2021 27-02-2021 0d
A1060 Placing the Beams of the Piles 1d 1d 0% 28-02-2021 28-02-2021 28-02-2021 28-02-2021 0d
A1070 De shuttering the Beams of the Piles 1d 1d 0% 01-03-2021 01-03-2021 01-03-2021 01-03-2021 0d
A1080 Excavation 27d 27d 0% 02-03-2021 01-04-2021 02-03-2021 01-04-2021 0d
A1090 Structural Filling 3d 3d 0% 03-04-2021 05-04-2021 03-04-2021 05-04-2021 0d
A1110 Shuttering P.C Raft 3d 3d 0% 06-04-2021 08-04-2021 06-04-2021 08-04-2021 0d
A1120 Placing P.C Raft 1d 1d 0% 10-04-2021 10-04-2021 10-04-2021 10-04-2021 0d
A1130 De shuttering P.C Raft 3d 3d 0% 11-04-2021 13-04-2021 11-04-2021 13-04-2021 0d
A1140 Shuttering R.C Raft 5d 5d 0% 14-04-2021 19-04-2021 14-04-2021 19-04-2021 0d
A1530 Insulation Between P.C Raft and R.C Raft 15d 15d 0% 14-04-2021 01-05-2021 16-03-2023 02-04-2023 596d
A1150 Steel Fixing R.C Raft 28d 28d 0% 17-04-2021 18-05-2021 17-04-2021 18-05-2021 0d
A1160 Placing R.C Raft 3d 3d 0% 19-05-2021 22-05-2021 19-05-2021 22-05-2021 0d
A1170 De shuttering R.C Raft 4d 4d 0% 25-05-2021 29-05-2021 25-05-2021 29-05-2021 0d
A1180 Shuttering Basement -Floor R.C Columns & Walls 17d 17d 0% 30-05-2021 17-06-2021 30-05-2021 17-06-2021 0d
A1190 Steel Fixing Basement - Floor R.C Columns & Walls 11d 11d 0% 01-06-2021 13-06-2021 06-06-2021 17-06-2021 4d
A1200 Placing Basement - Floor R.C Columns & Walls 2d 2d 0% 19-06-2021 20-06-2021 19-06-2021 20-06-2021 0d
A1210 De shuttering Basement - Floor R.C Columns & Walls 1d 1d 0% 23-06-2021 23-06-2021 23-06-2021 23-06-2021 0d
A1220 Shuttering Basement- Floor R.C Slab & Beams 8d 8d 0% 24-06-2021 04-07-2021 24-06-2021 04-07-2021 0d
A1230 Steel Fixing Basement- Floor R.C Slab & Beams 13d 13d 0% 27-06-2021 12-07-2021 27-06-2021 12-07-2021 0d
A1240 Placing Basement- Floor R.C Slab & Beams 2d 2d 0% 13-07-2021 14-07-2021 13-07-2021 14-07-2021 0d
A1250 De shuttering Basement- Floor R.C Slab & Beams 3d 3d 0% 29-07-2021 01-08-2021 29-07-2021 01-08-2021 0d
A1570 Insulation For Columns and Walls 10d 10d 0% 02-08-2021 12-08-2021 02-08-2021 12-08-2021 0d
A1540 Shuttering P.c Floor For Basement 2d 2d 0% 02-08-2021 03-08-2021 06-09-2021 07-09-2021 30d
A1750 Placing P.c Floor For Basement 1d 1d 0% 04-08-2021 04-08-2021 30-03-2023 30-03-2023 513d
A1950 De shuttering P.c Floor For Basement 2d 2d 0% 05-08-2021 07-08-2021 01-04-2023 02-04-2023 513d
A1100 Back filling 6d 6d 0% 14-08-2021 19-08-2021 14-08-2021 19-08-2021 0d
A1330 Shuttering G-Floor R.C Columns & Walls 10d 10d 0% 21-08-2021 31-08-2021 21-08-2021 31-08-2021 0d
A1340 Steel Fixing G - Floor R.C Columns & Walls 8d 8d 0% 23-08-2021 31-08-2021 23-08-2021 31-08-2021 0d
A1350 Placing G- Floor R.C Columns & Walls 2d 2d 0% 01-09-2021 02-09-2021 01-09-2021 02-09-2021 0d
A1360 De shuttering G - Floor R.C Columns & Walls 2d 2d 0% 06-09-2021 07-09-2021 06-09-2021 07-09-2021 0d
A1370 Shuttering G- Floor R.C Slab & Beams 10d 10d 0% 08-09-2021 19-09-2021 08-09-2021 19-09-2021 0d
A1380 Steel Fixing G- Floor R.C Slab & Beams 13d 13d 0% 11-09-2021 25-09-2021 11-09-2021 25-09-2021 0d
A1390 Placing G Floor R.C Slab & Beams 2d 2d 0% 26-09-2021 27-09-2021 26-09-2021 27-09-2021 0d
A1580 Shuttering 1st-Floor R.C Columns & Walls 9d 9d 0% 30-09-2021 11-10-2021 30-09-2021 11-10-2021 0d
A1590 Steel Fixing 1st - Floor R.C Columns & Walls 6d 6d 0% 03-10-2021 10-10-2021 04-10-2021 11-10-2021 1d
A1600 Placing 1st- Floor R.C Columns & Walls 2d 2d 0% 12-10-2021 13-10-2021 12-10-2021 13-10-2021 0d
A1400 De shuttering G Floor R.C Slab & Beams 3d 3d 0% 13-10-2021 16-10-2021 16-10-2021 18-10-2021 2d
A1610 De shuttering 1st - Floor R.C Columns & Walls 2d 2d 0% 17-10-2021 18-10-2021 17-10-2021 18-10-2021 0d
A1620 Shuttering 1st- Floor R.C Slab & Beams 8d 8d 0% 19-10-2021 27-10-2021 19-10-2021 27-10-2021 0d
A1630 Steel Fixing 1st- Floor R.C Slab & Beams 12d 12d 0% 21-10-2021 03-11-2021 21-10-2021 03-11-2021 0d
A1640 Placing 1st- Floor R.C Slab & Beams 2d 2d 0% 04-11-2021 06-11-2021 04-11-2021 06-11-2021 0d
A1780 Shuttering 2nd-Floor R.C Columns & Walls 8d 8d 0% 09-11-2021 17-11-2021 09-11-2021 17-11-2021 0d
A1790 Steel Fixing 2nd - Floor R.C Columns & Walls 5d 5d 0% 11-11-2021 16-11-2021 13-11-2021 17-11-2021 1d
A1800 Placing 2nd- Floor R.C Columns & Walls 2d 2d 0% 18-11-2021 20-11-2021 18-11-2021 20-11-2021 0d
A1650 De shuttering 1st- Floor R.C Slab & Beams 3d 3d 0% 21-11-2021 23-11-2021 22-11-2021 24-11-2021 1d
A1810 De shuttering 2nd - Floor R.C Columns & Walls 2d 2d 0% 23-11-2021 24-11-2021 23-11-2021 24-11-2021 0d
A1820 Shuttering 2nd- Floor R.C Slab & Beams 8d 8d 0% 25-11-2021 04-12-2021 25-11-2021 04-12-2021 0d
A1830 Steel Fixing 2nd- Floor R.C Slab & Beams 12d 12d 0% 28-11-2021 11-12-2021 28-11-2021 11-12-2021 0d
A1840 Placing 2nd- Floor R.C Slab & Beams 2d 2d 0% 12-12-2021 13-12-2021 12-12-2021 13-12-2021 0d
A1980 Shuttering 3rd-Floor R.C Columns & Walls 8d 8d 0% 16-12-2021 25-12-2021 16-12-2021 25-12-2021 0d

Page 1 of 5
Block 4 Primavera Project Planner Project Start 02-01-2021
Report Date 10-08-2020 08:07 Project Finish 02-04-2023

SR-01 Classic Schedule Report - Sort by ES, TF

Activity ID Activity Name Original Remaining Units % Start Finish Late Start Late Finish Total Float
Duration Duration Complete

A1990 Steel Fixing 3rd - Floor R.C Columns & Walls 5d 5d 0% 19-12-2021 23-12-2021 20-12-2021 25-12-2021 1d
A2000 Placing 3rd- Floor R.C Columns & Walls 1d 1d 0% 26-12-2021 26-12-2021 26-12-2021 26-12-2021 0d
A1850 De shuttering 2nd-Floor R.C Slab & Beams 3d 3d 0% 28-12-2021 30-12-2021 28-12-2021 30-12-2021 0d
A2010 De shuttering 3rd- Floor R.C Columns & Walls 2d 2d 0% 29-12-2021 30-12-2021 29-12-2021 30-12-2021 0d
A2020 Shuttering 3rd- Floor R.C Slab & Beams 8d 8d 0% 01-01-2022 09-01-2022 01-01-2022 09-01-2022 0d
A2030 Steel Fixing 3rd- Floor R.C Slab & Beams 12d 12d 0% 03-01-2022 16-01-2022 03-01-2022 16-01-2022 0d
A2040 Placing 3rd- Floor R.C Slab & Beams 2d 2d 0% 17-01-2022 18-01-2022 17-01-2022 18-01-2022 0d
A2180 Shuttering 4th-Floor R.C Columns & Walls 8d 8d 0% 22-01-2022 31-01-2022 22-01-2022 31-01-2022 0d
A2190 Steel Fixing 4th - Floor R.C Columns & Walls 5d 5d 0% 24-01-2022 30-01-2022 26-01-2022 31-01-2022 1d
A2200 Placing 4th- Floor R.C Columns & Walls 2d 2d 0% 01-02-2022 02-02-2022 01-02-2022 02-02-2022 0d
A2050 De shuttering 3rd- Floor R.C Slab & Beams 3d 3d 0% 03-02-2022 06-02-2022 05-02-2022 07-02-2022 1d
A2210 De shuttering 4th - Floor R.C Columns & Walls 2d 2d 0% 06-02-2022 07-02-2022 06-02-2022 07-02-2022 0d
A2220 Shuttering 4th- Floor R.C Slab & Beams 8d 8d 0% 08-02-2022 16-02-2022 08-02-2022 16-02-2022 0d
A2230 Steel Fixing 4th- Floor R.C Slab & Beams 12d 12d 0% 10-02-2022 23-02-2022 10-02-2022 23-02-2022 0d
A2240 Placing 4th-Floor R.C Slab & Beams 2d 2d 0% 24-02-2022 26-02-2022 24-02-2022 26-02-2022 0d
A1260 Brick Works Basement- Floor 5d 5d 0% 27-02-2022 03-03-2022 05-03-2022 09-03-2022 5d
A2380 Shuttering 5th-Floor R.C Columns & Walls 8d 8d 0% 01-03-2022 09-03-2022 01-03-2022 09-03-2022 0d
A2390 Steel Fixing 5th - Floor R.C Columns & Walls 5d 5d 0% 03-03-2022 08-03-2022 05-03-2022 09-03-2022 1d
A1420 Brick Works G- Floor 31d 31d 0% 05-03-2022 09-04-2022 10-03-2022 14-04-2022 5d
A1270 Preliminary Carpentry Works Basement- Floor 2d 2d 0% 05-03-2022 06-03-2022 11-04-2022 12-04-2022 32d
A1280 Preliminary Electrical Works Basement- Floor 2d 2d 0% 05-03-2022 06-03-2022 11-04-2022 12-04-2022 32d
A1290 Plastering Basement- Floor 6d 6d 0% 07-03-2022 13-03-2022 13-04-2022 19-04-2022 32d
A2400 Placing 5th- Floor R.C Columns & Walls 2d 2d 0% 10-03-2022 12-03-2022 10-03-2022 12-03-2022 0d
A2250 De shuttering 4th- Floor R.C Slab & Beams 3d 3d 0% 13-03-2022 15-03-2022 14-03-2022 16-03-2022 1d
A1300 Painting Basement- Floor 1d 1d 0% 14-03-2022 14-03-2022 28-04-2022 28-04-2022 39d
A2410 De shuttering 5th - Floor R.C Columns & Walls 2d 2d 0% 15-03-2022 16-03-2022 15-03-2022 16-03-2022 0d
A2150 Flooring Basement- Floor 6d 6d 0% 15-03-2022 21-03-2022 30-04-2022 05-05-2022 39d
A2420 Shuttering 5th- Floor R.C Slab & Beams 8d 8d 0% 17-03-2022 26-03-2022 17-03-2022 26-03-2022 0d
A2430 Steel Fixing 5th- Floor R.C Slab & Beams 12d 12d 0% 20-03-2022 02-04-2022 20-03-2022 02-04-2022 0d
A1310 Finishing of Carpentry Works Basement- Floor 3d 3d 0% 22-03-2022 24-03-2022 14-06-2022 16-06-2022 72d
A1320 Finishing of Electrical Works Basement- Floor 2d 2d 0% 22-03-2022 23-03-2022 25-10-2022 26-10-2022 185d
A2350 Insulation For Basement Opening Floor 1d 1d 0% 22-03-2022 22-03-2022 09-11-2022 09-11-2022 197d
A1550 Insulation For Basement Floor 11d 11d 0% 24-03-2022 05-04-2022 27-10-2022 09-11-2022 185d
A2440 Placing 5th- Floor R.C Slab & Beams 2d 2d 0% 03-04-2022 04-04-2022 03-04-2022 04-04-2022 0d
A2580 Shuttering 6th-Floor R.C Columns & Walls 8d 8d 0% 07-04-2022 16-04-2022 07-04-2022 16-04-2022 0d
A2590 Steel Fixing 6th - Floor R.C Columns & Walls 5d 5d 0% 10-04-2022 14-04-2022 11-04-2022 16-04-2022 1d
A1660 Brick Works 1st- Floor 13d 13d 0% 10-04-2022 24-04-2022 16-04-2022 30-04-2022 5d
A1450 Preliminary Sanitary Works G- Floor 3d 3d 0% 10-04-2022 12-04-2022 17-04-2022 19-04-2022 6d
A1440 Preliminary Electrical Works G- Floor 2d 2d 0% 10-04-2022 11-04-2022 18-04-2022 19-04-2022 7d
A1430 Preliminary Carpentry Works G- Floor 1d 1d 0% 10-04-2022 10-04-2022 19-04-2022 19-04-2022 8d
A1460 Plastering G- Floor 11d 11d 0% 13-04-2022 25-04-2022 20-04-2022 02-05-2022 6d
A2600 Placing 6th- Floor R.C Columns & Walls 2d 2d 0% 17-04-2022 18-04-2022 17-04-2022 18-04-2022 0d
A2450 De shuttering 5th- Floor R.C Slab & Beams 3d 3d 0% 19-04-2022 21-04-2022 20-04-2022 23-04-2022 1d
A2610 De shuttering 6th - Floor R.C Columns & Walls 2d 2d 0% 21-04-2022 23-04-2022 21-04-2022 23-04-2022 0d
A2620 Shuttering 6th- Floor R.C Slab & Beams 8d 8d 0% 24-04-2022 02-05-2022 24-04-2022 02-05-2022 0d
A1670 Preliminary Carpentry Works 1st- Floor 16d 16d 0% 25-04-2022 12-05-2022 01-05-2022 18-05-2022 5d
A1860 Brick Works 2nd- Floor 13d 13d 0% 25-04-2022 09-05-2022 11-05-2022 25-05-2022 14d
A1690 Preliminary Sanitary Works 1st- Floor 3d 3d 0% 25-04-2022 27-04-2022 16-05-2022 18-05-2022 18d
A1680 Preliminary Electrical Works 1st- Floor 2d 2d 0% 25-04-2022 26-04-2022 17-05-2022 18-05-2022 19d
A2630 Steel Fixing 6th- Floor R.C Slab & Beams 12d 12d 0% 26-04-2022 09-05-2022 26-04-2022 09-05-2022 0d
A1470 Painting G- Floor 3d 3d 0% 26-04-2022 28-04-2022 03-05-2022 05-05-2022 6d
A1480 Flooring G- Floor 26d 26d 0% 30-04-2022 29-05-2022 07-05-2022 05-06-2022 6d
A2640 Placing 6th- Floor R.C Slab & Beams 2d 2d 0% 10-05-2022 11-05-2022 10-05-2022 11-05-2022 0d
A2060 Brick Works 3rd- Floor 13d 13d 0% 10-05-2022 24-05-2022 02-06-2022 16-06-2022 20d
A1890 Preliminary Sanitary Works 2nd- Floor 3d 3d 0% 10-05-2022 12-05-2022 11-06-2022 13-06-2022 27d
A1880 Preliminary Electrical Works 2nd- Floor 2d 2d 0% 10-05-2022 11-05-2022 12-06-2022 13-06-2022 28d
A1700 Plastering 1st- Floor 13d 13d 0% 14-05-2022 28-05-2022 19-05-2022 02-06-2022 5d
A1870 Preliminary Carpentry Works 2nd- Floor 16d 16d 0% 14-05-2022 31-05-2022 26-05-2022 13-06-2022 11d

Page 2 of 5
Block 4 Primavera Project Planner Project Start 02-01-2021
Report Date 10-08-2020 08:07 Project Finish 02-04-2023

SR-01 Classic Schedule Report - Sort by ES, TF

Activity ID Activity Name Original Remaining Units % Start Finish Late Start Late Finish Total Float
Duration Duration Complete

A2780 Shuttering 7th-Floor R.C Columns & Walls 8d 8d 0% 15-05-2022 23-05-2022 15-05-2022 23-05-2022 0d
A2790 Steel Fixing 7th - Floor R.C Columns & Walls 5d 5d 0% 17-05-2022 22-05-2022 18-05-2022 23-05-2022 1d
A2800 Placing 7th- Floor R.C Columns & Walls 1d 1d 0% 24-05-2022 24-05-2022 24-05-2022 24-05-2022 0d
A2260 Brick Works 4th- Floor 13d 13d 0% 25-05-2022 08-06-2022 21-06-2022 06-07-2022 23d
A2090 Preliminary Sanitary Works 3rd- Floor 3d 3d 0% 25-05-2022 28-05-2022 07-07-2022 10-07-2022 36d
A2080 Preliminary Electrical Works 3rd- Floor 2d 2d 0% 25-05-2022 26-05-2022 09-07-2022 10-07-2022 37d
A2650 De shuttering 6th- Floor R.C Slab & Beams 3d 3d 0% 26-05-2022 29-05-2022 26-05-2022 29-05-2022 0d
A2810 De shuttering 7th - Floor R.C Columns & Walls 2d 2d 0% 28-05-2022 29-05-2022 28-05-2022 29-05-2022 0d
A1710 Painting 1st- Floor 2d 2d 0% 29-05-2022 30-05-2022 04-06-2022 05-06-2022 5d
A2820 Shuttering 7th- Floor R.C Slab & Beams 8d 8d 0% 30-05-2022 07-06-2022 30-05-2022 07-06-2022 0d
A1490 Finishing of Carpentry Works G- Floor 2d 2d 0% 30-05-2022 31-05-2022 18-06-2022 19-06-2022 16d
A1500 Finishing of Electrical Works G- Floor 2d 2d 0% 30-05-2022 31-05-2022 07-11-2022 08-11-2022 136d
A1720 Flooring 1st- Floor 12d 12d 0% 31-05-2022 13-06-2022 06-06-2022 19-06-2022 5d
A2830 Steel Fixing 7th- Floor R.C Slab & Beams 12d 12d 0% 01-06-2022 14-06-2022 01-06-2022 14-06-2022 0d
A1900 Plastering 2nd- Floor 13d 13d 0% 01-06-2022 15-06-2022 14-06-2022 28-06-2022 11d
A2070 Preliminary Carpentry Works 3rd- Floor 16d 16d 0% 01-06-2022 19-06-2022 18-06-2022 06-07-2022 14d
A1560 Insulation G-floor Bath and Kitchen 1d 1d 0% 01-06-2022 01-06-2022 10-11-2022 10-11-2022 137d
A1520 Final Finishing G- Floor 2d 2d 0% 02-06-2022 04-06-2022 06-03-2023 07-03-2023 235d
A2460 Brick Works 5th- Floor 13d 13d 0% 09-06-2022 23-06-2022 11-07-2022 25-07-2022 26d
A2290 Preliminary Sanitary Works 4th- Floor 3d 3d 0% 09-06-2022 12-06-2022 02-08-2022 04-08-2022 45d
A2280 Preliminary Electrical Works 4th- Floor 2d 2d 0% 09-06-2022 11-06-2022 03-08-2022 04-08-2022 46d
A1730 Finishing of Carpentry Works 1st- Floor 22d 22d 0% 14-06-2022 10-07-2022 20-06-2022 16-07-2022 5d
A1740 Finishing of Electrical Works 1st- Floor 2d 2d 0% 14-06-2022 15-06-2022 09-11-2022 10-11-2022 125d
A2840 Placing 7th- Floor R.C Slab & Beams 2d 2d 0% 15-06-2022 16-06-2022 15-06-2022 16-06-2022 0d
A1910 Painting 2nd- Floor 2d 2d 0% 16-06-2022 18-06-2022 29-06-2022 02-07-2022 11d
A1770 Insulation 1st-floor Bath and Kitchen 2d 2d 0% 16-06-2022 18-06-2022 12-11-2022 13-11-2022 125d
A1920 Flooring 2nd- Floor 12d 12d 0% 19-06-2022 03-07-2022 03-07-2022 16-07-2022 11d
A2980 Shuttering 8th-Floor R.C Columns & Walls 8d 8d 0% 20-06-2022 28-06-2022 20-06-2022 28-06-2022 0d
A2270 Preliminary Carpentry Works 4th- Floor 16d 16d 0% 20-06-2022 09-07-2022 07-07-2022 25-07-2022 14d
A2100 Plastering 3rd- Floor 13d 13d 0% 20-06-2022 05-07-2022 11-07-2022 25-07-2022 17d
A2990 Steel Fixing 8th - Floor R.C Columns & Walls 5d 5d 0% 22-06-2022 27-06-2022 23-06-2022 28-06-2022 1d
A2660 Brick Works 6th- Floor 13d 13d 0% 25-06-2022 10-07-2022 30-07-2022 13-08-2022 29d
A2490 Preliminary Sanitary Works 5th- Floor 3d 3d 0% 25-06-2022 27-06-2022 28-08-2022 30-08-2022 54d
A2480 Preliminary Electrical Works 5th- Floor 2d 2d 0% 25-06-2022 26-06-2022 29-08-2022 30-08-2022 55d
A3000 Placing 8th- Floor R.C Columns & Walls 2d 2d 0% 29-06-2022 02-07-2022 29-06-2022 02-07-2022 0d
A2850 De shuttering 7th- Floor R.C Slab & Beams 3d 3d 0% 03-07-2022 05-07-2022 04-07-2022 06-07-2022 1d
A1940 Finishing of Electrical Works 2nd- Floor 2d 2d 0% 04-07-2022 05-07-2022 12-11-2022 13-11-2022 111d
A3010 De shuttering 8th - Floor R.C Columns & Walls 2d 2d 0% 05-07-2022 06-07-2022 05-07-2022 06-07-2022 0d
A2110 Painting 3rd- Floor 2d 2d 0% 06-07-2022 07-07-2022 26-07-2022 27-07-2022 17d
A1970 Insulation 2nd-floor Bath and Kitchen 2d 2d 0% 06-07-2022 07-07-2022 14-11-2022 15-11-2022 111d
A3020 Shuttering 8th- Floor R.C Slab & Beams 8d 8d 0% 07-07-2022 16-07-2022 07-07-2022 16-07-2022 0d
A2120 Flooring 3rd- Floor 12d 12d 0% 09-07-2022 21-07-2022 28-07-2022 10-08-2022 17d
A3030 Steel Fixing 8th- Floor R.C Slab & Beams 12d 12d 0% 10-07-2022 23-07-2022 10-07-2022 23-07-2022 0d
A2470 Preliminary Carpentry Works 5th- Floor 16d 16d 0% 10-07-2022 27-07-2022 26-07-2022 13-08-2022 14d
A2300 Plastering 4th- Floor 13d 13d 0% 10-07-2022 24-07-2022 06-08-2022 20-08-2022 23d
A1930 Finishing of Carpentry Works 2nd- Floor 22d 22d 0% 11-07-2022 04-08-2022 17-07-2022 10-08-2022 5d
A2860 Brick Works 7th- Floor 13d 13d 0% 11-07-2022 25-07-2022 17-08-2022 31-08-2022 32d
A2690 Preliminary Sanitary Works 6th- Floor 3d 3d 0% 11-07-2022 13-07-2022 22-09-2022 25-09-2022 63d
A2680 Preliminary Electrical Works 6th- Floor 2d 2d 0% 11-07-2022 12-07-2022 24-09-2022 25-09-2022 64d
A1760 Final Finishing 1st- Floor 2d 2d 0% 11-07-2022 12-07-2022 08-03-2023 09-03-2023 205d
A2140 Finishing of Electrical Works 3rd- Floor 2d 2d 0% 23-07-2022 24-07-2022 14-11-2022 15-11-2022 97d
A3040 Placing 8th- Floor R.C Slab & Beams 2d 2d 0% 24-07-2022 25-07-2022 24-07-2022 25-07-2022 0d
A2310 Painting 4th- Floor 2d 2d 0% 25-07-2022 26-07-2022 21-08-2022 22-08-2022 23d
A2170 Insulation 3rd-floor Bath and Kitchen 2d 2d 0% 25-07-2022 26-07-2022 16-11-2022 17-11-2022 97d
A3060 Brick Works 8th- Floor 13d 13d 0% 26-07-2022 09-08-2022 05-09-2022 19-09-2022 35d
A2890 Preliminary Sanitary Works 7th- Floor 3d 3d 0% 26-07-2022 28-07-2022 18-10-2022 20-10-2022 72d
A2880 Preliminary Electrical Works 7th- Floor 2d 2d 0% 26-07-2022 27-07-2022 19-10-2022 20-10-2022 73d
A2320 Flooring 4th- Floor 12d 12d 0% 27-07-2022 09-08-2022 23-08-2022 05-09-2022 23d

Page 3 of 5
Block 4 Primavera Project Planner Project Start 02-01-2021
Report Date 10-08-2020 08:07 Project Finish 02-04-2023

SR-01 Classic Schedule Report - Sort by ES, TF

Activity ID Activity Name Original Remaining Units % Start Finish Late Start Late Finish Total Float
Duration Duration Complete

A2370 Insulation 4th-floor Bath and Kitchen 2d 2d 0% 27-07-2022 28-07-2022 19-11-2022 20-11-2022 97d
A3180 Shuttering 9th-Floor R.C Columns & Walls 8d 8d 0% 28-07-2022 06-08-2022 28-07-2022 06-08-2022 0d
A2670 Preliminary Carpentry Works 6th- Floor 16d 16d 0% 28-07-2022 15-08-2022 14-08-2022 31-08-2022 14d
A2500 Plastering 5th- Floor 13d 13d 0% 28-07-2022 11-08-2022 31-08-2022 14-09-2022 29d
A2570 Insulation 5th-floor Bath and Kitchen 2d 2d 0% 30-07-2022 31-07-2022 21-11-2022 22-11-2022 97d
A3190 Steel Fixing 9th - Floor R.C Columns & Walls 5d 5d 0% 31-07-2022 04-08-2022 01-08-2022 06-08-2022 1d
A2130 Finishing of Carpentry Works 3rd- Floor 22d 22d 0% 06-08-2022 30-08-2022 11-08-2022 05-09-2022 5d
A1960 Final Finishing 2nd- Floor 2d 2d 0% 06-08-2022 07-08-2022 11-03-2023 12-03-2023 185d
A3200 Placing 9th- Floor R.C Columns & Walls 2d 2d 0% 07-08-2022 08-08-2022 07-08-2022 08-08-2022 0d
A3050 De shuttering 8th- Floor R.C Slab & Beams 3d 3d 0% 09-08-2022 11-08-2022 10-08-2022 13-08-2022 1d
A3260 Brick Works 9th- Floor 13d 13d 0% 10-08-2022 24-08-2022 24-09-2022 08-10-2022 38d
A3090 Preliminary Sanitary Works 8th- Floor 3d 3d 0% 10-08-2022 13-08-2022 14-11-2022 16-11-2022 81d
A3080 Preliminary Electrical Works 8th- Floor 2d 2d 0% 10-08-2022 11-08-2022 15-11-2022 16-11-2022 82d
A2340 Finishing of Electrical Works 4th- Floor 2d 2d 0% 10-08-2022 11-08-2022 13-03-2023 14-03-2023 183d
A3210 De shuttering 9th - Floor R.C Columns & Walls 2d 2d 0% 11-08-2022 13-08-2022 11-08-2022 13-08-2022 0d
A2510 Painting 5th- Floor 2d 2d 0% 13-08-2022 14-08-2022 15-09-2022 17-09-2022 29d
A3220 Shuttering 9th- Floor R.C Slab & Beams 8d 8d 0% 14-08-2022 22-08-2022 14-08-2022 22-08-2022 0d
A2520 Flooring 5th- Floor 12d 12d 0% 15-08-2022 28-08-2022 18-09-2022 01-10-2022 29d
A3230 Steel Fixing 9th- Floor R.C Slab & Beams 12d 12d 0% 16-08-2022 29-08-2022 16-08-2022 29-08-2022 0d
A2870 Preliminary Carpentry Works 7th- Floor 16d 16d 0% 16-08-2022 03-09-2022 01-09-2022 19-09-2022 14d
A2700 Plastering 6th- Floor 13d 13d 0% 16-08-2022 30-08-2022 26-09-2022 10-10-2022 35d
A2770 Insulation 6th-floor Bath and Kitchen 2d 2d 0% 16-08-2022 17-08-2022 23-11-2022 24-11-2022 84d
A3460 Brick Works 10th- Floor 13d 13d 0% 25-08-2022 08-09-2022 12-10-2022 26-10-2022 41d
A3290 Preliminary Sanitary Works 9th- Floor 3d 3d 0% 25-08-2022 28-08-2022 24-11-2022 27-11-2022 77d
A3280 Preliminary Electrical Works 9th- Floor 2d 2d 0% 25-08-2022 27-08-2022 28-11-2022 29-11-2022 80d
A2540 Finishing of Electrical Works 5th- Floor 2d 2d 0% 29-08-2022 30-08-2022 15-03-2023 16-03-2023 169d
A3240 Placing 9th- Floor R.C Slab & Beams 2d 2d 0% 30-08-2022 31-08-2022 30-08-2022 31-08-2022 0d
A2330 Finishing of Carpentry Works 4th- Floor 22d 22d 0% 31-08-2022 25-09-2022 06-09-2022 01-10-2022 5d
A2710 Painting 6th- Floor 2d 2d 0% 31-08-2022 01-09-2022 11-10-2022 12-10-2022 35d
A2160 Final Finishing 3rd- Floor 2d 2d 0% 31-08-2022 01-09-2022 13-03-2023 14-03-2023 165d
A2720 Flooring 6th- Floor 12d 12d 0% 03-09-2022 15-09-2022 13-10-2022 26-10-2022 35d
A3380 Shuttering 10th-Floor R.C Columns & Walls 7d 7d 0% 04-09-2022 11-09-2022 04-09-2022 11-09-2022 0d
A3070 Preliminary Carpentry Works 8th- Floor 16d 16d 0% 04-09-2022 21-09-2022 20-09-2022 08-10-2022 14d
A2900 Plastering 7th- Floor 13d 13d 0% 04-09-2022 18-09-2022 22-10-2022 06-11-2022 41d
A2970 Insulation 7th-floor Bath and Kitchen 2d 2d 0% 04-09-2022 05-09-2022 26-11-2022 27-11-2022 70d
A3390 Steel Fixing 10th - Floor R.C Columns & Walls 5d 5d 0% 06-09-2022 11-09-2022 06-09-2022 11-09-2022 0d
A3660 Brick Works 11th- Floor 13d 13d 0% 10-09-2022 24-09-2022 01-11-2022 15-11-2022 44d
A3490 Preliminary Sanitary Works 10th- Floor 3d 3d 0% 10-09-2022 12-09-2022 28-11-2022 30-11-2022 67d
A3480 Preliminary Electrical Works 10th- Floor 2d 2d 0% 10-09-2022 11-09-2022 30-11-2022 01-12-2022 69d
A3400 Placing 10th- Floor R.C Columns & Walls 2d 2d 0% 12-09-2022 13-09-2022 12-09-2022 13-09-2022 0d
A3250 De shuttering 9th- Floor R.C Slab & Beams 3d 3d 0% 15-09-2022 18-09-2022 15-09-2022 18-09-2022 0d
A3410 De shuttering 10th - Floor R.C Columns & Walls 2d 2d 0% 17-09-2022 18-09-2022 17-09-2022 18-09-2022 0d
A2740 Finishing of Electrical Works 6th- Floor 2d 2d 0% 17-09-2022 18-09-2022 18-03-2023 19-03-2023 155d
A3420 Shuttering 10th- Floor R.C Slab & Beams 8d 8d 0% 19-09-2022 27-09-2022 19-09-2022 27-09-2022 0d
A2910 Painting 7th- Floor 2d 2d 0% 19-09-2022 20-09-2022 07-11-2022 08-11-2022 41d
A3430 Steel Fixing 10th- Floor R.C Slab & Beams 12d 12d 0% 21-09-2022 04-10-2022 21-09-2022 04-10-2022 0d
A2920 Flooring 7th- Floor 12d 12d 0% 21-09-2022 04-10-2022 09-11-2022 22-11-2022 41d
A3270 Preliminary Carpentry Works 9th- Floor 16d 16d 0% 22-09-2022 10-10-2022 09-10-2022 26-10-2022 14d
A3100 Plastering 8th- Floor 13d 13d 0% 22-09-2022 06-10-2022 17-11-2022 01-12-2022 47d
A3170 Insulation 8th-floor Bath and Kitchen 2d 2d 0% 22-09-2022 24-09-2022 28-11-2022 29-11-2022 56d
A3690 Preliminary Sanitary Works 11th Floor 3d 3d 0% 25-09-2022 27-09-2022 01-12-2022 04-12-2022 57d
A3680 Preliminary Electrical Works 11th- Floor 2d 2d 0% 25-09-2022 26-09-2022 03-12-2022 04-12-2022 58d
A2530 Finishing of Carpentry Works 5th- Floor 22d 22d 0% 26-09-2022 20-10-2022 02-10-2022 26-10-2022 5d
A2360 Final Finishing 4th- Floor 2d 2d 0% 26-09-2022 27-09-2022 15-03-2023 16-03-2023 145d
A3440 Placing 10th- Floor R.C Slab & Beams 2d 2d 0% 05-10-2022 06-10-2022 05-10-2022 06-10-2022 0d
A2940 Finishing of Electrical Works 7th- Floor 2d 2d 0% 05-10-2022 06-10-2022 20-03-2023 21-03-2023 141d
A3110 Painting 8th- Floor 2d 2d 0% 08-10-2022 09-10-2022 03-12-2022 04-12-2022 47d
A3580 Shuttering 11th-Floor R.C Columns & Walls 7d 7d 0% 10-10-2022 17-10-2022 10-10-2022 17-10-2022 0d

Page 4 of 5
Block 4 Primavera Project Planner Project Start 02-01-2021
Report Date 10-08-2020 08:07 Project Finish 02-04-2023

SR-01 Classic Schedule Report - Sort by ES, TF

Activity ID Activity Name Original Remaining Units % Start Finish Late Start Late Finish Total Float
Duration Duration Complete

A3120 Flooring 8th- Floor 12d 12d 0% 10-10-2022 23-10-2022 05-12-2022 18-12-2022 47d
A3470 Preliminary Carpentry Works 10th- Floor 16d 16d 0% 11-10-2022 29-10-2022 27-10-2022 15-11-2022 14d
A3370 Insulation 9th-floor Bath and Kitchen 2d 2d 0% 11-10-2022 12-10-2022 30-11-2022 01-12-2022 42d
A3300 Plastering 9th- Floor 13d 13d 0% 11-10-2022 25-10-2022 13-12-2022 27-12-2022 53d
A3590 Steel Fixing 11th - Floor R.C Columns & Walls 5d 5d 0% 12-10-2022 17-10-2022 12-10-2022 17-10-2022 0d
A3600 Placing 11th- Floor R.C Columns & Walls 2d 2d 0% 20-10-2022 22-10-2022 20-10-2022 22-10-2022 0d
A3450 De shuttering 10th- Floor R.C Slab & Beams 3d 3d 0% 22-10-2022 24-10-2022 24-10-2022 26-10-2022 2d
A2730 Finishing of Carpentry Works 6th- Floor 22d 22d 0% 22-10-2022 16-11-2022 27-10-2022 22-11-2022 5d
A2560 Final Finishing 5th- Floor 2d 2d 0% 22-10-2022 23-10-2022 18-03-2023 19-03-2023 125d
A3140 Finishing of Electrical Works 8th- Floor 2d 2d 0% 24-10-2022 25-10-2022 22-03-2023 23-03-2023 127d
A3610 De shuttering 11th - Floor R.C Columns & Walls 2d 2d 0% 25-10-2022 26-10-2022 25-10-2022 26-10-2022 0d
A3310 Painting 9th- Floor 2d 2d 0% 26-10-2022 27-10-2022 28-12-2022 29-12-2022 53d
A3620 Shuttering 11th- Floor R.C Slab & Beams 8d 8d 0% 27-10-2022 06-11-2022 27-10-2022 06-11-2022 0d
A3320 Flooring 9th- Floor 12d 12d 0% 29-10-2022 12-11-2022 31-12-2022 12-01-2023 53d
A3630 Steel Fixing 11th- Floor R.C Slab & Beams 12d 12d 0% 31-10-2022 13-11-2022 31-10-2022 13-11-2022 0d
A3670 Preliminary Carpentry Works 11th- Floor 16d 16d 0% 31-10-2022 17-11-2022 16-11-2022 04-12-2022 14d
A3570 Insulation 10th-floor Bath and Kitchen 2d 2d 0% 31-10-2022 01-11-2022 03-12-2022 04-12-2022 28d
A3500 Plastering 10th- Floor 13d 13d 0% 31-10-2022 14-11-2022 08-01-2023 22-01-2023 59d
A3340 Finishing of Electrical Works 9th- Floor 2d 2d 0% 13-11-2022 14-11-2022 25-03-2023 26-03-2023 113d
A3640 Placing 11th- Floor R.C Slab & Beams 2d 2d 0% 14-11-2022 15-11-2022 14-11-2022 15-11-2022 0d
A3510 Painting 10th- Floor 2d 2d 0% 15-11-2022 16-11-2022 23-01-2023 24-01-2023 59d
A2930 Finishing of Carpentry Works 7th- Floor 22d 22d 0% 17-11-2022 12-12-2022 23-11-2022 18-12-2022 5d
A3520 Flooring 10th- Floor 12d 12d 0% 17-11-2022 30-11-2022 25-01-2023 07-02-2023 59d
A2760 Final Finishing 6th- Floor 2d 2d 0% 17-11-2022 19-11-2022 20-03-2023 21-03-2023 105d
A3770 Insulation 11th-floor Bath and Kitchen 2d 2d 0% 19-11-2022 20-11-2022 05-12-2022 06-12-2022 14d
A3700 Plastering 11th- Floor 13d 13d 0% 19-11-2022 03-12-2022 02-02-2023 16-02-2023 65d
A3650 De shuttering 11th- Floor R.C Slab & Beams 3d 3d 0% 30-11-2022 03-12-2022 30-11-2022 03-12-2022 0d
A3540 Finishing of Electrical Works 10th- Floor 2d 2d 0% 01-12-2022 03-12-2022 27-03-2023 28-03-2023 99d
A3790 Shuttering Inclined P.c For Roof 1d 1d 0% 04-12-2022 04-12-2022 04-12-2022 04-12-2022 0d
A3710 Painting 11th- Floor 2d 2d 0% 04-12-2022 05-12-2022 18-02-2023 19-02-2023 65d
A3820 Placing For Inclined P.c For Roof 1d 1d 0% 05-12-2022 05-12-2022 05-12-2022 05-12-2022 0d
A3830 Deshuttering For Inclined P.c For Roof 1d 1d 0% 06-12-2022 06-12-2022 06-12-2022 06-12-2022 0d
A3720 Flooring 11th- Floor 12d 12d 0% 06-12-2022 19-12-2022 20-02-2023 05-03-2023 65d
A3840 Insulation For Roof Floor 4d 4d 0% 07-12-2022 11-12-2022 07-12-2022 11-12-2022 0d
A3800 Thermal Insulation For Roof 33d 33d 0% 12-12-2022 18-01-2023 12-12-2022 18-01-2023 0d
A3130 Finishing of Carpentry Works 8th- Floor 22d 22d 0% 13-12-2022 07-01-2023 19-12-2022 12-01-2023 5d
A2960 Final Finishing 7th- Floor 2d 2d 0% 13-12-2022 14-12-2022 22-03-2023 23-03-2023 85d
A3740 Finishing of Electrical Works 11th- Floor 2d 2d 0% 20-12-2022 21-12-2022 29-03-2023 30-03-2023 85d
A3330 Finishing of Carpentry Works 9th- Floor 22d 22d 0% 08-01-2023 01-02-2023 14-01-2023 07-02-2023 5d
A3160 Final Finishing 8th- Floor 2d 2d 0% 08-01-2023 09-01-2023 25-03-2023 26-03-2023 65d
A3810 Flooring For Roof 23d 23d 0% 19-01-2023 14-02-2023 19-01-2023 14-02-2023 0d
A3530 Finishing of Carpentry Works 10th- Floor 22d 22d 0% 02-02-2023 27-02-2023 08-02-2023 05-03-2023 5d
A3360 Final Finishing 9th- Floor 2d 2d 0% 02-02-2023 04-02-2023 27-03-2023 28-03-2023 45d
A3780 Facing 40d 40d 0% 15-02-2023 02-04-2023 15-02-2023 02-04-2023 0d
A3730 Finishing of Carpentry Works 11th- Floor 22d 22d 0% 28-02-2023 25-03-2023 06-03-2023 30-03-2023 5d
A3560 Final Finishing 10th- Floor 2d 2d 0% 28-02-2023 01-03-2023 29-03-2023 30-03-2023 25d
A3760 Final Finishing 11th- Floor 2d 2d 0% 26-03-2023 27-03-2023 01-04-2023 02-04-2023 5d