July / 2022 〜 January / 2023

Extradosed Bridge Superstructure


Construction Works
§1 GENERAL VIEW OF EXTRADOSED BRIDGE

• ① Overall of Extradosed Bridge

§2 WHAT IS THE CANTILEVER WORKS?


• ① Overall of CanƟlever ConstrucƟon
• ② Pier Table Works
• ③ Form Traveller

§3. TECHNICAL FEATURE OF GYAING KAWKAREIK BRIDGE


• ① PT Works and CalculaƟon
• ② Corrugated Steel Plate Web (CSPW)
• ③Strut Structure
• ④ Pylon and Stay Cable
• ⑤ Closure Works

§4 Japanese Technologies for Superstructure


• ① Bearing
• ② Expansion Joint
• ③ Hand Rail
§3 TECHNICAL FEATURE OF
GYAING KAWKAREIK BRIDGE

① PT WORKS AND CALCULATION

Overall of Cantilever Construction


(1). PT CABLES

(A). SEPARATION BY TYPE OF PC TENDONS

Inner Cable ----- Construction Cable


----- Transverse Cable
----- Inner Cable
----- PT Bar
----- Inner Strut Cable

Outer Cable ----- Stay Cable (see another theme)


----- Span Cable (Not Applicable)
(1). CONSTRUCTION CABLE

(A). CABLE ARRANGEMENT


(B). PHOTO OF CONSTRUCTION CABLE
(PIER TABLE SECTION)
(C). SYSTEM

Detail of Construction Cable


Strand Type : SWPR7BL 12S15.2mm
(Diameter 15.2mm strand x 12nos strands)
Tensioning Method : Dywidag Post Tension Method (Bonded)
Duct Dimension and Material : Galvanized Steel Duct I.d 80mm / O.d.85mm
Design Section : Center of Pier Table Section
(D). THEORY & OBJECTIVES

Purpose of Construction Cable (PC Cable for Cantilever Construction)


In the Cantilever Construction Erection Method, the upper edge of the main girder on the piers is subject to a
significant bending moment (negative bending), and there is concern that the composite stress against tension in
the concrete may exceed the limit value.

The PC cables are used to applying pre-stressing force corresponding to the bending moment (negative bending)
that occurs at this point.
(E). CALCULATION (REQUIRE FORCE AND DESIGN SECTION)
(E). CALCULATION
(F). MANAGEMENT GRAPH

Japan Standard Management Method


: Friction – Pressure Control Method
(F). MANAGEMENT GRAPH(EXPLANATION)

Final Pressure
Decision Point
Friction Value
Reading Point

Upper Control Line


μ = 0.3+0.4 = 0.7

Ep Line Draw-in Adjust


line

Ep for finish
line

Reading Elongation

Lower Control Line


μ = 0.3-0.4 = -0.1
(2). TRANSVERSE CABLE

(A). CABLE ARRANGEMENT


(B). PHOTO OF TRANSVERSE CABLE
(BLOCK-8)
(C). SYSTEM

Detail of Transverse Cable


Strand Type : SWPR7BL 5F15.2mm
(Diameter 15.2mm strand x 5nos strands)
Duct Dimension and Material : Plastic Duct 90mm x 22mm
Tensioning Method : UPS Post Tension Method (Bonded)
Design Section : Outer Strut Connection Point / Above of Web
(D). THEORY & OBJECTIVES

Purpose of Construction Cable (PC Cable for Transverse Cable)


These PC cables are placed in the transverse direction of the floor slab.

The main purpose is to resist bending moments (negative bending) caused mainly by live loads (such as wheel
loads and sidewalk crowd loads) and bridge face construction loads acting on the slab.
(E). CALCULATION

Critical Section
(E). CALCULATION

Critical Section
Critical Section
(F). MANAGEMENT GRAPH

World Standard Management Method


: Elongation – Pressure Control Method
(F). MANAGEMENT GRAPH(EXPLANATION)

Elongation Line
Calculation
Pressure + 10% Line

Calculation
Point

Upper Control Line


Calculation Pressure + 10% Pressure Line

Calculation Elongation
+10% Point

Reading Elongation

Lower Control Line


Calculation Elongation +10%

World Standard Management Method


: Elongation – Pressure Control Method
(3). INNER CABLE

(A). CABLE ARRANGEMENT


(B). PHOTO OF INNER CABLE
(C). SYSTEM

Detail of Inner Cable


Strand Type : SWPR7BL 12S15.2mm(Side Span)
SWPR7BL 15S15.2mm(Center Span)
(Diameter 15.2mm strand x 12(5)nos strands)
Tensioning Method : Dywidag Post Tension Method (Bonded)
Duct Dimension and Material : Galvanized Steel Duct I.d 90mm / O.d.95mm
Design Section : Nearby Center of the Span
(D). THEORY & OBJECTIVES

Purpose of Construction Cable (PC Cable for Inner Cable)


PC cables are placed in the longitudinal direction of the bottom slab.
The main purpose of this cable is to resist the bending moment (positive bending) acting on the under slab by
tensioning this cable placed near the center of the span after the completion of the tension erection and the
construction of closed sections such as side span closure and center span closure.
(E). CALCULATION
(F). MANAGEMENT GRAPH
(4). PT BAR

(A). TENDON ARRANGEMENT


(B). PHOTO OF PT BARS
(C). SYSTEM

Detail of PT Bars

Symbol : SBPR 930/1180 φ36mm


Tensioning Method
: Dywidag Post Tension Method
Duct Dimension and Material
: Galvanized Steel Duct
I.d 45mm / O.d.48mm
(D). THEORY & OBJECTIVES
stay cable anchorage

PC
bars

If loading distanced points, One of the counters for this is


local tensile stress can be to add another compression
appeared in between. point in the middle.

PC
bars

Stay cable anchorage in girder side

Purpose of Construction Cable (PT Bars)


PT Bars are placed in the longitudinal direction of center web.
This bar is placed for counter to "LOCAL" stress condition by two distanced concentrated loading at the stay cable
anchorages.
(E). CALCULATION
(F). MANAGEMENT TABLE

World Standard Management Method


: Elongation – Pressure Control Method
(5). INNER STRUT CABLE

(A). TENDON ARRANGEMENT


(B). PHOTO OF INNER STRUT
(C). SYSTEM
Anchorage Zone Joint Area
Anchor Plate Air Vent Hole
Anchor Plate
Mansion SEEE Cable Coupler Mansion
Nut

Reinforcement Bar Nut


Reinforcement Bar

Mansion Anchor Plate (A4 Type)

Nut Coupler Reinforcement Bar

Detail of Inner Strut Cable

Symbol : SEEC F-Type 310(19xφ12.4), F230(19xφ10.8)


Tensioning Method : SEEC F-Type Post Tension Method
(D). THEORY & OBJECTIVES

inner strut

When resist the


torsion, tensile force
can act on the strut.
= "Needs of PC cable"

If no inner strut, box girder section By placing inner strut, box girder
can be skewed by eccentric load. section can be maintained even
against eccentric loading.

Purpose of Inner Strut Cable


Inner strut cables are placed along the inner strut set inside of the box girder section.
By prestressing the inner strut, it can resist the tensile force acting on the inner strut to maintain the box girder
section as box shape even under the eccentric loading condition.
(E). CALCULATION
(F). MANAGEMENT GRAPH
(2). REFERENCE
(DESIGN CONSIDERATION :REFERENCE FROM VSL SYSTEM MANUAL)
Thank you for listening!!