TE-419843 - Rev.A - MR For Chemical Injection Package
TE-419843 - Rev.A - MR For Chemical Injection Package
TE-419843 - Rev.A - MR For Chemical Injection Package
OPRNS
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
PMT
ENG’G CERT
MWK
SBK
JFGP 2
Jafurah Utilities, Sulfur and Interconnecting Systems
(Package 3)
DESCRIPTION
MATERIAL REQUISITION
JO/EWO
``
FOR
CHEMICAL INJECTION PACKAGE
2-MAR-22
DATE
REV. NO.
SBK
6000002309 CHEMICAL INJECTION NON-WELL HEAD TIE-INS
DATE 2-MAR-22_
ENGINEERING
MANAGER
JHK
DATE 2-MAR-22
REVIEWED BY PROCUREMENT QC SUPERVISOR Y.S. CHOI
CERTIFIED
CONSTRUCTION
REVIEWED BY PROJECT PROCUREMENT MANAGER K.H.LEE
AGENCY
________________
DATE ___________
OPERATIONS
________
DATE ___________
A 2-Mar-22 ISSUED FOR REVIEW S.B.KIM J.H.KWAK M.W.KIM
DATE _____________
CONTROL NUMBER
BY: ______________
(DCC)NO. _______________________________
REVISION CERTIFICATE
MATERIAL REQUISITION DWG.TYPE PLANT .NO INDEX DRAWING NO. SHT. NO. REV. NO.
MWK
A 2-MAR-22 10-14329-0003 ISSUED FOR REVIEW SBK MWK
JHK
OF THIS DRAWING IS COVERED, FOR ALL
SBK
APPROVAL/CERTIFICATION REQUIREMENTS, CONTROL NUMBER
AGENCY
________
DATE 2-MAR-22
MANAGER
ENGINEER
CERTIFIED
DISCIPLINE
DATE 2-MAR-22_
BY DRAWING COMPLETION CERTIFICATE BY: ______________
DATE 2-MARN-22
OPERATIONS
ENGINEERING
CONSTRUCTION
DATE ___________
DATE ___________
________________
(DCC)NO. _______________________________
DATE _____________
``
JAFUARAH
Saudi Aramco 2616-ENG (10/2002)
MATERIAL REQUISITION
SAUDI ARABIA
861
PLANT .NO
U
INDEX
2
SAUDI ARABIAN OIL COMPANY
JO / EWO: 10-14329-0003
DRAWING NO.
TE-419843
76
OF
SHT. NO.
A
SECTION 1. BIDDER’S LIST AND MR APPROVAL/COORDINATION
REV. NO.
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
Saudi Aramco 2616-ENG (10/2002)
OPRNS
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
PMT
ENG’G CERT
MWK
SECTION 2. INDEX
SBK
``
7.2 P&ID 16
SECTION 8. PROJECT SPECIFICATION 18
2-MAR-22
DATE
DISCIPLINE
ENGINEER SECTION 9. SA STANDARDS, SPECIFICATION & 175 FORM 21
SBK 9.1 SAUDI ARAMCO ENGINEERING STANDARDS 21
DATE 2-MAR-22_
ENGINEERING 9.2 SAUDI ARAMCO ENGINEERING PROCEDURES 23
MANAGER
JHK
9.3 SAUDI ARAMCO MATERIAL SYSTEM SPECIFICATIONS 24
DATE 2-MAR-22
CERTIFIED
9.4 SAUDI ARAMCO STANDARD DRAWINGS & LIBRARY DRAWINGS 26
MWK
9.5 SAUDI ARAMCO INSPECTION AND TESTING REQUIREMENTS 27
DATE 2-MARN-22
9.6 SAUDI ARAMCO NON MATERIAL REQUIREMENTS 28
CONSTRUCTION
AGENCY 9.7 SAUDI ARAMCO STANDARD FORMS 29
________________
SECTION 10. GENERAL REQUIREMENT 32
DATE ___________
BY: ______________
VERIFICATION
(DCC)NO. _______________________________
REVISION CERTIFICATE
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
PMT
MWK
10.1.10 MATERIALS 35
SBK
10.1.11 NAMEPLATES 36
10.1.12 NOISE CONTROL 36
10.1.13 SPECIAL TOOLS 36
10.1.14 CORROSION PROTECTIVE COATING AND PAINTING 37
10.1.15 PRESERVATION AND PROTECTION 37
DESCRIPTION
10.1.19 TRAINING 39
10.1.20 SUB-SUPPLIERS 39
10.1.21 GUARANTEES 40
10.1.22 DOCUMENTATION 40
JO/EWO
``
DISCIPLINE
ENGINEER 10.2.1 CHEMICAL INJECTION PUMP 43
SBK 10.2.2 STORAGE TANK 43
DATE 2-MAR-22_
ENGINEERING 10.2.3 PULSATION SUPPRESSION DEVICES 44
MANAGER
JHK
10.2.4 LUBRICATIONS 44
DATE 2-MAR-22
CERTIFIED
10.2.5 MATERIALS 44
MWK 10.2.6 ELECTRIC MOTORS 45
DATE 2-MARN-22
10.2.7 COUPLINGS AND COUPLING GUARDS 46
CONSTRUCTION
AGENCY 10.2.8 FOUNDATION AND STRUCTURE BASE FRAME 46
________________
DATE ___________
10.2.9 EARTHING BOSSES AND GROUNDING PADS 47
OPERATIONS 10.2.10 CONTROL AND INSTRUMENTATION 47
________
10.2.11 PRESSURE SAFETY VALVE 50
DATE ___________
BY: ______________
VERIFICATION
10.2.13 PIPING 50
EDSD
(DCC)NO. _______________________________
REVISION CERTIFICATE
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
PMT
MWK
``
2-MAR-22
DATE
REV. NO.
DISCIPLINE
ENGINEER
SBK
DATE 2-MAR-22_
ENGINEERING
MANAGER
JHK
DATE 2-MAR-22
CERTIFIED
MWK
DATE 2-MARN-22
CONSTRUCTION
AGENCY
________________
DATE ___________
OPERATIONS
________
DATE ___________
DATE _____________
CONTROL NUMBER
BY: ______________
VERIFICATION
EDSD
APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV. NO. _____A_____
(DCC)NO. _______________________________
REVISION CERTIFICATE
MATERIAL REQUISITION DWG.TYPE PLANT .NO INDEX DRAWING NO. SHT. NO. REV. NO.
MWK
A 2-MAR-22 10-14329-0003 ISSUED FOR REVIEW SBK MWK
JHK
OF THIS DRAWING IS COVERED, FOR ALL
SBK
APPROVAL/CERTIFICATION REQUIREMENTS, CONTROL NUMBER
AGENCY
________
DATE 2-MAR-22
MANAGER
ENGINEER
CERTIFIED
DISCIPLINE
DATE 2-MAR-22_
BY DRAWING COMPLETION CERTIFICATE BY: ______________
DATE 2-MARN-22
OPERATIONS
ENGINEERING
CONSTRUCTION
DATE ___________
DATE ___________
________________
(DCC)NO. _______________________________
DATE _____________
``
JAFUARAH
A
NO.
REV.
Saudi Aramco 2616-ENG (10/2002)
MATERIAL REQUISITION
2-MAR-22
REVISION
SECTION 3. REVISION HISTORY
SAUDI ARABIA
ISSUED FOR REVIEW
861
PLANT .NO
DESCRIPTION
U
INDEX
2
SAUDI ARABIAN OIL COMPANY
JO / EWO: 10-14329-0003
DRAWING NO.
TE-419843
76
OF
SHT. NO.
REMARK
A
REV. NO.
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
REVISION CERTIFICATE EDSD REV. NO. DATE JO/EWO DESCRIPTION ENG’G CERT PMT OPRNS
THIS INDICATES THAT REV. NO. _____A_____ VERIFICATION
MWK
A 2-MAR-22 10-14329-0003 ISSUED FOR REVIEW SBK MWK
JHK
OF THIS DRAWING IS COVERED, FOR ALL
SBK
APPROVAL/CERTIFICATION REQUIREMENTS, CONTROL NUMBER
AGENCY
________
DATE 2-MAR-22
MANAGER
ENGINEER
CERTIFIED
DISCIPLINE
DATE 2-MAR-22_
BY DRAWING COMPLETION CERTIFICATE BY: ______________
DATE 2-MARN-22
OPERATIONS
ENGINEERING
CONSTRUCTION
DATE ___________
DATE ___________
________________
(DCC)NO. _______________________________
DATE _____________
``
JAFUARAH
Saudi Aramco 2616-ENG (10/2002)
MATERIAL REQUISITION
SAUDI ARABIA
861
PLANT .NO
U
INDEX
SECTION 4. MR CHECK LIST (COMPANY ONLY)
2
SAUDI ARABIAN OIL COMPANY
JO / EWO: 10-14329-0003
DRAWING NO.
TE-419843
76
OF
SHT. NO.
A
REV. NO.
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
Saudi Aramco 2616-ENG (10/2002)
OPRNS
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
PMT
ENG’G CERT
MWK
5.1 SCOPE
All items not specifically mentioned in this specification, but necessary and required to
form an operational system as describe herein, shall be identified by SUPPLIER to
10-14329-0003 ISSUED FOR REVIEW
BUYER in his bid reply and upon approval shall be provided by SUPPLIER as a part of
the system.
Any errors or omissions in this specification shall not absolve SUPPLIER from the
responsibility of designing and providing complete and fully functional equipment as
described in this requisition.
JO/EWO
``
Errors or omissions noted during their initial bid review which impact on the scope of
supply, scope of work, scope of services, etc, should be urgently addressed to BUYER for
2-MAR-22
review, clarification and approval. These errors or omissions could be included in the
DATE
scope items.
A
DISCIPLINE
ENGINEER If the errors/omissions are noted by SUPPLIER during detail engineering process,
SBK SUPPLIER has obligation to resolve the errors/omissions without cost and delivery impact.
DATE 2-MAR-22_
ENGINEERING
MANAGER
The design/manufacturing of the equipment/materials shall be in accordance with all
specification, drawing, procedures, standards and other documents attached hereto and
JHK
with the best modern practice and shall be such to facilitate inspection, cleaning,
DATE 2-MAR-22
CERTIFIED
maintenance and repair to ensure satisfactory operation of the equipment/ materials under
all service conditions.
MWK
DATE 2-MARN-22
________________ This Material Requisition defines the functional and technical requirements for the material
DATE ___________ documentation design, fabrication, inspection, testing, painting, preparation for shipment
OPERATIONS and delivery of the GOODS and service listed below for installation of the JAFURAH
________ DEVELOPMENT PROGRAM, PACKAGE 2 AT JAFURAH, SAUDI ARABIA.
DATE ___________
For a list of definitions within this Material Requisition, refer to Section 10 - Appendix 1.
DATE _____________
CONTROL NUMBER
BY: ______________
VERIFICATION
The basic scope is listed below for Centrifugal Pump-VI (ASME-Vertical). For detailed
EDSD
(DCC)NO. _______________________________
REVISION CERTIFICATE
1 Produced Water
OF THIS DRAWING IS COVERED, FOR ALL
32-
Chemical Injection 175-
861-U-0403 1 6000002309 3 SAMSS-
Package Skids 324400
038
MATERIAL REQUISITION DWG.TYPE PLANT .NO INDEX DRAWING NO. SHT. NO. REV. NO.
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
PMT
MWK
Positive 31-
175-
Displacement Pumps 8 6000002361 0 SAMSS-
311500
009
DESCRIPTION
862-U-2301 175-
Package 1 6000002309 3 SAMSS-
324400
038
Positive 31-
175-
``
DISCIPLINE
3 Cooling Water
ENGINEER
System Chemical 32-
862-U-2302 175-
Injection Package 1 6000002309 3 SAMSS-
SBK 324400
DATE 2-MAR-22_ Skids 038
ENGINEERING
MANAGER
Chemical Storage 32-
175-
JHK
Tank 6 6000002479 3 SAMSS-
325100
DATE 2-MAR-22 030
CERTIFIED
Positive 31-
MWK 175-
Displacement Pumps 14 6000002361 0 SAMSS-
DATE 2-MARN-22 311500
009
CONSTRUCTION
AGENCY Electric Motor for 6000000994 17-
175-
________________ Pumps 14 1 SAMSS-
6000000995 170200
DATE ___________ 503
OPERATIONS 4 Hypochlorite Dosing 32-
862-U-2902 175-
________ Package 1 6000002309 3 SAMSS-
324400
DATE ___________ 038
DATE _____________
CONTROL NUMBER
32-
BY: ______________
325100
030
Positive 31-
175-
Displacement Pumps 2 6000002361 0 SAMSS-
311500
009
APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV. NO. _____A_____
(DCC)NO. _______________________________
REVISION CERTIFICATE
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
PMT
MWK
Positive 31-
175-
Displacement Pumps 3 6000002361 0 SAMSS-
311500
009
10-14329-0003 ISSUED FOR REVIEW
``
Positive 31-
175-
3 6000002361 0 SAMSS-
REV. NO.
009
DISCIPLINE
ENGINEER
Electric Motor for 6000000994 17-
175-
SBK Pumps 3 1 SAMSS-
6000000995 170200
DATE 2-MAR-22_ 503
ENGINEERING
MANAGER 7 869-U- Caustic Injection 32-
175-
1003/2003/3003 Package 3 6000002309 3 SAMSS-
JHK
324400
DATE 2-MAR-22
038
CERTIFIED
Chemical Storage 32-
175-
MWK
Tank 1 6000002479 3 SAMSS-
325100
DATE 2-MARN-22 030
CONSTRUCTION Positive 31-
AGENCY 175-
Displacement Pumps 2 6000002361 0 SAMSS-
________________ 311500
009
DATE ___________
BY: ______________
175-
VERIFICATION
038
(DCC)NO. _______________________________
31-
REVISION CERTIFICATE
Positive
OF THIS DRAWING IS COVERED, FOR ALL
175-
Displacement Pumps 2 6000002361 0 SAMSS-
311500
009
MATERIAL REQUISITION DWG.TYPE PLANT .NO INDEX DRAWING NO. SHT. NO. REV. NO.
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
PMT
MWK
Positive 31-
175-
Displacement Pumps 4 6000002361 0 SAMSS-
311500
009
175-
1010/2010/3010 Dosing Package 3 6000002309 3 SAMSS-
324400
038
2-MAR-22
DATE
030
A
DISCIPLINE
Positive 31-
ENGINEER
175-
Displacement Pumps 2 6000002361 0 SAMSS-
SBK 311500
009
DATE 2-MAR-22_
ENGINEERING
Electric Motor for 6000000994 17-
MANAGER 175-
Pumps 2 1 SAMSS-
6000000995 170200
JHK 503
DATE 2-MAR-22
CERTIFIED
BY: ______________
One lot
VERIFICATION
maintenance, if
EDSD
required
NOTE:
1. 9COM No.: “Material Number” on Regulated Vendor List. Source approved
APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV. NO. _____A_____
(DCC)NO. _______________________________
MATERIAL REQUISITION DWG.TYPE PLANT .NO INDEX DRAWING NO. SHT. NO. REV. NO.
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
PMT
2. The above information is preliminary for main component only, and the final sub-
ENG’G CERT
MWK
3. The listed Inspection Levels represent minimum requirements only, these inspection
levels can always be elevated to higher levels, based on COMPANY directions.
4. For detailed scope of supply, refer to Section 10 - Appendix 2.
Quality
Material
9COM MFR ID MFR Name Country Limitation
Description
(Note 8)
30000001 PROMINENT GMBH Germany
10-14329-0003 ISSUED FOR REVIEW
DATE 2-MARN-22
30004091 WEG EQUIPAMENTOS ELETRICOS S.A. Brazil
BY: ______________
(DCC)NO. _______________________________
REVISION CERTIFICATE
MATERIAL REQUISITION DWG.TYPE PLANT .NO INDEX DRAWING NO. SHT. NO. REV. NO.
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
PMT
Quality
Material
9COM MFR ID MFR Name Country Limitation
ENG’G CERT
MWK
Description
(Note 8)
30005856 ABB MOTORS AND MECHANICAL INC. USA
SBK
SBK
30000931 GULF SPECIALIZED WORKS FACTORY Saudi Arabia
DATE 2-MAR-22_ 30003100 KUWAIT PIPE INDUSTRIES AND OIL SERV Kuwait
ENGINEERING
MANAGER
30003749 ZAMIL PROCESS EQUIPMENT CO. LTD. Saudi Arabia
JHK
30004084 THE PETROLEUM PROJECTS AND TECHNICA Egypt
DATE 2-MAR-22
CERTIFIED 30004371 ROTARY ENGINEERING PTE LTD Singapore
TANK; SHOP
600000
MWK FABRICATED; 30004689 ABJ ENGNEERING AND CONTRACTING Kuwait
2479
DATE 2-MARN-22 32-SAMSS-030;
30005085 BEMCO STEEL INDUSTRIES CO. LTD. Saudi Arabia
CONSTRUCTION
AGENCY 30005436 GULF HEAVY INDUSTRIES COMPANY Saudi Arabia
________________
30005471 HESHAM HELAL AL SEWEDY AND PARTNERS Saudi Arabia
DATE ___________
30005513 AL-ZAMIL METAL WORKS FACTORY Saudi Arabia
OPERATIONS
DATE ___________
30006356 AL-ZAMIL COMPANY FOR HEAVY STEEL Saudi Arabia
DATE _____________
CONTROL NUMBER
BY: ______________
(DCC)NO. _______________________________
MATERIAL REQUISITION DWG.TYPE PLANT .NO INDEX DRAWING NO. SHT. NO. REV. NO.
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
PMT
Quality
Material
9COM MFR ID MFR Name Country Limitation
ENG’G CERT
MWK
Description
(Note 8)
30008496 INMA STEEL FABRICATORS CO. LTD. Saudi Arabia
SBK
SBK
DATE 2-MARN-22
SUPPLIER shall comply with the two attachments in Section 8.1, Sub-Vendor Listing &
CONSTRUCTION Manufacturing Method Statement, and submit these two attachments with his bid reply.
AGENCY
The attachments should include:
________________
DATE ___________
a) List the major sub-components (minimum 2nd/3rd level sub-components as
OPERATIONS
applicable) which are not specified in this MR. Indicate if the sub-components are RVL
________ managed, i.d. aligned with Inspectable 9COM material number (will be provided later) or
DATE ___________
not. Provide the applicable 9COM material number that applies, if applicable.
DATE _____________
CONTROL NUMBER
BY: ______________
SUPPLIERS are COMPANY approved or not, and provide the reference SUPPLIER ID
EDSD
number as applicable.
c) Complete the Manufacturing Methods Statement indicating the methodology for
manufacturing, inspection and testing, FAT, IFAT and shipment to site as clearly
APPROVAL/CERTIFICATION REQUIREMENTS,
(DCC)NO. _______________________________
REVISION CERTIFICATE
SUPPLIER is expected to comply with the submittal of these two attachments with his bid
reply, otherwise his bid shall be rendered incomplete and subject to rejection.
MATERIAL REQUISITION DWG.TYPE PLANT .NO INDEX DRAWING NO. SHT. NO. REV. NO.
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
PMT
MWK
8. Quality Limitation
(1) If “Yes”, SUPPLIER shall confirm quality limitation for each part.
SBK
(2) For induction motor, SUPPLIER shall confirm capacity limitation of each motor SUB-
SUPPLIER.
DESCRIPTION
``
2-MAR-22
DATE
REV. NO.
DISCIPLINE
ENGINEER
SBK
DATE 2-MAR-22_
ENGINEERING
MANAGER
JHK
DATE 2-MAR-22
CERTIFIED
MWK
DATE 2-MARN-22
CONSTRUCTION
AGENCY
________________
DATE ___________
OPERATIONS
________
DATE ___________
DATE _____________
CONTROL NUMBER
BY: ______________
VERIFICATION
EDSD
APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV. NO. _____A_____
(DCC)NO. _______________________________
REVISION CERTIFICATE
MATERIAL REQUISITION DWG.TYPE PLANT .NO INDEX DRAWING NO. SHT. NO. REV. NO.
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
PMT
ENG’G CERT
MWK
869-U-
``
869-U-
TE-419889 MDS - BFW Chemical Dosing Package B
A
1009/2009/3009
DISCIPLINE
ENGINEER
869-U- MDS - Ammonium Sulfate Dosing
TE-419890 B
SBK 1010/2010/3010 Package
DATE 2-MAR-22_
ENGINEERING
MANAGER
7.2 P&ID
JHK
DATE 2-MAR-22
CERTIFIED
Document No. Item No. Description Rev
MWK
DATE 2-MARN-22
TD-251001-001 P&ID - Piping Symbols & Legend E
CONSTRUCTION
AGENCY
TD-251002-001 P&ID - Equipment Symbols & Legend E
________________
P&ID - Instrument Symbols & Legend
DATE ___________ TD-251003-001 D
(1)
OPERATIONS
P&ID - Instrument Symbols & Legend
________ TD-251004-001 E
(2)
DATE ___________
TD-251005-001 D
CONTROL NUMBER
BY: ______________
(3)
VERIFICATION
EDSD
(DCC)NO. _______________________________
REVISION CERTIFICATE
MATERIAL REQUISITION DWG.TYPE PLANT .NO INDEX DRAWING NO. SHT. NO. REV. NO.
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
PMT
ENG’G CERT
MWK
``
2-MAR-22
DATE
REV. NO.
DISCIPLINE
ENGINEER
SBK
DATE 2-MAR-22_
ENGINEERING
MANAGER
JHK
DATE 2-MAR-22
CERTIFIED
MWK
DATE 2-MARN-22
CONSTRUCTION
AGENCY
________________
DATE ___________
OPERATIONS
________
DATE ___________
DATE _____________
CONTROL NUMBER
BY: ______________
VERIFICATION
EDSD
APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV. NO. _____A_____
(DCC)NO. _______________________________
REVISION CERTIFICATE
MATERIAL REQUISITION DWG.TYPE PLANT .NO INDEX DRAWING NO. SHT. NO. REV. NO.
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
PMT
ENG’G CERT
MWK
The documents listed below shall be formed as a part of this Material Requisition. Any
document and standard not listed below, but is referred in any of the following documents
shall be applicable to SUPPLIER and their scope of supply.
The latest edition of all the Codes and Standards stated in each specification and any
documents referred in this Requisition, including the following, shall be applied.
DESCRIPTION
``
TD-101101 C
DISCIPLINE VALVES
ENGINEER
DATE ___________
TYPICAL INSTRUMENTATION INSTALLATION
TD-671300-001 C
DETAILS
DATE _____________
CONTROL NUMBER
BY: ______________
VERIFICATION
EDSD
(DCC)NO. _______________________________
REVISION CERTIFICATE
MATERIAL REQUISITION DWG.TYPE PLANT .NO INDEX DRAWING NO. SHT. NO. REV. NO.
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
PMT
MWK
DISCIPLINE
ENGINEER
NEMA National Electrical Manufacturers Association
SBK
DATE 2-MAR-22_
ENGINEERING
MANAGER
IEC 60034 Rotating Electrical Machines
JHK
IEC 60079 Electrical Apparatus for Explosive Gas Atmospheres
DATE 2-MAR-22
CERTIFIED
ANSI/HI 14.6 Rotodynamic pumps for hydraulic performance acceptance test
MWK
DATE 2-MARN-22
ASME SA-388 Standard Practice for Ultrasonic Examination of Heavy Steel
CONSTRUCTION Forgings
AGENCY
ASME B16.5 Pipe Flanges and Flanged Fittings
________________
DATE ___________ STF05520 Details for Pipe Railing for Walking and Working Platforms
DATE _____________
BY: ______________
VERIFICATION
EDSD
(DCC)NO. _______________________________
REVISION CERTIFICATE
This equipment shall be in accordance with ASME Code and Stamped in accordance with
OF THIS DRAWING IS COVERED, FOR ALL
MATERIAL REQUISITION DWG.TYPE PLANT .NO INDEX DRAWING NO. SHT. NO. REV. NO.
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
PMT
In addition to the project specifications and documents listed in this Material Requisition, the
ENG’G CERT
MWK
Codes and Standards stated in each specification together with any documents referred to
therein shall apply.
SBK
If not stated, the latest edition of the above Standards and Codes at time of LOI shall govern.
DESCRIPTION
NOTES:
``
2-MAR-22
DATE
REV. NO.
DISCIPLINE
ENGINEER
SBK
DATE 2-MAR-22_
ENGINEERING
MANAGER
JHK
DATE 2-MAR-22
CERTIFIED
MWK
DATE 2-MARN-22
CONSTRUCTION
AGENCY
________________
DATE ___________
OPERATIONS
________
DATE ___________
DATE _____________
CONTROL NUMBER
BY: ______________
VERIFICATION
EDSD
APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV. NO. _____A_____
(DCC)NO. _______________________________
REVISION CERTIFICATE
MATERIAL REQUISITION DWG.TYPE PLANT .NO INDEX DRAWING NO. SHT. NO. REV. NO.
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
PMT
ENG’G CERT
MWK
For 9.1 through 9.7, “SAUDI ARAMCO Standard” If any other documents and
specifications to meet satisfactory design even not listed in this Material Requisition are
necessary, they shall be considered as a part of this Material Requisition. SUPPLIER shall
use “SAUDI ARAMCO Standard” In the Material Requisition only not latest specification.
There are useful index files that contains in each directory.
DESCRIPTION
``
DISCIPLINE
SAES-A-135 On Stream Inspection Requirements 20 Jun 2018
ENGINEER
SAES-A-202 Saudi Aramco Engineering Drawing Preparation 25 May 2014
SBK
DATE 2-MAR-22
SAES-B-054 Access, Egress, and Materials Handling for Plant 28 Mar 2017
CERTIFIED
Facilities
MWK
DATE 2-MARN-22 SAES-B-067 Safety Identification and Safety Colors 28 Jan 2020
CONSTRUCTION SAES-B-068 Electrical Area Classification 23 Nov 2017
AGENCY
________________
SAES-D-001 Design Criteria for Pressure Vessels 17 Aug 2020
DATE ___________
OPERATIONS
SAES-G-006 Positive Displacement Pumps – Controlled Volume 11 Feb 2011
________
SAES-H-001 Coating Selection and Application Requirements for 23 May 2019
DATE ___________
Industrial Plants and Equipment
DATE _____________
CONTROL NUMBER
BY: ______________
VERIFICATION
SAES-H-002 Internal and External Coatings for Steel Pipelines and 22 Feb 2018
EDSD
Piping
SAES-H-002V Approved Saudi Aramco Data Sheets for the 07 Feb 2017
Pipeline and Piping Coatings
APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV. NO. _____A_____
(DCC)NO. _______________________________
REVISION CERTIFICATE
MATERIAL REQUISITION DWG.TYPE PLANT .NO INDEX DRAWING NO. SHT. NO. REV. NO.
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
PMT
MWK
SBK
SAES-L-100 Applicable Codes and Standards for Pressure Piping 16 Feb 2017
A
DISCIPLINE
Systems
ENGINEER
SBK
SAES-L-105 Piping Line Class 29 Jan 2018
DATE 2-MAR-22_
ENGINEERING
MANAGER
SAES-L-108 Selection of Valves 1 Mar 2016
JHK
SAES-L-109 Selection of Flanges, Stud Bolts and Gaskets 29 Jan 2018
DATE 2-MAR-22
CERTIFIED
SAES-L-110 Limitations on Pipe Joints and Components 29 Feb 2018
MWK SAES-L-125 Safety Instruction Sheet for Piping and Pipelines 16 Feb 2017
DATE 2-MARN-22
CONSTRUCTION SAES-L-132 Materials Selection for Pipelines, Piping and Process 24 Aug 2016
AGENCY
Equipment
________________
DATE ___________ SAES-L-133 Corrosion Protection Requirements for Pipelines, 01 Jan 2018
OPERATIONS Piping, and Process Equipment
________
DATE ___________
SAES-L-136 Pipe, Flange, and Fitting Material Requirements 31 Dec 2016
DATE _____________
CONTROL NUMBER
BY: ______________
(DCC)NO. _______________________________
REVISION CERTIFICATE
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
PMT
MWK
SBK
DISCIPLINE
ENGINEER
SAEP-122 Project Records 24 Jan 2017
SBK SAEP-302 Instructions of Obtaining a Waiver of a Mandatory 20 Nov 2017
DATE 2-MAR-22_
ENGINEERING
MANAGER
Saudi Aramco Engineering Requirement
SAEP-302A Attachment A of SAEP-302 25 Aug 2016
JHK
MWK
SAEP-302C Mandatory and Recommended Standards 25 Aug 2016
DATE 2-MARN-22
SAEP-319 Pressure Relief Devices - Testing and Inspection 2 Jul 2017
CONSTRUCTION Requirements
AGENCY
________________
SAEP-325 Inspection Requirements for Pressure Equipment 20 Oct 2014
DATE ___________
OPERATIONS
SAEP-343 Risk-Based Inspection (RBI) for Saudi Aramco 24 Jan 2019
Facilities
________
DATE ___________
SAEP-351 Bolted Flange Joints Assembly 11 Jan 2017
DATE _____________
CONTROL NUMBER
BY: ______________
VERIFICATION
SAEP-415 Vibration Limits for Existing Rotating Machinery, Piping 07 Aug 2017
and Structures
APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV. NO. _____A_____
(DCC)NO. _______________________________
REVISION CERTIFICATE
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
PMT
MWK
``
SAEP-3101 Equipment and Spare Parts Data Requirements for 31 Mar 2014
DATE
DISCIPLINE
ENGINEER
SBK SAEP-3101B Appendix B - Spare Parts Data Package Status Report 24 Mar 2014
DATE 2-MAR-22_ (SPDPSR) Required Format
ENGINEERING
MANAGER
SAEP-3101C Appendix C - Instructions to Suppliers for Providing 24 Mar 2014
JHK Spare Parts and Operating Materials Data for New
DATE 2-MAR-22
Equipment Purchased
CERTIFIED
MWK
SAEP-3101D Appendix D - Spare Parts Data Package (SPDP) 24 Mar 2014
DATE 2-MARN-22 Checklists
CONSTRUCTION
AGENCY
________________
9.3 SAUDI ARAMCO MATERIAL SYSTEM SPECIFICATIONS
DATE ___________
DATE ___________
01-SAMSS-010 Fabricated steel Piping 09 Jul 2018
DATE _____________
CONTROL NUMBER
BY: ______________
VERIFICATION
(DCC)NO. _______________________________
REVISION CERTIFICATE
MATERIAL REQUISITION DWG.TYPE PLANT .NO INDEX DRAWING NO. SHT. NO. REV. NO.
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
PMT
MWK
SBK
``
DISCIPLINE
26-SAMSS-088 Turbine Oils 22 Nov 2017
ENGINEER
SBK
26-SAMSS-091 Grease 30 Nov 2017
DATE 2-MAR-22_
ENGINEERING
31-SAMSS-009 Positive Displacement Pumps – Controlled 14 Mar 2018
MANAGER Volume
JHK
DATE 2-MAR-22
32-SAMSS-002 Manufacture of Fibreglass-Reinforced Plastic 25 Dec 2016
CERTIFIED (FRP) Storage Tanks
MWK 32-SAMSS-030 Manufacture of Small Metallic Atmospheric 09 Oct 2018
DATE 2-MARN-22
Storage Tanks
CONSTRUCTION
AGENCY 32-SAMSS-038 Shop Fabricated Skid-Mounted Units 16 Jan 2019
________________
DATE ___________
34-SAMSS-010 Quality Requirements for Pressure Retaining 01 Jan 2018
Instruments
OPERATIONS
BY: ______________
VERIFICATION
Cable
APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV. NO. _____A_____
(DCC)NO. _______________________________
MATERIAL REQUISITION DWG.TYPE PLANT .NO INDEX DRAWING NO. SHT. NO. REV. NO.
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
PMT
MWK
Qualifications
Local Instruments Symbols (Pneumatic &
AB-036492-001 07
2-MAR-22
DATE
AB-036492-002 05
A
BY: ______________
connections
VERIFICATION
EDSD
(DCC)NO. _______________________________
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
PMT
MWK
DB-950048-001 01
Level Instrument (up to Class 600 ANSI Rating)
Pressure Indicators and Switches Locally
DC-950040-001 01
Mounting Instrument Piping Details
Pressure Indicators and Switches Panel or Wall
DC-950041-001 01
Mounted Instrument Piping Details
Instruments Piping Details Pressure
DC-950042-001 01
DESCRIPTION
DD-950022-012 00
Grid
DD-950025-001 Nameplate Details For Instrument Boards 00
DD-950053-001 Field Mounting Details For Instruments 00
JO/EWO
9.5
``
Requirements
DISCIPLINE
ENGINEER
175-010800 PIPE : Beveled End, Seamless or Welded, Straight 22 Dec 2015
SBK
Seam, Stainless Steel Pipe
DATE 2-MAR-22_
ENGINEERING 175-013100 PIPE: Fabrication of Spools; Carbon, Alloy, High 12 Jul 2017
MANAGER
Strength Special, Low and High Temperature Steels
JHK
DATE 2-MAR-22 175-019800 PIPING AUXILIARY – For Mechanical Equipment 01 Nov 2016
CERTIFIED (NOTE 1)
MWK 175-022500 Spectacle Plates, Spacers, Blanks 03 Nov 2015
DATE 2-MARN-22
CONSTRUCTION
AGENCY
175-022501 Flanges : Weldneck, Blind Flanges; Forged Steel & 12 Jul 2017
________________ Alloy
DATE ___________
175-043000 Valve Material Certification Requirements Dec 2016
OPERATIONS
________
DATE ___________
175-043600 Valves: Metallic; Includes gate, globe, angle, check, 12 Jul 2017
needle, ball, plug, piston, and butterfly
DATE _____________
CONTROL NUMBER
BY: ______________
VERIFICATION
(DCC)NO. _______________________________
REVISION CERTIFICATE
MATERIAL REQUISITION DWG.TYPE PLANT .NO INDEX DRAWING NO. SHT. NO. REV. NO.
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
PMT
MWK
``
SBK 175-340100 VALVES: Control, Steel, General Service, Pneumatic 16 Nov 2015
DATE 2-MAR-22_ Operated, Up to and Including Class 2500 Ratings
ENGINEERING
MANAGER
175-340200 Instrumentation for Packaged Units 19 Jan 2017
JHK
DATE 2-MAR-22
CERTIFIED 175-341700 Pressure Retaining Instruments 12 Mar 2017
MWK
DATE 2-MARN-22 175-341900 VALVE: Safety Relief Conventional and Balanced 26 Jun 2016
CONSTRUCTION
Type
AGENCY
________________
DATE ___________
DATE ___________
DATE _____________
CONTROL NUMBER
BY: ______________
VERIFICATION
(DCC)NO. _______________________________
REVISION CERTIFICATE
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
PMT
MWK
01 Aug 2006
Machinery
SBK
``
SBK 17-SAMSS-502
DATE 2-MAR-22_
ENGINEERING
SA-2693 Safety Instruction Sheet - Tanks 01 Nov 2010
MANAGER
DATE 2-MAR-22
SA-2773 Instrument Specification Sheet - Pressure 01 Nov 2010
CERTIFIED
Instruments
MWK
DATE 2-MARN-22
SA-2787 Instrument Specification Sheet - Pressure 01 Nov 2010
CONSTRUCTION
Regulators
AGENCY
DATE ___________
BY: ______________
VERIFICATION
EDSD
(DCC)NO. _______________________________
REVISION CERTIFICATE
MATERIAL REQUISITION DWG.TYPE PLANT .NO INDEX DRAWING NO. SHT. NO. REV. NO.
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
PMT
MWK
SBK
Specification
SA-8020-200 Pressure Transmitter - Smart 01 Nov 2010
DISCIPLINE
ENGINEER
SA-8020-415 Thermocouple assembly instrument 01 Nov 2010
SBK specification sheet
DATE 2-MAR-22_
ENGINEERING SA-8020-416 Resistance Temperature Detectors 01 Nov 2010
MANAGER
JHK
DATE 2-MAR-22
SA-8020-418 Thermowells 01 Nov 2010
CERTIFIED
________
BY: ______________
VERIFICATION
(DCC)NO. _______________________________
MATERIAL REQUISITION DWG.TYPE PLANT .NO INDEX DRAWING NO. SHT. NO. REV. NO.
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
PMT
MWK
SBK
-
SDS-EE-17502 Motor datasheet format
DESCRIPTION
``
2-MAR-22
DATE
REV. NO.
DISCIPLINE
ENGINEER
SBK
DATE 2-MAR-22_
ENGINEERING
MANAGER
JHK
DATE 2-MAR-22
CERTIFIED
MWK
DATE 2-MARN-22
CONSTRUCTION
AGENCY
________________
DATE ___________
OPERATIONS
________
DATE ___________
DATE _____________
CONTROL NUMBER
BY: ______________
VERIFICATION
EDSD
APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV. NO. _____A_____
(DCC)NO. _______________________________
REVISION CERTIFICATE
MATERIAL REQUISITION DWG.TYPE PLANT .NO INDEX DRAWING NO. SHT. NO. REV. NO.
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
PMT
ENG’G CERT
MWK
10.1.1 GENERAL
DISCIPLINE
ENGINEER
BUYER/COMPANY are under no obligation to consider, accept or find any
SBK
deviations from the specified requirements. No deviation is accepted except for
DATE 2-MAR-22_
ENGINEERING
those listed on the DEVIATION / CLARIFICATION LIST in Appendix 3 subjected to
MANAGER BUYER / COMPANY’s prior approval.
JHK
DATE 2-MAR-22 Alternatives may be offered for materials and fabrication, if technically or
CERTIFIED
economically justified and provided they meet the requirements of the applicable
MWK codes and standards and have obtained prior written approval from BUYER.
DATE 2-MARN-22 However, SUPPLIER shall provide his bid proposal on the MR scope of supply and
then submit any alternate proposal accordingly.
CONSTRUCTION
AGENCY
________
If any inconsistency or conflict exists between this Material Requisition and other
DATE ___________ BUYER/COMPANY’s documents, Industry Standards, Codes or Drawings, it shall
be the responsibility of SUPPLIER to bring it to the attention of BUYER in writing,
DATE _____________
CONTROL NUMBER
BY: ______________
BUYER along with COMPANY shall resolve the inconsistency or the conflict.
Conflicts with Reference Standards, Specifications, Drawings, Forms and Codes
listed in Section 8 and 9 shall not be permitted unless accompanied by
BUYER/COMPANY pre-agreed written waiver and/or confirmation.
APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV. NO. _____A_____
(DCC)NO. _______________________________
REVISION CERTIFICATE
MATERIAL REQUISITION DWG.TYPE PLANT .NO INDEX DRAWING NO. SHT. NO. REV. NO.
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
PMT
This Material Requisition in no way releases SUPPLIER from the final guarantees
ENG’G CERT
MWK
In case of conflict among any referenced codes and standards or between any
referenced codes and standards and technical specifications, BUYER will
DESCRIPTION
DISCIPLINE
ENGINEER 10.1.3 SITE CONDITION
SBK
DATE 2-MAR-22_ Refer to Basic Engineering Design Data “861-A-TD-821950 (BEDD) & SAES-A-
ENGINEERING
MANAGER
112”.
JHK SUPPLIER shall ensure that all equipment/materials within his scope of supply are
DATE 2-MAR-22 suitable for installation and operation under the site ambient conditions.
CERTIFIED
Equipment components shall have dimensional tolerances such that it can be
MWK
replaced by spare parts without modifying them.
DATE 2-MARN-22
CONSTRUCTION
AGENCY
Wind Data
________________
BY: ______________
VERIFICATION
EDSD
Earthquake Data :
- Earthquake Code : ASCE 7-05
- Short Period Acceleration (Ss) in %g : 16.0%
APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV. NO. _____A_____
(DCC)NO. _______________________________
MATERIAL REQUISITION DWG.TYPE PLANT .NO INDEX DRAWING NO. SHT. NO. REV. NO.
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
PMT
- Site Class : D
ENG’G CERT
MWK
``
Note 2 : For air cooled heat exchangers, the design air inlet temperature shall
DISCIPLINE
ENGINEER be 47°C (1% dry bulb temperature from SAES-A-112), with design margins
SBK
applied.
DATE 2-MAR-22_
ENGINEERING
MANAGER
Minimum Design Temperature due to Solar Heating shall be 185°F.
JHK
DATE 2-MAR-22
CERTIFIED 10.1.5 HAZARDOUS AREAS
MWK
DATE 2-MARN-22 Chemical Injection Package and associated systems shall be suitable to following
area classification.
CONSTRUCTION
AGENCY
________________
- 861-U-0403 (Produced Water Chemical Injection Package) : Safe Area
DATE ___________
DATE ___________
BY: ______________
VERIFICATION
EDSD
(DCC)NO. _______________________________
Temp. Class T3
REVISION CERTIFICATE
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
PMT
MWK
Class T3
10.1.6 EQUIPMENT
DESCRIPTION
SUPPLIER shall be responsible for providing and/or coordinating the detail design of
all equipment and components within the scope of supply. SUPPLIER shall provide
expediting services, progress reports, organize SUPPLIER and SUB-SUPPLIER co-
10-14329-0003 ISSUED FOR REVIEW
The equipment in the scope of SUPPLIER shall comply fully with all the referenced
Specifications, Standards, Forms, Drawings and Codes listed in Section 8 and
2-MAR-22
DATE
DISCIPLINE
ENGINEER 10.1.7 EQUIPMENT ASSEMBLY
SBK
DATE 2-MAR-22_
SUPPLIER shall provide the equipment/materials under this Material Requisition,
ENGINEERING fully wired and assembled practically to minimize BUYER’s site construction work.
MANAGER
JHK
DATE 2-MAR-22
CERTIFIED
10.1.8 OFF SKID AND SHIP LOOSE ITEMS
MWK
SUPPLIER shall provide a list of off skids and ship loose items, together with
DATE 2-MARN-22
estimated size and weight information, in his bid. SUPPLIER shall also provide a
CONSTRUCTION
description of site installation work to be executed by BUYER for each off skid and
AGENCY
ship loose item to enable estimating construction work volume involved.
________________
DATE ___________
OPERATIONS
10.1.9 ACCESSIBILITY AND MAINTENABILITY
________
DATE ___________
All components requiring operational checks and maintenance shall be easily
accessible. SUPPLIER shall be responsible for providing all access walkways,
DATE _____________
CONTROL NUMBER
BY: ______________
VERIFICATION
ladders, stairs, platforms and associated support structures required for the
EDSD
(DCC)NO. _______________________________
REVISION CERTIFICATE
10.1.10 MATERIALS
MATERIAL REQUISITION DWG.TYPE PLANT .NO INDEX DRAWING NO. SHT. NO. REV. NO.
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
PMT
Material shall comply with and be selected as per data sheet, project specification
ENG’G CERT
MWK
All materials for pressure part shall be designed as per relevant ASME Codes for
all parts. The materials directly welded on pressure retaining components shall
be of the same material as that used for the pressure retaining components.
10.1.11 NAMEPLATES
DESCRIPTION
brand name, and date of application. ASME nameplate shall be attached next to
``
SUPPLIER’s nameplate.
SUPPLIER shall also verify, confirm and comply with the specific and unique
2-MAR-22
DATE
a) Tag number
A
DISCIPLINE
ENGINEER b) Manufacturer
SBK
c) Full model number
DATE 2-MAR-22_ d) Serial number
ENGINEERING
MANAGER e) Ingress protection rating
JHK
f) Area classification
DATE 2-MAR-22 g) Flange size and rating (where applicable)
CERTIFIED
MWK
OPERATIONS
Each unit shall be designed to ensure that during all modes of operation, the total
________
overall package sound pressure level emitted by the Package and its associated
DATE ___________
auxiliaries does not exceed 85 dB(A) measured at a distance of 3 feet (1 m) from
the surface of machine.
DATE _____________
CONTROL NUMBER
BY: ______________
VERIFICATION
If the noise level is greater than 90 dB(A) at a distance of 1 m from the skid edge,
EDSD
(DCC)NO. _______________________________
REVISION CERTIFICATE
SUPPLIER shall confirm requirements of special tools to install, adjust, operate and
maintain the equipment and provide it, if required.
MATERIAL REQUISITION DWG.TYPE PLANT .NO INDEX DRAWING NO. SHT. NO. REV. NO.
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
PMT
ENG’G CERT
MWK
All equipment and materials shall be supplied suitably protected from corrosion
during transportation, storage, after installation and during operation according to
the referenced documents in Section 8 and Section 9.
Painting shall be applied to where it needs as per coating map. Manufacturer
standard for external coating is acceptable provided that manufacturer standard is
suitable for highly corrosive (C5-I) environment with high durability. (equivalent to
DESCRIPTION
C5 in ISO 12944)
All painting shall be performed after hydrostatic test.
SUPPLIER shall follow the requirement of BUYER’s equipment color code and get
BUYERs approval of SUPPLIER’s painting procedure. Inspection shall be
10-14329-0003 ISSUED FOR REVIEW
SUPPLIER shall also provide 5% touch-up paint materials for field repair work.
SUPPLIER shall also comply and be responsible to meet the requirements that are
additional and specified by the applicable SAMSS.
JO/EWO
``
2-MAR-22
________________
DATE ___________
10.1.16 PACKING AND SHIPPING
OPERATIONS
________ SUPPLIER shall ensure that all equipment and materials are designed and packed
DATE ___________
for transit to site without damage and in accordance with the requirements of the
DATE _____________
BY: ______________
VERIFICATION
EDSD
Tested and inspected equipment shall be emptied, dried, painted and where
necessary, preserved for shipment and long term outside storage.
All platforms and ladders shall be assembled and tested for fit-up and then
APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV. NO. _____A_____
(DCC)NO. _______________________________
MATERIAL REQUISITION DWG.TYPE PLANT .NO INDEX DRAWING NO. SHT. NO. REV. NO.
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
PMT
SUPPLIER shall protect his equipment during transportation, handling and storage
ENG’G CERT
MWK
All equipment shall be packed and weather protected for export. Loose parts shall
be boxed and shipped along with an itemized packing list with the main assembly.
SUPPLIER shall clearly indicate on the shipping cases or other packages the
required storage conditions.
DESCRIPTION
Loose parts shall be individually numbered and boxed and shipped along with the
packing list contains parts and item numbers.
If the SUPPLIER fails to deliver any part of the Goods at the agreed time due to
the Supplier’s default, the supplier shall supply the Goods involved in the late
JO/EWO
deliver in terms of the FCA, and actual Costs including fright fare, custom duty and
all relevant Costs to the Site shall be borne by the SUPPLIER. BUYER holds the
``
SUPPLIER shall comply with the specific shipping preparation requirements listed
in SAMSS, BUYER’s Packing and Shipping Instructions, as well as the
REV. NO.
JHK
MWK
SUPPLIER’s supplied material shall comply with Saudi Standards, Metrology, and
DATE 2-MARN-22 Quality Organization (SASO) requirements. If a SASO certificate is required for
SUPPLIER’s supplied materials, SUPPLIER shall promptly forward a copy of the
CONSTRUCTION
AGENCY SASO approved certificate to COMPANY Representative and to BUYER.
________________
DATE ___________ SUPPLIER shall ensure to comply with the SASO Certificate and Hazardous
OPERATIONS material import/special approval requirements and to coordinate with BUYER to
________
confirm the compliance prior to physical shipment of materials.
DATE ___________
SUPPLIER shall be responsible to ensure that if the commodity requires a special
DATE _____________
CONTROL NUMBER
BY: ______________
permit issued by the applicable Saudi Ministry, SUPPLIER obtain such permit prior
VERIFICATION
For the purpose of Customs Clearance in KSA through online SABER system
which is mandatory requirement for the imported equipment and materials to KSA
from Feb. 2020 instead of SASO Certificate.
APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV. NO. _____A_____
(DCC)NO. _______________________________
REVISION CERTIFICATE
SUPPLIER shall provide BUYER with the following documents for SABER system
registration by 90 days before contracted delivery terms.
MATERIAL REQUISITION DWG.TYPE PLANT .NO INDEX DRAWING NO. SHT. NO. REV. NO.
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
PMT
a) Drawings
ENG’G CERT
MWK
SUPPLIER shall bear any costs for the preparation of the said documents and
10-14329-0003 ISSUED FOR REVIEW
SUPPLIER shall quote for the provision of suitably qualified and experienced
``
personnel for the supervision of filed services. The following field services might be
2-MAR-22
required:
DATE
a) Installation
REV. NO.
b) Commissioning
DISCIPLINE
ENGINEER
c) Site Performance Testing
SBK
DATE 2-MAR-22_
ENGINEERING
These Field Services will be the subject of a separate contract when required.
MANAGER
JHK
DATE 2-MAR-22
CERTIFIED 10.1.19 TRAINING
MWK
DATE 2-MARN-22
SUPPLIER shall quote the provision of suitably experienced and qualified
personnel to train COMPANY’s personnel in:
CONSTRUCTION
AGENCY a) Pricing for training sessions to be held in the Kingdom of Saudi Arabia.
________________
DATE ___________
b) Pricing for trainers to work In Kingdom.
OPERATIONS c) Pricing for specific training courses outside the Kingdom of Saudi Arabia.
________
Training shall be carried out on site or SUPPLIER’s training facility and shall
DATE ___________
include the provision of support documentation.
DATE _____________
CONTROL NUMBER
BY: ______________
VERIFICATION
10.1.20 SUB-SUPPLIERS
APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV. NO. _____A_____
(DCC)NO. _______________________________
REVISION CERTIFICATE
SUPPLIER shall control, co-ordinate, expedite and resolve all problems with any
SUB-SUPPLIERS in order to meet the requirements of this Material Requisition.
MATERIAL REQUISITION DWG.TYPE PLANT .NO INDEX DRAWING NO. SHT. NO. REV. NO.
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
PMT
SUPPLIER shall guarantee and be responsible for the design and performance of
ENG’G CERT
MWK
all sub-supplied items. SUPPLIER shall ensure that all the relevant information,
reference documents and documentation requirements are passed on to any SUB-
SBK
SUPPLIERS
SUPPLIER shall ensure that all his SUB-SUPPLIERS manufacturing site have and
maintain documented quality management system in accordance with the ISO-
10-14329-0003 ISSUED FOR REVIEW
Major equipment components and materials shall be supplied from the SAUDI
ARAMCO RVL List when applicable. SUPPLIER shall fill up “Sub-Vendor Listing &
Manufacturing Method Statement” attached in Sec. 8.1 of this Material Requisition
to submit such SUB-SUPPLIER’s information, whether SUB-SUPPLIERS are listed
in the RVL or not, for COMPANY’s prior approval.
JO/EWO
``
SUPPLIER shall, as part of the detail design documentation, provide a copy of all
REV. NO.
DISCIPLINE
request. SUPPLIER is to ensure that all relevant SAUDI ARAMCO technical and
ENGINEER quality requirements are passed onto the SUB-SUPPLIERS for compliance.
SBK
DATE 2-MAR-22_ SUPPLIER shall provide original manufacturer source information for all material
ENGINEERING
MANAGER
and spare parts supplied on each PURCHASE ORDER including, but not limited to,
manufacturer’s name, address, sales order number, sales contact name,
JHK
telephone number, fax number and e-mail address.
DATE 2-MAR-22
CERTIFIED
SUPPLIER shall visit, perform SUB-SUPPLIERS’ shop expediting and report to
MWK
BUYER whenever BUYER requests without additional cost impact.
DATE 2-MARN-22
CONSTRUCTION
AGENCY
OPERATIONS SUPPLIER shall guarantee that the complete scope of supply shall safely and reliably
________ meet all of the requirements of this Material Requisition and its reference documents.
DATE ___________
DATE _____________
CONTROL NUMBER
BY: ______________
VERIFICATION
10.1.22 DOCUMENTATION
EDSD
(DCC)NO. _______________________________
REVISION CERTIFICATE
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
PMT
All SUPPLIER drawings and as-built drawings shall be produced by Bentley Micro
ENG’G CERT
MWK
station CADD in accordance with the CADD specifications in SAES-A-202 and SAEP-
110. AutoCAD shall not be allowed.
SBK
All drawings shall reflect all dimension, design detail and written works in SI
(modified) units and shall be in the English language. However, operating parameters
such as design pressure, design temperature, flowrate and etc. shall be US
Customary Units.
SUPPLIER shall submit Monthly Progress Report at designated date of every month
until complete delivery.
DESCRIPTION
As per SAEP-3101, SUPPLIER shall submit the SPDP package to the BUYER by
the specified delivery date which shall be either the same delivery date as NMR-
602 or delivery prior to shipment release of the equipment.
10-14329-0003 ISSUED FOR REVIEW
Non-Material Requirements (NMR item 601, 602, and 603 on SAUDI ARAMCO
7900 Series Forms) are an integral part of this requirement as are the complete
spare parts packages as such, notwithstanding the terms of payment provisions in
the applicable conditions of purchase, purchase order payment up to the full
purchase order price may be withheld until all Non-Material Requirements and
spare parts data packages are delivered and accepted by COMPANY.
JO/EWO
Material delivery shall not be considered complete until two (2) complete original
``
sets and one (1) electronic copy of Vendor Equipment Operating Instructions and
Equipment Maintenance Manuals have been transmitted to COMPANY and
2-MAR-22
DATE
DISCIPLINE
10.1.23 UNITS OF MEASUREMENTS
ENGINEER
SBK Unless specified otherwise, English units shall be used for name plates, operating
DATE 2-MAR-22_ parameters, data sheets, gauges/instruments as specified in Attachment 1 of BEDD
ENGINEERING
MANAGER
(TD-821950).
JHK
DATE 2-MAR-22
CERTIFIED 10.1.24 LANGUAGE
MWK
DATE 2-MARN-22
All the correspondence as well as drawings, instructions, data sheets, design
calculations and any other written information shall be issued in the English
CONSTRUCTION
AGENCY
language. Certificates issued in the country of origin language shall be submitted
________________
“as final” complete with the English translation.
DATE ___________
OPERATIONS
10.1.25 PROJECT COORDINATION
________
DATE ___________
After PURCHASE ORDER placement, SUPPLIER shall assign a project
DATE _____________
CONTROL NUMBER
BY: ______________
(DCC)NO. _______________________________
REVISION CERTIFICATE
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
PMT
MWK
``
2-MAR-22
DATE
REV. NO.
DISCIPLINE
ENGINEER
SBK
DATE 2-MAR-22_
ENGINEERING
MANAGER
JHK
DATE 2-MAR-22
CERTIFIED
MWK
DATE 2-MARN-22
CONSTRUCTION
AGENCY
________________
DATE ___________
OPERATIONS
________
DATE ___________
DATE _____________
CONTROL NUMBER
BY: ______________
VERIFICATION
EDSD
APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV. NO. _____A_____
(DCC)NO. _______________________________
REVISION CERTIFICATE
MATERIAL REQUISITION DWG.TYPE PLANT .NO INDEX DRAWING NO. SHT. NO. REV. NO.
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
PMT
MWK
and API 675 3rd Edition, data sheets and mentioned project specifications. Pumps
shall be provided from COMPANY approved manufacturer.
All pumps shall be in compliance with SAES-G-006, 31-SAMSS-009, and API 675
10-14329-0003 ISSUED FOR REVIEW
The Net Positive Inlet Pressure Available (NPIPA) shall exceed the Net Positive
Inlet Pressure Required (NPIPR) by a minimum of 1m head of liquid pumped
converted to pressure in kPa (psi).
JO/EWO
``
DISCIPLINE
system. For this signaling system, a pressure detector (pressure transmitter) shall
ENGINEER
be used for dry designs and a conductivity probe shall be used for pumps having
SBK an intermediate fluid between the diaphragms.
DATE 2-MAR-22_
ENGINEERING Pump shall have an electronic automatic adjustable length stroke controller,
MANAGER
capable of remote land local control without stopping the pump. Stroke length shall
JHK
be adjustable, both locally and by a control signal from the remote control room.
DATE 2-MAR-22
CERTIFIED
Mechanical lost motion capacity adjustment is not permitted.
MWK Each pump shall have a minimum operating capacity of 30 – 110% of the
DATE 2-MARN-22
recommended dosing rate.
CONSTRUCTION
AGENCY For each of the chemical injection points, pump shall be specified to cover the full
________________ range of flow specified for all dosing modes (i.e. including normal and shock).
DATE ___________
Pumps shall have adjustable speed (stroke rate) or stroke length to enable
OPERATIONS different dosing rates from the same pump.
________
DATE ___________
DATE _____________
BY: ______________
VERIFICATION
EDSD
The storage tank shall be provided with quick opening for chemical loading and
THIS INDICATES THAT REV. NO. _____A_____
(DCC)NO. _______________________________
REVISION CERTIFICATE
inspection.
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
PMT
Chemical storage tanks shall, as a minimum, be equipped with fill nozzle, utility
ENG’G CERT
MWK
nozzle, vent, pressure relief, overflow, discharge, low point drain, level and
temperature instrumentation.
SBK
Block valves shall be installed directly at the tank nozzles. If more than one line
connects to the same nozzle, valves shall be installed in each line, in addition to
the nozzle block valve.
DESCRIPTION
The Package VENDOR shall complete tank data sheet Form SA-2696 for review
by BUYER.
SUPPLIER shall propose appropriate means of loading for each selected chemical
10-14329-0003 ISSUED FOR REVIEW
necessary to meet the following criteria. Unfiltered peak to peak pulsation levels
``
- Rated suction pressure or 100 kPa gauge (15 psig) whichever is less;
DATE
- Rated discharge pressure or 100 kPa gauge (15 psig) whichever is less.
REV. NO.
The SUPPLIER shall be responsible for ensuring that the following situations are
DISCIPLINE
ENGINEER avoided:
SBK
- Cavitation in the suction or discharge of the pump;
DATE 2-MAR-22_
ENGINEERING
- Over delivery due to suction losses or uncontrolled delivery;
MANAGER
- Exceeding maximum allowable working pressure of pressure containing parts
JHK (including auxiliaries).
DATE 2-MAR-22
CERTIFIED The SUPPLIER shall provide any fittings required for charging the pulsation
MWK dampers. These shall be securely fastened to the pump.
DATE 2-MARN-22
CONSTRUCTION
AGENCY
OPERATIONS
Lubrication shall be recommended by SUPPLIER based on SAUDI ARAMCO
Standard, and recommendation charge for the initial charge, pre-commissioning
________
DATE ___________
and start-up and commissioning shall be provided by SUPPLIER.
DATE _____________
CONTROL NUMBER
BY: ______________
BUYER can request equivalent lube oil and grease types and SUPPLIER shall
VERIFICATION
10.2.5 MATERIALS
APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV. NO. _____A_____
(DCC)NO. _______________________________
SUPPLIER shall verify and advise material constructions suitable for the service
REVISION CERTIFICATE
MATERIAL REQUISITION DWG.TYPE PLANT .NO INDEX DRAWING NO. SHT. NO. REV. NO.
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
PMT
MWK
Sheet is not acceptable, and higher grade than specified materials on Mechanical
Data Sheet can be applicable as per SUPPLIER’s recommendation, but shall have
COMPANY’s approval.
The electric motors shall be induction as specified on the motor data sheets and
shall be designed in accordance with SAUDI ARAMCO material specification 17-
SAMSS-503 and SAUDI ARAMCO engineering standard SAES-P-113.
Motors shall be based on full voltage.
For LV motor between 1 HP (0.75 kW) and 500 HP (370 kW), the supply voltage
JO/EWO
shall be 480 V and the rated voltage of the motor shall be 460 V.
``
All motors shall be suitable for the Hazardous area classification specified on the
data sheet.
2-MAR-22
DATE
Totally enclosed motors shall have at least one drain hole with a plug at each end.
Motors shall be provided with a minimum of 2 suitable grounding terminal lugs.
REV. NO.
DISCIPLINE Degree of protection for motor shall be minimum "IP55" in accordance with IEC
ENGINEER
60529.
SBK
DATE 2-MAR-22_
Degree of protection for terminal box shall be “NEMA 4X” in accordance with
ENGINEERING NEMA 250 or “IP55” in accordance with IEC 60529.
MANAGER
JHK
The terminal box shall have Type 300 series stainless steel hardware (Bolts, nuts
DATE 2-MAR-22
and etc.).
Motor winding insulation shall be Class “F” with an allowable Class “B”
CERTIFIED
MWK
Temperature rise above the ambient of 50℃ as per NEMA MG 1, Part12, Part 20
DATE 2-MARN-22
or Part 21, or IEC 60034-1 limits as applicable.
CONSTRUCTION
AGENCY The Space heater rated voltage shall be 230V.
________________
Space heaters shall be provided for motors rated 75 kW (100 HP) and above.
DATE ___________
OPERATIONS If Space heaters are provided, a caution nameplate shall be provided stating
________
CAUTION : SPACE HEATERS MAY BE ENERGIZED.
DATE ___________
The orientation of terminal box shall be adjustable in each 90 deg wise.
DATE _____________
CONTROL NUMBER
BY: ______________
Main terminal boxes for electric motors shall be one step oversized per NEMA MG
VERIFICATION
EDSD
1.
Cooling fan shall be of the non-sparking, non-corrosive type, and per the IEEE Std.
841, section 6.4.
Installations in hazardous locations shall be per the National Electrical Code, with
APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV. NO. _____A_____
(DCC)NO. _______________________________
REVISION CERTIFICATE
MATERIAL REQUISITION DWG.TYPE PLANT .NO INDEX DRAWING NO. SHT. NO. REV. NO.
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
PMT
MWK
protection must be marked and must correspond with NEC Article 505
requirements for suitable protection method(s) for the hazardous area where the
equipment is applied.
- Increased safety (protection type “e”) motors and terminal boxes are not
permitted Class I, Zone 1 or Zone 2 locations.
- Equipment listed and marked in accordance to NEC for use in Zone 0, 1, or 2
DESCRIPTION
locations shall be permitted in Class I, Division 2 locations for the same gas and
with a suitable temperature class.
10-14329-0003 ISSUED FOR REVIEW
Coupling guards with inspection cover (or window) shall be provided and shall
``
sufficiently enclose the coupling and the shafts to prevent any personnel from
contacting parts during operation of the equipment train.
2-MAR-22
DATE
This cover or window must be securely fixed and require a tool or key to enable
them to be opened.
REV. NO.
DISCIPLINE
ENGINEER 10.2.8 FOUNDATION AND STRUCTURE BASE FRAME
SBK
DATE 2-MAR-22_ Fabrication of structure base frame shall be in accordance with 12-SAMSS-007
ENGINEERING
MANAGER
“Fabrication of Structural and Miscellaneous Steel”.
JHK SUPPLIER shall be responsible for the proper design of the base plate and for the
DATE 2-MAR-22 elimination of any unacceptable characteristics such as harmonic vibration.
CERTIFIED
Package components shall be skid mounted. The structure base frame shall
MWK
complete with the followings:
DATE 2-MARN-22
Lifting lugs
CONSTRUCTION
AGENCY
BY: ______________
Base frame shall be provided with four (4) lifting lugs installed such that the center
VERIFICATION
EDSD
of gravity of the package is midway between opposite lugs, to allow a single point
lift.
Lifting lugs on the base frame shall be magnetic particle examined.
SUPPLIER shall demonstrate that sufficient access is being provided for
APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV. NO. _____A_____
(DCC)NO. _______________________________
REVISION CERTIFICATE
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
PMT
All equipment shall be mounted within the dimensions of the baseplate with no
ENG’G CERT
MWK
Stainless steel earthing (grounding) bosses for baseplate (structural base frame)
shall be provided at diagonal positioned and wiring throughout inclusive of cable
gland and lugs as per standard drawing, which will be provided at the detail design
phase. Tapped hole shall be provided for stainless steel bolt which will be supplied
10-14329-0003 ISSUED FOR REVIEW
by others.
The Vendor shall provide and install the necessary instrumentation and junction
JO/EWO
boxes required to monitor and protect the Chemical Injection Package and all
``
Vendor supplied associated auxiliary systems over the full range of operating
conditions. Refer to 861-J-TD-821303, C&I Package Equipment Specification.
2-MAR-22
DATE
The instrument and control shall be in accordance with the project specification
“34-SAMSS-831 - Instrumentation for Package Units”
REV. NO.
DISCIPLINE
The equipment within the Vendor scope shall be monitored, protected and
ENGINEER controlled by the CONTRACTOR’s Process Control System (PCS). This shall be
SBK provided by others and consist of, but is not limited to:
DCS for basic process control
DATE 2-MAR-22_
ENGINEERING
MANAGER
________________ All equipment used for machinery protection system shall comply with 34-SAMSS-
DATE ___________ 625.
OPERATIONS
The monitor(s) / module(s) for the machinery protection and condition monitoring
________
system(s) covered by 34-SAMSS-625 for monitoring bearing temperature and
DATE ___________
vibration shall be outside of Vendor scope and shall be supplied by others for
DATE _____________
BY: ______________
VERIFICATION
EDSD
The Vendor scope includes all on-skid equipment of instrumentation; cabling and
separate junction boxes for Foundation Fieldbus, ESD, DCS analog, DCS digital,
VMS probes / transducers and bearing temperature signals as required by SAUDI
ARAMCO specifications and Vendor recommendation.
APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV. NO. _____A_____
(DCC)NO. _______________________________
The MPS probes that are supplied by the Vendor shall be compatible with the
REVISION CERTIFICATE
project MPS. There will be a common VMS / CMS, but the Vendor has yet to be
determined.
MATERIAL REQUISITION DWG.TYPE PLANT .NO INDEX DRAWING NO. SHT. NO. REV. NO.
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
PMT
The Vendor shall indicate if there are any distance limitations to be considered
ENG’G CERT
MWK
The Vendor shall provide all field instrumentation, including primary connections,
and shall clearly define during the bid phase if any instrument is supplied loose.
Where instruments are supplied loose, Vendor shall provide detailed installation
10-14329-0003 ISSUED FOR REVIEW
details documenting the arrangement, activities and materials required for the
process, pneumatic, electrical and support hook-ups.
Instruments interfaced with the Distributed Control System (DCS) shall be
Foundation Fieldbus. Instrument systems wired to the Emergency Shutdown
(ESD) shall use 4-20mA signals with a superimposed HART protocol for smart
communications.
JO/EWO
``
The Vendor shall supply all required documentation to support safety requirements
A
DISCIPLINE
for the package, as well as documentation for the DCS / ESD Vendor such as:
ENGINEER
Logic diagrams
SBK
________
The Vendor shall resolve all comments and actions arising out of the HAZOP and
DATE ___________ SIL reviews to ensure compliance with SAUDI ARAMCO, Project and International
Code requirements.
DATE _____________
CONTROL NUMBER
BY: ______________
VERIFICATION
Control signals and measured value signals shall not be affected by stray AC
EDSD
voltage or other interference of any type normally found in an industrial facility. The
Vendor shall provide shielded cables.
Unless otherwise specifically approved by COMPANY switch type instruments
shall not be used. Instead transmitter type instruments shall be installed by
APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV. NO. _____A_____
(DCC)NO. _______________________________
REVISION CERTIFICATE
Vendor.
MATERIAL REQUISITION DWG.TYPE PLANT .NO INDEX DRAWING NO. SHT. NO. REV. NO.
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
PMT
The Vendor shall complete all COMPANY instrument datasheets using the formats
ENG’G CERT
MWK
the cable formation chosen. This format will be advised to Vendor during detailed
engineering.
The Vendor shall provide multi-sided sunshades on all Vendor provided transmitter
racks, gauge boards and local control panels.
Junction boxes shall be supplied with 316L SS material.
DESCRIPTION
the equipment.
The Vendor shall provide multi-sided sunshades on all Vendor provided transmitter
racks, gauge boards and local control panels.
SUPPLIER shall provide strainer for chemical injection pumps, and differential
pressure transmitter requirement to be evaluated on case by case basis dependent
JO/EWO
transmitter to provide remote level indication, including high and low level
alarms.
REV. NO.
DISCIPLINE
ENGINEER
A temperature gauge shall be supplied on the tank for indication of bulk
fluid temperature.
SBK
JHK Pressure and flow transmitters shall be supplied on the common discharge
DATE 2-MAR-22 manifold.
CERTIFIED
MWK Pump shall have an external PSV with the PSV discharge line piped back
DATE 2-MARN-22 to the tank.
CONSTRUCTION
AGENCY Double diaphragm pumps shall be provided with a diaphragm failure signal
________________ system.
DATE ___________
OPERATIONS Instrumentation shall be wired to skid edge Junction Box for wiring to the
________ DCS by others.
DATE ___________
All junction boxes, cable trays, instruments and panels shall be suitable for
DATE _____________
CONTROL NUMBER
BY: ______________
Sunshades shall be suitably sized and installed to provide full protection to the
transmitter body, including any Liquid-Crystal Display (LCD) display, from solar
radiation.
APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV. NO. _____A_____
(DCC)NO. _______________________________
REVISION CERTIFICATE
MATERIAL REQUISITION DWG.TYPE PLANT .NO INDEX DRAWING NO. SHT. NO. REV. NO.
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
PMT
MWK
Each positive displacement pump shall have an external PSV with independent
SBK
discharge line piped back to the tank above the high high liquid level.
A pressure relief valve must be installed on the pump discharge to vent fluid back
into the suction line if pressure builds up. The actual pump internal relief valve
setting shall be between 110% and 120% of the rated discharge pressure.
Pressure relief valves with operating pressure greater than 15 psig shall carry
ASME code stamp “UV” as per ASME Section VIII.
DESCRIPTION
Pressure relief valves shall have a minimum process connection size of ¾ -inch
threaded or 1-inch flanged.
Pressure relief valve minimum flange rating for the inlet connection shall be ASME
10-14329-0003 ISSUED FOR REVIEW
Class 150 as per ASME B16.5 and the outlet flange rating shall follow the relevant
piping material specification.
10.2.13 PIPING
REV. NO.
DISCIPLINE
ENGINEER All Vendor auxiliary connections to CONTRACTOR interface pipework shall be
SBK
flanged.
DATE 2-MAR-22_ As far as possible all piping interfaces shall be grouped and brought to the skid
ENGINEERING
MANAGER edge.
JHK Flange connections overhanging the baseplate skid edge are not permitted.
DATE 2-MAR-22
CERTIFIED All tubing and tubing fittings on the package shall utilize US fittings and US sized
MWK
tubing.
DATE 2-MARN-22
All bolting material for flange joints installed in highly (C5-I) or severely corrosive
CONSTRUCTION
(C5-M) environments shall be protected based on para 6.2.7 of SAES-A-134.
AGENCY
________________ Piping systems shall be generally designed and constructed in compliance with the
DATE ___________ requirements of ASME B31.3 piping codes.
OPERATIONS
Design of piping shall be in compliance with the Saudi Aramco Engineering
________ Standard SAES-L-310, Design of Plant Piping.
DATE ___________
Piping material specification shall be in compliance with TD-821107, PIPING
DATE _____________
CONTROL NUMBER
BY: ______________
SUPPLIER shall be responsible for all aspects of individual piping flexibility and
supporting requirements during detailed design.
SUPPLIER shall ensure a clear access of 750mm is maintained from 2 sides for all
APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV. NO. _____A_____
(DCC)NO. _______________________________
REVISION CERTIFICATE
Equipment nozzles
MATERIAL REQUISITION DWG.TYPE PLANT .NO INDEX DRAWING NO. SHT. NO. REV. NO.
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
PMT
MWK
Actuators
Instruments
SUPPLIER shall design piping systems to eliminate dead legs to the maximum
extent possible. In locations at which the introduction of a dead leg cannot be
avoided, SUPPLIER shall keep the length of the dead leg to an absolute minimum.
DESCRIPTION
The drain valves shall ideally be mounted immediately on the branch outlet from
the main line (and as close possible to the strainer drain flange/outlet), to minimize
dead leg and associated corrosion issues.
10-14329-0003 ISSUED FOR REVIEW
SUPPLIER shall take into account the need for flexibility in piping to allow for
removal of valves, spectacle blinds, blinds / spacers and any other removable
specialty items. Jacking bolts shall be provided as required.
SUPPLIER shall provide all valves 6 inch & above, spectacle blinds, blinds and
spacers and all removable items weighing more than 25 kgs. with ‘’open to sky’’ as
JO/EWO
basis of the design and shall ensure that those are accessible by cranes/mobile
``
lifts. Any difficulties to meet the ‘’open to sky’’ requirements shall require
CONTRACTOR approval and, in such cases, necessary lifting beam / monorails
2-MAR-22
DATE
with chain & hoist shall be provided to enable their removal and reinstatement.
SUPPLIER shall provide 3D model generated by SP3D 2018 Version and
REV. NO.
Equipment Tag Number, Nozzle Number and Line Number shall be included in
A
DISCIPLINE
ENGINEER
model property.
SBK
DATE 2-MAR-22_
ENGINEERING
10.2.14 TEST AND INSPECTION
MANAGER
JHK PUMP
DATE 2-MAR-22
CERTIFIED
The pumps shall be tested and inspected in accordance with 31-SAMSS-009, API
675 third edition, inspection & testing requirement form 175-311500, project
MWK
specification and equipment datasheets.
DATE 2-MARN-22
CONSTRUCTION
Test certificates only are required for pump types with proven SAUDI ARAMCO
AGENCY operating experience.
________________
DATE ___________ Hydrostatic test and performance test shall be in accordance with API 675.
OPERATIONS
________
DATE ___________
ELECTRIC MOTOR DRIVES
DATE _____________
BY: ______________
VERIFICATION
Requisition, and Equipment Data Sheets. All motor feet shall be fastened to the
test base or ground for the exact vibration test.
Test certificate shall be provided.
APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV. NO. _____A_____
(DCC)NO. _______________________________
REVISION CERTIFICATE
OF THIS DRAWING IS COVERED, FOR ALL
MATERIAL REQUISITION DWG.TYPE PLANT .NO INDEX DRAWING NO. SHT. NO. REV. NO.
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
PMT
MWK
Safety Relief Valves shall be tested and inspected in accordance with Inspection &
SBK
Relief Valve Authorization and Test Report Record (SA-3099A) shall be submitted.
STORAGE TANK
DESCRIPTION
Tank shall be tested and inspected in accordance with Inspection & Testing
Requirements Form 175-325100 or 175-325300 respectively.
10-14329-0003 ISSUED FOR REVIEW
``
FIELD TESTING
2-MAR-22
DATE
SBK
As soon as possible after the installation is completed, a field performance test
DATE 2-MAR-22_
shall be conducted on each equipment. SUPPLIER shall present the test and
ENGINEERING verify taken data in an acceptable manner. The test should confirm, as a minimum,
MANAGER
that the equipment can meet the design rating of flow and pressure.
JHK
DATE 2-MAR-22
CERTIFIED
MWK
DATE 2-MARN-22
CONSTRUCTION
AGENCY
________________
DATE ___________
OPERATIONS
________
DATE ___________
DATE _____________
CONTROL NUMBER
BY: ______________
VERIFICATION
EDSD
APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV. NO. _____A_____
(DCC)NO. _______________________________
REVISION CERTIFICATE
MATERIAL REQUISITION DWG.TYPE PLANT .NO INDEX DRAWING NO. SHT. NO. REV. NO.
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
PMT
APPENDIX 1 – DEFINITIONS
ENG’G CERT
MWK
SBK
The following words and expressions used in this Material Requisition have the meanings
given to the below:
BUYER means HYUNDAI ENGINEERING CO., LTD. or HYUNDAI
ENGINEERING AND CONSTRUCTION CO., LTD.
COMPANY means SAUDI ARABIAN OIL COMPANY (SAUDI ARAMCO).
DESCRIPTION
SDI (or VDR) – Supplier Document Index (or Vendor Data Register)
REV. NO.
DISCIPLINE
ENGINEER
SBK The following words and/or expression, unless otherwise specifically clarified, used in
DATE 2-MAR-22_ COMPANY documents and/or drawings shall be considered as follows.
ENGINEERING
MANAGER Shall Must
JHK
Recommended Mandatorily Required
DATE 2-MAR-22
CERTIFIED
Preferred Supplied or Applied
MWK
SA means SAUDI ARAMCO
DATE 2-MARN-22
CONSTRUCTION
AGENCY
________________
DATE ___________
OPERATIONS
________
DATE ___________
DATE _____________
CONTROL NUMBER
BY: ______________
VERIFICATION
EDSD
APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV. NO. _____A_____
(DCC)NO. _______________________________
REVISION CERTIFICATE
MATERIAL REQUISITION DWG.TYPE PLANT .NO INDEX DRAWING NO. SHT. NO. REV. NO.
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
PMT
ENG’G CERT
MWK
SUPPLIER shall supply the listed equipment items complete with all ancillary equipment
necessary to meet the conditions as defined in this Section and the Equipment Data
Sheets in Section 7.
The equipment shall perform all the duties as specified on the Equipment Data Sheets.
SUPPLIER shall also be responsible for providing / co-coordinating detail design of all
DESCRIPTION
equipment and components within the scope of supply, providing expediting services,
progress reports, organizing SUPPLIER and SUB-SUPPLIER co-ordination / kick-off /
design review meetings, resolving engineering questions relating to equipment within the
scope of supply and package interfaces.
10-14329-0003 ISSUED FOR REVIEW
SUPPLIER shall select SUB-SUPPLIERS for equipment and materials from COMPANY
Regulated Vendor List. SUPPLIER shall fill up his SUB-SUPPLIERS using Sub-Vendor
Listing & Manufacturing Method Statement and submit it for COMPANY’s prior approval.
SUPPLIER’s scope of supply shall include, but is not limited to, the following items
detailed in the tabulation:
JO/EWO
``
compliance
REV. NO.
DISCIPLINE
ENGINEER
1.1 Chemical Injection Packages shall include:
SBK
JHK
DATE 2-MAR-22
Produced Water Chemical Injection Package
CERTIFIED skid 1- Biocide
MWK
DATE 2-MARN-22
Produced Water Chemical Injection Package
skid 2- Corrosion inhibitor
CONSTRUCTION
AGENCY
________________
Produced Water Chemical Injection Package
DATE ___________ skid 3- Oxygen Scavenger
OPERATIONS
________
Produced Water Chemical Injection Package
DATE ___________
skid 4- Scale inhibitor
DATE _____________
CONTROL NUMBER
BY: ______________
(DCC)NO. _______________________________
REVISION CERTIFICATE
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
PMT
MWK
compliance
SBK
``
SBK
1.1.9 BFW Chemical Dosing Package (869-U-
DATE 2-MAR-22_
1009/2009/3009) consisting of the following injection
ENGINEERING skids
MANAGER
JHK
BFW Dosing chemical skid 1 – phosphate
DATE 2-MAR-22
CERTIFIED
Injection
MWK
BFW Dosing chemical skid 2 - Oxygen
DATE 2-MARN-22
scavenger Injection
CONSTRUCTION
AGENCY
1.1.10 Ammonium Sulfate Dosing Package (869-U-
________________
DATE ___________
1010/2010/3010)
OPERATIONS
________
DATE ___________
DATE _____________
CONTROL NUMBER
BY: ______________
VERIFICATION
EDSD
APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV. NO. _____A_____
(DCC)NO. _______________________________
REVISION CERTIFICATE
MATERIAL REQUISITION DWG.TYPE PLANT .NO INDEX DRAWING NO. SHT. NO. REV. NO.
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
PMT
MWK
compliance
SBK
DISCIPLINE
ENGINEER
Level gauge selected in accordance with SAES-
J-100
SBK
DATE 2-MAR-22_
ENGINEERING
Temperature gauge for each tank
MANAGER
CONSTRUCTION
AGENCY
________________
DATE ___________
OPERATIONS
________
DATE ___________
DATE _____________
CONTROL NUMBER
BY: ______________
VERIFICATION
EDSD
APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV. NO. _____A_____
(DCC)NO. _______________________________
REVISION CERTIFICATE
MATERIAL REQUISITION DWG.TYPE PLANT .NO INDEX DRAWING NO. SHT. NO. REV. NO.
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
PMT
MWK
compliance
SBK
``
pressure transmitter)
A
DISCIPLINE
ENGINEER Remote electronic automatic adjustable length
SBK
stroke controller (remote / local)
DATE 2-MAR-22_
ENGINEERING
MANAGER
Back pressure valves, if required
JHK
Suction strainer for positive displacement dosing
DATE 2-MAR-22
CERTIFIED
pump inlet (Y type, flanged with blow off valve)
MWK
Pressure relief valves on pump discharges with
DATE 2-MARN-22
lines routed back to the storage tank
CONSTRUCTION
AGENCY
________________
Pressure gauges on each pump discharge
DATE ___________
OPERATIONS
Sight glasses and flow metering/monitoring
device on each common discharge
________
DATE ___________
Pressure transmitter and flow transmitter on
DATE _____________
CONTROL NUMBER
BY: ______________
(DCC)NO. _______________________________
REVISION CERTIFICATE
MATERIAL REQUISITION DWG.TYPE PLANT .NO INDEX DRAWING NO. SHT. NO. REV. NO.
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
PMT
MWK
compliance
SBK
JO/EWO
Wherever, if required
2-MAR-22
DATE
REV. NO.
DISCIPLINE
ENGINEER
SBK
DATE 2-MAR-22_
ENGINEERING
MANAGER
JHK
DATE 2-MAR-22
CERTIFIED
MWK
DATE 2-MARN-22
CONSTRUCTION
AGENCY
________________
DATE ___________
OPERATIONS
________
DATE ___________
DATE _____________
CONTROL NUMBER
BY: ______________
VERIFICATION
EDSD
APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV. NO. _____A_____
(DCC)NO. _______________________________
REVISION CERTIFICATE
MATERIAL REQUISITION DWG.TYPE PLANT .NO INDEX DRAWING NO. SHT. NO. REV. NO.
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
PMT
MWK
compliance
SBK
equipment items
instrumentation
A
DISCIPLINE
ENGINEER
Grounding (earthing) bosses, diagonally
SBK
positioned & wiring throughout inclusive of cable
DATE 2-MAR-22_
ENGINEERING
glanding and lugs
MANAGER
OPERATIONS
Overall sunshade (removable type) for all
________ chemical injection packages
DATE ___________
DATE _____________
CONTROL NUMBER
BY: ______________
VERIFICATION
EDSD
APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV. NO. _____A_____
(DCC)NO. _______________________________
REVISION CERTIFICATE
MATERIAL REQUISITION DWG.TYPE PLANT .NO INDEX DRAWING NO. SHT. NO. REV. NO.
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
PMT
MWK
compliance
SBK
Exhaust muffler
10-14329-0003 ISSUED FOR REVIEW
Emergency Stop
REV. NO.
DISCIPLINE
ENGINEER
Pump Selector Switch and Running Status
Indication Lamp
SBK
DATE 2-MAR-22_
ENGINEERING
Local / Remote Selector Switch
MANAGER
DATE 2-MARN-22
junction box for wiring to the DCS (wiring from junction box
to DCS by others).
CONSTRUCTION
AGENCY
________ 1.11 Cleaning and drying of all pressure containing parts after
DATE ___________
hydrostatic test at shop as per code and specifications
DATE _____________
CONTROL NUMBER
BY: ______________
VERIFICATION
required
(DCC)NO. _______________________________
1.14 Hydrostatic test for all pressure containing parts and piping
MATERIAL REQUISITION DWG.TYPE PLANT .NO INDEX DRAWING NO. SHT. NO. REV. NO.
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
PMT
MWK
compliance
SBK
1.15 All vent and drain piping & valves, manifolded, fully
supported and brought to a skid edge flange.
section 6.10.
2-MAR-22
DATE
1.21 Special tools. The Vendor shall provide all special tools
that are Vendor specific design and that
REV. NO.
DATE 2-MAR-22
1.23 Lifting equipment quotation as per section 6.6.
CERTIFIED
MWK
Note; OPTIONAL QUOTE ITEM
DATE 2-MARN-22
1.24 Special lifting equipment quotation as per section 6.6.
CONSTRUCTION
AGENCY
OPERATIONS
2.1 Performing / co-ordinating all calculations, simulations,
________
analysis etc. and providing all the documents / drawings
DATE ___________
as specified in this material requisition and all
referenced specifications and standards, and / or the
DATE _____________
CONTROL NUMBER
BY: ______________
(DCC)NO. _______________________________
MATERIAL REQUISITION DWG.TYPE PLANT .NO INDEX DRAWING NO. SHT. NO. REV. NO.
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
PMT
MWK
compliance
SBK
2.2 Providing BUYER with all the electrical & utility data to
enable BUYER to design and install electrical & utility
supplies to all consumers within SUPPLIER’s scope.
DISCIPLINE handling space and determine final plot space for easy
ENGINEER
access during installation and maintenance.
SBK
DATE 2-MAR-22_ 2.7 Co-ordinating all the required activities with the relevant
ENGINEERING
MANAGER Sub-Vendors.
JHK
DATE 2-MAR-22
2.8 Performing all studies required by the COMPANY
CERTIFIED standards and specifications
MWK
DATE 2-MARN-22
2.9 Provide 3D model and participate in 30%, 60% and
90% model reviews.
CONSTRUCTION
AGENCY
________
DATE ___________
DATE _____________
CONTROL NUMBER
BY: ______________
VERIFICATION
EDSD
APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV. NO. _____A_____
(DCC)NO. _______________________________
REVISION CERTIFICATE
MATERIAL REQUISITION DWG.TYPE PLANT .NO INDEX DRAWING NO. SHT. NO. REV. NO.
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
PMT
MWK
compliance
SBK
Kick-off meeting
HAZOP review
DESCRIPTION
SIL review
Pre-inspection meetings
10-14329-0003 ISSUED FOR REVIEW
Safety reviews
JO/EWO
Expediting meetings
``
3D model reviews
2-MAR-22
DATE
DISCIPLINE meeting.
ENGINEER
BY: ______________
VERIFICATION
(DCC)NO. _______________________________
REVISION CERTIFICATE
MATERIAL REQUISITION DWG.TYPE PLANT .NO INDEX DRAWING NO. SHT. NO. REV. NO.
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
PMT
MWK
compliance
SBK
DISCIPLINE
(SPDP) as specified in COMPANY Procedure SAEP-
ENGINEER
3101 Appendix C and D.
SBK
DATE 2-MAR-22
CERTIFIED 4.1 System and components testing, inspection and
preparation for shipping in accordance with the
MWK
DATE 2-MARN-22
Equipment Data Sheets, referenced Standards,
Specification and all the relevant COMPANY’s
CONSTRUCTION
AGENCY
inspection 175 Forms and enclosed in Section 9.
________________
DATE ___________
4.2 Positive Displacement Pump
OPERATIONS
________
4.2.1 The pumps shall be tested in accordance with API 675,
DATE ___________ Project Specifications, testing requirement form 175-
DATE _____________
BY: ______________
VERIFICATION
Sheets.
EDSD
(DCC)NO. _______________________________
REVISION CERTIFICATE
MATERIAL REQUISITION DWG.TYPE PLANT .NO INDEX DRAWING NO. SHT. NO. REV. NO.
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
PMT
MWK
compliance
SBK
``
form 175-341900.
REV. NO.
DATE 2-MAR-22
Free access to the manufacturing plants for the
CERTIFIED
BUYER/COMPANY inspectors or nominated
MWK
DATE 2-MARN-22
representative.
CONSTRUCTION
AGENCY
4.7 Final Inspection
________________
DATE ___________
DATE _____________
CONTROL NUMBER
BY: ______________
Exclusions
VERIFICATION
EDSD
The following are out of SUPPLIERs work scope unless otherwise stated in
this Material Requisition:
(DCC)NO. _______________________________
REVISION CERTIFICATE
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
PMT
MWK
``
2-MAR-22
DATE
REV. NO.
DISCIPLINE
ENGINEER
SBK
DATE 2-MAR-22_
ENGINEERING
MANAGER
JHK
DATE 2-MAR-22
CERTIFIED
MWK
DATE 2-MARN-22
CONSTRUCTION
AGENCY
________________
DATE ___________
OPERATIONS
________
DATE ___________
DATE _____________
CONTROL NUMBER
BY: ______________
VERIFICATION
EDSD
APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV. NO. _____A_____
(DCC)NO. _______________________________
REVISION CERTIFICATE
MATERIAL REQUISITION DWG.TYPE PLANT .NO INDEX DRAWING NO. SHT. NO. REV. NO.
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
PMT
MWK
SUPPLIER shall state list all clarifications and deviations from this Material Requisition
SBK
and referenced Standards, Specifications, Forms, Drawings and Codes in the following. If
no exception is taken from a specific document, then SUPPLIER is deemed by BUYER /
COMPANY to be in full compliance with that document.
If the bid is fully compliant, SUPPLIER shall submit the list marked “NO DEVIATIONS”.
No deviations from the requirements of this Material Requisition are allowed except those
DESCRIPTION
Conclusion
. References (C or D) Requirements Proposed Reasoning /
Clarifications Justification
/ Deviations
1
2
JO/EWO
``
3
4
2-MAR-22
DATE
5
REV. NO.
DISCIPLINE
ENGINEER
SBK
DATE 2-MAR-22_
ENGINEERING
MANAGER
JHK
DATE 2-MAR-22
CERTIFIED
The above list shall be submitted with the quotation, using the attached form in this
Material Requisition.
MWK
DATE 2-MARN-22
.
CONSTRUCTION
AGENCY
________________
DATE ___________
OPERATIONS
________
DATE ___________
DATE _____________
CONTROL NUMBER
BY: ______________
VERIFICATION
EDSD
APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV. NO. _____A_____
(DCC)NO. _______________________________
REVISION CERTIFICATE
MATERIAL REQUISITION DWG.TYPE PLANT .NO INDEX DRAWING NO. SHT. NO. REV. NO.
MWK
A 2-MAR-22 10-14329-0003 ISSUED FOR REVIEW SBK MWK
JHK
OF THIS DRAWING IS COVERED, FOR ALL
SBK
APPROVAL/CERTIFICATION REQUIREMENTS, CONTROL NUMBER
AGENCY
________
DATE 2-MAR-22
MANAGER
ENGINEER
CERTIFIED
DISCIPLINE
DATE 2-MAR-22_
BY DRAWING COMPLETION CERTIFICATE BY: ______________
DATE 2-MARN-22
OPERATIONS
ENGINEERING
CONSTRUCTION
DATE ___________
DATE ___________
________________
(DCC)NO. _______________________________
DATE _____________
``
JAFUARAH
Saudi Aramco 2616-ENG (10/2002)
MATERIAL REQUISITION
SAUDI ARABIA
SECTION 11. QA/QC REQUIREMENT
861
PLANT .NO
Refer to the QA-QC Requirements attached in Section 11.
U
INDEX
2
SAUDI ARABIAN OIL COMPANY
JO / EWO: 10-14329-0003
DRAWING NO.
TE-419843
A
REV. NO.
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
Saudi Aramco 2616-ENG (10/2002)
OPRNS
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
PMT
ENG’G CERT
MWK
SUPPLIER shall provide separate quotations and relevant list of spare parts
according to project requirements and definitions here below listed.
Start-Up Spare Parts are parts or components required during construction, pre-
commissioning, and commissioning. SUPPLIER shall provide the Start-Up Spare
Parts associated with all SUPPLIER-furnished Materials. SUPPLIER shall provide
for BUYER / COMPANY’s Approval list with full details of Start-Up Spare Parts to
10-14329-0003 ISSUED FOR REVIEW
SUPPLIER shall provide the List of Start-Up Spare Parts with bid reply.
JO/EWO
Operating Spare Parts are spare parts or components that are required for
continuous operation of the plant, equipment, or system after commissioning of the
2-MAR-22
DATE
equipment and capital spare parts, if any. SUPPLIER shall provide for BUYER /
COMPANY’s Approval all Operating Spare Parts required data as stated in SAEP-
REV. NO.
3101.
DISCIPLINE
ENGINEER
SUPPLIER shall provide the List of Operating Spare Parts with bid reply.
SBK
DATE 2-MAR-22_
ENGINEERING
MANAGER
12.3 OPERATING MATERIALS (OPTIONAL)
JHK
DATE 2-MAR-22
CERTIFIED
Operating Materials are consumable materials that are required for the continuous
operation of the equipment and are consumed in the normal course of operations
MWK
and, therefore, require periodic replenishment. SUPPLIER shall supply all required
DATE 2-MARN-22
quantities of chemicals, filtration materials, lubricants, desiccants, industrial gases,
CONSTRUCTION emulsifiers, batteries, transformer oils, and any other catalysts, operating fluids,
AGENCY
consumable, and materials required for the initial charge, pre-commissioning and
________________
DATE ___________
Start-Up, and commissioning of the equipment. SUPPLIER shall also provide a
forecast of the initial charge and Start-Up quantities of all items referenced in this
OPERATIONS
Paragraph to BUYER. The forecast shall include quantities expected during Start-Up
________
and normal maximum and minimum operating conditions as well as during summer
DATE ___________
and winter operating conditions, and any other limiting conditions.
DATE _____________
CONTROL NUMBER
BY: ______________
SUPPLIER shall provide the List of Operating Materials with bid reply.
VERIFICATION
EDSD
(DCC)NO. _______________________________
SUPPLIER shall comply with SPDP requirements as per SAEP-3101 Appendix C& D.
MATERIAL REQUISITION DWG.TYPE PLANT .NO INDEX DRAWING NO. SHT. NO. REV. NO.
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
PMT
MWK
SUPPLIER shall be responsible and shall ensure that the requirements of SAEP-
DESCRIPTION
3101, Appendix C & D are passed to SUB-SUPPLIERS and included in the PO for
SUB-SUPPLIER compliance. SUPPLIER shall be informed of COMPANY lessons
learned where most of the delays in the final approval of SPDP packages are due
to:
10-14329-0003 ISSUED FOR REVIEW
delivery of SPDP and ensure that final payment is linked to the final submittal and
A
MWK
12.5 SPECIAL TOOLS
DATE 2-MARN-22
SUPPLIER shall provide any special tools required for installation, field-testing,
CONSTRUCTION
AGENCY
commissioning, operation or maintenance / overhauling of the whole equipment
________________
supplied, including all auxiliaries, if required.
DATE ___________
SUPPLIER shall provide the List of Special Tools with bid reply. If any category
OPERATIONS
doesn’t apply, SUPPLIER shall provide the confirmation statement.
________
DATE ___________
DATE _____________
CONTROL NUMBER
BY: ______________
VERIFICATION
EDSD
APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV. NO. _____A_____
(DCC)NO. _______________________________
REVISION CERTIFICATE
MATERIAL REQUISITION DWG.TYPE PLANT .NO INDEX DRAWING NO. SHT. NO. REV. NO.
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
PMT
ENG’G CERT
MWK
This section defines the scope of documentation and issue purpose for documents
to be provided by SUPPLIER as a minimum.
SUPPLIER shall provide all documentation listed in VDR attached in folder
DESCRIPTION
SUPPLIER shall properly check and confirm Calendar Weeks stated in Non
``
DISCIPLINE
13.2 DRAWING AND DOCUMENTS REQUIREMENT
ENGINEER
SBK SUPPLIER shall supply all necessary drawings, calculations and procedures in the
DATE 2-MAR-22_ quantities specified in SUPPLIER DOCUMENT REQUIREMENTS SCHEDULE.
ENGINEERING
MANAGER
The following documents shall be submitted with the quotation, as a minimum:
JHK
DATE 2-MAR-22
- Deviation & Clarification List
CERTIFIED
- Experience List for similar service
MWK
DATE 2-MARN-22
- Equipment Leaflet / Catalogue
- Equipment List with Specification including Auxiliary Items
CONSTRUCTION
AGENCY
________________
- Equipment Data Sheets and Performance Curve including Auxiliary Equipment
DATE ___________
- General Arrangement Drawing including Loading Data and Nozzle Location
OPERATIONS
- Package Layout Drawing (Plot Plan), if required
________
DATE ___________ - Piping and Instrument Diagram & Process Flow Diagram
DATE _____________
CONTROL NUMBER
BY: ______________
(DCC)NO. _______________________________
MATERIAL REQUISITION DWG.TYPE PLANT .NO INDEX DRAWING NO. SHT. NO. REV. NO.
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
PMT
MWK
SBK
DATE 2-MAR-22_
ENGINEERING
MANAGER
JHK
DATE 2-MAR-22
CERTIFIED
MWK
DATE 2-MARN-22
CONSTRUCTION
AGENCY
________________
DATE ___________
OPERATIONS
________
DATE ___________
DATE _____________
CONTROL NUMBER
BY: ______________
VERIFICATION
EDSD
APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV. NO. _____A_____
(DCC)NO. _______________________________
REVISION CERTIFICATE
MATERIAL REQUISITION DWG.TYPE PLANT .NO INDEX DRAWING NO. SHT. NO. REV. NO.
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
PMT
ENG’G CERT
MWK
All drawings, datasheets, certificates, etc., supplied by SUPPLIER shall show the
following information:
10-14329-0003 ISSUED FOR REVIEW
BUYER’s Name
BUYER’s PURCAHSE ORDER Number
BUYER’s Line Item Number
BUYER’s Job Order Number
BUYER’s Plant Number
JO/EWO
DISCIPLINE
All drawings larger than 8.5 x 11 inch shall be folded and inserted in individual 8.5 x
ENGINEER 11 inch Manila pockets which shall have standard three-ring side punching for
SBK insertion in the binders. Binders shall be three-ring type and lettered to how the
DATE 2-MAR-22_ project title and location.
ENGINEERING
MANAGER
SUPPLIER shall prepare a transmittal cover letter identifying all NMR submissions to
JHK
BUYER with the following: Identifying NMR Sub-Item Number of the attached NMR
DATE 2-MAR-22
CERTIFIED
form(s) (i.e. 601.1; 602.1; 603.1 and etc.). Also Provide the NMR form number and
title and the number of copies. Failure to comply with this basic requirement shall
represent a “SUPPLIER’s error” and a “delivery delay” and shall be subject to
MWK
DATE 2-MARN-22
Remedies as advised by BUYER.
CONSTRUCTION
AGENCY
________________
In case of any conflict between the requirements of this Material Requisition and the
DATE ___________
attached specifications or data sheet(s), such information shall be immediately
brought to BUYER’s attention for resolution.
OPERATIONS
________
SUPPLIER shall submit to BUYER a proposed fabrication schedule within fifteen (15)
DATE ___________
working days after the award of PURCHASE ORDER. This schedule shall be subject
DATE _____________
to BUYER’s approval.
CONTROL NUMBER
BY: ______________
VERIFICATION
EDSD
The items included in this Material Requisition are subject to inspection by BUYER’s
inspector or his designated representative in accordance with inspection
requirements form(s) SA-175.
APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV. NO. _____A_____
(DCC)NO. _______________________________
SUPPLIER shall notify BUYER at least fifteen (15) days before the material is ready
REVISION CERTIFICATE
for final inspection. The material shall not be shipped until an inspection release has
been obtained, indicating that the material complies with all applicable specifications.
MATERIAL REQUISITION DWG.TYPE PLANT .NO INDEX DRAWING NO. SHT. NO. REV. NO.
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
PMT
SUPPLIER shall mark each shipping crate with PURCHASE ORDER number, and
ENG’G CERT
MWK
line item number(s), using 50.8mm(2inch) high painted letters. Materials shall also be
marked with PURCHASE ORDER number/line item number(s).
SBK
Any design changes necessary or desired by SUPPLIER which will affect this this
Material Requisition and/or specifications, drawings, etc. shall be brought to the
BUYER’s attention for his written approval prior to proceeding with the work.
the Contractor’s Vendor Data Submittal Procedure and the specific marking/stamping
requirements of the NMR 602 technical specification form.
SUPPLIER is required to submit Spare Parts Data Package (SPDP), as per Section
12 of this MR and as per SAEP-3101, appendix C and D.
JO/EWO
SUPPLIER shall include in his quote the prices of all the Spare Parts.
``
SUPPLIER shall provide original manufacturer source information for all materials
2-MAR-22
DATE
and spare parts supplied on each PURCHASE ORDER including, but not limit to,
manufacturer’s name, address, sales order number, sales contact name, telephone
REV. NO.
DISCIPLINE
ENGINEER
Spare parts shall be separately packed with marking. Spare Parts check and
SBK
verification shall be part of the final Packing/Crating inspection to ensure compliance
DATE 2-MAR-22_
ENGINEERING
prior to shipment of materials.
MANAGER
JHK Nonmaterial Requirement (NMR item 601,602 and 603 on SAUDI ARAMCO 7900
DATE 2-MAR-22 series Forms) are an integral Part of this requirement as are the complete spare parts
CERTIFIED
package as such, notwithstanding the terms of payment provisions in the applicable
MWK conditions of PURCHASE ORDER price may be withheld until all non-material
DATE 2-MARN-22 requirements and spare parts data packages are delivered and accepted by BUYER.
CONSTRUCTION
AGENCY Material delivery shall not be considered complete until two (2) complete original sets
________________ and one (1) electronic copy of SUPPLIER’s Equipment Operating Instructions and
DATE ___________ Equipment Maintenance Manuals have been transmitted to BUYER and receipt of
OPERATIONS instructions and Manuals has been acknowledge by BUYER.
________
DATE ___________ All correspondence, specification, drawing, or other papers pertaining to procurement
shall bear the following reference:
DATE _____________
CONTROL NUMBER
BY: ______________
VERIFICATION
EDSD
(DCC)NO. _______________________________
REVISION CERTIFICATE
MATERIAL REQUISITION DWG.TYPE PLANT .NO INDEX DRAWING NO. SHT. NO. REV. NO.
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
PMT
MWK
PDF files and Microstation (with Autosacs) files. (Drawing template and Microstation
``
SUPPLIER and BUYER understand that BUYER is contracting with SUPPLIER for
A
DISCIPLINE
the purchase of goods hereunder for ultimate transfer to, and use by, the Saudi
ENGINEER Arabian Oil Company (SAUDI ARAMCO) or its designee in Saudi Arabia. Therefore,
SBK SUPPLIER agrees that, in any event, all rights of BUYER for any failure to meet
DATE 2-MAR-22_ specifications or for any other breach of warranty shall run to the benefit of and be
ENGINEERING
MANAGER
fully enforceable by SAUDI ARAMCO.
JHK
Standard Warranty: period and terms i.e. 12 months from Operations or 18 months
DATE 2-MAR-22
CERTIFIED
from delivery. Also SUPPLIER shall indicate the start and end dates for standard
warranty.
MWK
DATE 2-MARN-22
PREMIUM WARRANTY - (Contract Schedule A, paragraph 10.4) SUPPLIER shall
CONSTRUCTION indicate if they provide PREMIUM WARRANTY to cover the period beyond
CONTACTOR’s Warranty obligations (MCC + 12 months). SUPPLIER shall provide
AGENCY
________________
DATE ___________
premium warranty period and term and cost to BUYER for COMPANY approval.
________
avoid confusion and ensure transparency.
DATE ___________
BY: ______________
VERIFICATION
EDSD
(DCC)NO. _______________________________
c) Pricing for specific training courses outside the Kingdom of Saudi Arabia
REVISION CERTIFICATE
MATERIAL REQUISITION DWG.TYPE PLANT .NO INDEX DRAWING NO. SHT. NO. REV. NO.
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
PMT
ENG’G CERT
MWK
SUPPLIER shall ensure that all equipment and materials are designed and packed for transit
to site without damage and in accordance with the requirements of the documents listed in
Section 8.
SUPPLIER shall refer to packing specifications as follows;
Document No. Description Rev
DESCRIPTION
``
2-MAR-22
DATE
REV. NO.
DISCIPLINE
ENGINEER
SBK
DATE 2-MAR-22_
ENGINEERING
MANAGER
JHK
DATE 2-MAR-22
CERTIFIED
MWK
DATE 2-MARN-22
CONSTRUCTION
AGENCY
________________
DATE ___________
OPERATIONS
________
DATE ___________
DATE _____________
CONTROL NUMBER
BY: ______________
VERIFICATION
EDSD
APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV. NO. _____A_____
(DCC)NO. _______________________________
REVISION CERTIFICATE
MATERIAL REQUISITION DWG.TYPE PLANT .NO INDEX DRAWING NO. SHT. NO. REV. NO.