Professional Documents
Culture Documents
DCN 2724 Supplier Evaluation Survey
DCN 2724 Supplier Evaluation Survey
DCN 2724 Supplier Evaluation Survey
Visit Purpose
Quality Level Up Site Quality Assessment
Emergency Support Technical review
Mass
Production PCR Evaluation Hydraulic Cleanliness
Supplier Development Part Readiness
Supplier Process Audit HVPT
Attendees Circulation
Name Company Position Name Company Position
General Comments:
Conclusion:
Future Requests:
Status Rank
Item # Detailed Problems Identified Corrective Action Plan Owner / Responsibility Due date 1,2,3,4 ABC
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
70%-79% & no zero's on Key requirements = Restricted from additional sourcing until effective improvement plan is implemented Assessment Score
< 70% is recommended Not to source without an agreed improvement plan between Hyster-Yale Group Procurement / SQE and the
Supplier.
Defined Executed
Advanced Quality Planning 0% 0% Comment
1 Project schedule should cover 1. Sourcing 2. Program Definition 3.Product Design 4. Process Design 5. DV &
PV 6. Revision / CAPA.
2 A drawing review process should exist to confirm dimensional, material, functional and reliability are clearly
defined for the product.
3 Production readiness of supplied parts should be tracked as a part of overall readiness for completed
assembly production.
4 A process should be in place to identify and communicate Critical to Quality characteristics for control by
the supplier and/or receiving.
5 Control plans, DFMEA's, FMEA's should be developed to identify process / product characteristics to be
controlled.
6 A Part Approval or PPAP equivalent process should be in place to ensure compliance, of supplied parts, to
documented requirements.
7 Completed product validation should include applicable reliability, durability or regulatory requirements
i.e.... UL, EU, etc...
8 A system should be in place to identify, register and follow-up on open issues through the entire
development process.
9 Status reports should be available to show status of tooling, equipment, "runoff" approvals and Mfg.
Instruction readiness.
10 Pre-HVPT, HVPT trails and Production runs must report both acceptable and non-conforming product to
prove capacity and quality requirements can be met.
11 A process should be in place to ensure packaging requirements are understood so that quality of the
product is maintained to point of use.
Incoming Supplied Parts 0% 0%
12 Incoming product should have records proving compliance provided by the supplier or a receiving
inspection system.
13 Suspect parts must be clearly identified and segregated from approved / accepted parts.
14 Supplier should have a system to identify parts requiring inspection or containment prior to be used in
production.
15 Company should have a corrective action system to assure corrective action is effective and should prevent
recurrence.
16 A system in place to manage changes with suppliers and customers. (Process Change or Engineering
Change system).
17 Supplier quality performance should be measured against a target which supports the concept of
continuous improvement.
18 A supplier improvement program should include onsite reviews, improvement targets, incentives and
repercussions based on performance.
Training 0% 0%
19 The training program should cover all production processes.
20 The training program should ensure operators can demonstrate process competency before released to
production on their own.
21 The program should ensure training if any changes or modifications occur in the production process
through a ECN, PCR or Corrective Action.
22 Training / skill status of all operators should be easily accessible for purpose of managing operator
placement in the production process.
23 Expiration dates of certification, for special skills (welding, machining, etc..), are tracked for compliance.
Manufacturing Process 0% 0%
24 List the applicable environmental regulation(s) or requirement(s).
24a Records should prove any applicable local environmental rules & regulations are observed and in
compliance?
25 Applicable fool proof/poka yoke's, fixtures and functional checks should be in place to ensure control of
Key/CTQ characteristics.
26 Machine start up instructions should be in use and approved by management.
27 Upper and lower operating ranges should be specified for variable equipment controls such as for welding,
gas, voltage....
28 Equipment with "key" variable outputs (torque, vibration/leak/hypot test…) should have alarms to indicate
out of range conditions.
29 All production and temporary work instructions should be clear, easy to follow, easily accessible, cover
critical to quality and safety points.
30 5S rules should be applied throughout the production process. SORT - STRAIGHTEN - SHINE - STANDARDIZE
- SUSTAIN.
31 Material is presented and organized in accordance with lean manufacturing rules. Minimize travel and
support sequence of events.
32 A process exists and is in use for employees to provide feedback and to make improvements to their work
areas.
33 Lot traceability in place for key parts and processes for identification, if required, at the customer in the
event of a non-conformance.
34 Key or Critical to Quality characteristics should be identified & capable to 1.33 CPk or be checked 100% prior
to shipping.
35 Inspection equipment should be proven capable to inspect the given feature or function of the product
(10x more accurate than the drawing tolerance)
36 Company should have a calibration/verification program for inspection and process tools to assure their
accuracy. (Gages, torque, etc..)
37 First piece inspection in place to authorize shift process setup and process audits in place to ensure
compliance to requirements.
39 Procedures should ensure repair, rework and inspection of suspect parts so only parts that meet
requirements are shipped.
40 Supplier must clearly segregate and identify completed product approved for shipment from suspect or
incomplete product.
41 Monitors equipment/tool downtime and demonstrates a preventive maintenance & improvement plan for
equipment, tooling and fixtures
42 Methods are in place to trigger replenishment of parts and material to support production and on time
delivery.
43 A system should be in place to alert production of customer non-conformances and necessary actions to
ensure control.
44 A method should be in place to register non-conformances for corrective action with the manufacturing
process.
45 Non-conformance root cause analysis should address Why Made and Why Shipped to the "5th Why".
(Systemic R/C & CAPA & consider 4 M's)
46 Part data retention is in line with part or system complexity (bracket vs. valve or display).
47 Abnormal conditions or deviations to processes should be tracked to ensure permanent corrective action in
a timely manner.
Customer (Internal and External) Satisfaction 0% 0%
48 Targets should be in alignment with the customers expectations per latest ASE. Quality (PPM), Delivery (On
time), Warranty(%).
49 An organization structure and process should be in place to register and respond to non-conformance
reports from the customer for Warranty and Quality.
50 A process should be in place to manage the receipt and response to warranty claims even if no fault is
found per the MSA.
Overall Score 0% 0%
12 0 - No R/I system in place 1 - Informal / Inconsistent 3 - Inspected per a plan 9 - Inspected per plan and documented with regular reviews of performance
13 0 - No system in place 1 - Segregated but not identified 3 - Identified, but with no designated location 9 - Parts are segregated/identified, with designated location
14 0 - No system exits 1 - Thru email/verbal 3 - Basic Spreadsheet 9 - Parts are identified as part of inventory receipt / management system
15 0 - No system exits 1 - Basic Spreadsheet 3 - Organized process such as 7-D, 8-D, DMAIC exists 9 - Centralized of list of records is maintained for team follow-up
16 0 - No process 1 - Informal / Inconsistent 3 - Communicate to customer only 9 - Process in place to facilitate communication from suppliers and to customers
17 0 - No tracking system 1 - Tracked 3 - Improvement actions are documented 9 - Continuous improvement toward or in alignment with the target is documented
18 0 - No program 1 - Informal / Inconsistent 3 - Includes onsite audits but accountable team not in place 9 - Formalized with accountable team in place
19 0 - No program 1 - Informal / Inconsistent 3 - Formal program exists, but does not cover all the processes 9 - Formal training exists, and covers all processes
20 0 - No Evaluation 1 - Evaluation is informal & inconsistent 3 - Formal evaluation but not specific for each process 9 - Formal evaluation exists, and specific to the process
21 0 - No system 1 - Informal & inconsistent 3 - Process exists but no closed loop to monitor completion 9 - Process in place with closed loop to monitor completion
22 0 - No tracking 1 - Records available but not easily accessible 3 - Records easily accessible, but not up to date/incomplete 9 - Records are up to date and easily accessible
23 0 - No tracking 1 - Records available but not easily accessible 3 - Records easily accessible, but not up to date/incomplete 9 - Records are up to date and easily accessible
24
24a 0 - No tracking 1 - Records available but not easily accessible 3 - Records easily accessible, but not up to date/incomplete 9 - Records are up to date and easily accessible
25 0 - No poka yoke's in place 1 - Informal & inconsistent 3 - Poka yoke in place, but not validated regularly 9 - Poka yoke in place & validated regularly
26 0 -No instructions 1-Informal & inconsistent 3-Instructions available but not approved by Mgmt/Rev Controlled 9-Instructions available & approved by Mgmt/Rev Controlled
27 0 - No operation ranges defined 1- Informal inconsistent 3- Marked at the equipment/gage 9 - Defined in a work instruction or machine setup and at equipment/gage
28 0 - No alarms 1 - visual only (passive) 3 - visual and audible (passive) 9 - Alarm is "active". Process cannot proceed w/o manual override or intervention.
29 0 - No Work Instructions 1 - Written only 3 - Also includes Pictorial & SOE 9- Also includes key / CTQ & Safety information
30 0 - Disorganized, not clean, no 5-S in place 1 - semi organized, semi clean, no 5S system 3 - 5-S system, mostly organized & clean 9 - 5-S fully implemented & followed
31 0 - No lean rules in place 1 - Evidence of some lean rules in place 3 - Formal program followed in most areas 9 - Formal program implemented plant wide
32 0 - No process 1 - In place, but not formalized 3 - In place, formalized, but not followed entirely 9 - In place, formalized, and followed thoroughly
33 0 - No lot traceability 1 - Production traceable to production week or month 3 - Production traceable to a given day or shift 9 - Production traceable to a shift & operator
34 0 - No CTQ's tracked 1 - Some CTQ's, but not capable or 100% inspected 3 - CTQ system, but not all capable or 100% inspected 9- CTQ system, and all are capable or 100% inspected
35 0 - No inspection equip/not capable 1 - Some equip available but not fully capable 3 - Most equipment available & fully capable 9 - All equip available & fully capable
36 0 - No process 1 - Process in place, but not formal 3 - Formalized, but not followed consistently 9 - Formalized, and evidence indicates 100% conformance
37 0 - No process in place 1 -Informal audit, no checklist 3 - Basic checklist utilized 9 - Process checked to be in compliance with work instructions/process setup instructions
38 0 - No inspections performed 1 - Visual only 3 Inspections include dimensional checks 9 Inspections also include functional checks which verify fit / function for the truck
39 0 - No procedure in place 1 - Visual only 3 Inspections include dimensional checks 9 Inspections also include functional checks which verify fit / function for the truck
40 0 - No system in place 1 - Segregated but not identified 3 - Identified, but with no designated location 9 - Parts are segregated/identified, with designated location
41 0 - Not monitored 1 - Tracked informally / decentralized 3 - Tracked and prioritized with P.M. plan 9 - PM plan in place with evidence of improvement actions taken
42 0 - Product is "pushed", not pulled 1 - Manual planning in place based on customer orders 3 - Manual planning covers 6 week L/T 9 - MRP + Kanban system in place
43 0 - No system 1 - System involves only phone or email 3 - System includes written notice 9 - Events are registered in Corrective Action system with status reporting
44 0 - No system exits 1 - Basic Spreadsheet 3 - Organized process such as 7-D, 8-D, DMAIC exists 9 - Centralized of list of records is maintained for team follow-up
45 0 - No system 1 - Only "why shipped" addressed 3 - "Why made" also addressed 9 - Clear 5 why established to identify system /business process failure & verification
46 0- No data collection 1- System exists but no evidence of use 3- System exists with evidence of use 9- System will support data crosscheck to suppliers lot date or serial #
47 0 - No system 1 - Temporary work instruction 3 - Instruction with training 9 - Process expiration dates and / or Qty established with evidence of closure
48 0- No targets 1- Targets exist, but not aligned with customer's expectations 3- Some targets meting customer's expectations 9- All targets meeting customer's expectations
49 0 - No system exits 1 - Basic Spreadsheet 3 - Organized process such as 7-D, 8-D, DMAIC exists 9 - Centralized of list of records is maintained for team follow-up
50 0 - No system 1 - Only pas /fail reports upon request 3 -Test criteria and data results available only by request 9 - Test criteria and results issued to customer proactively
15a Please use Process Audit Worksheet to fill in details to this question.
Active and up-to-date system used to identify parts requiring inspection or containment
16 prior to being released to inventory ###
Supplied part corrective action system active and up-to-date to ensure corrective action is
17 effective and will prevent recurrence. ###
A system to manage changes with suppliers. (Process Change or Engineering Change
18 system) ###
Please use Process Audit Worksheet to fill in details to this question.
9
Methods should be in place to ensure final product is labeled correctly. Confirm
19 mislabeling rejections identified in last 6 months.
19a Please use Process Audit Worksheet to fill in details to this question.
Rust Preventative Oil: (only applies to rust preventative oil that will be exposed to truck hydraulic system) Score Comment
22 Is the cleanliness of rust preventative oil monitored? ###
Is cleanliness of rust preventative oil consistent with Hyster-Yale Group part cleanliness requirements? ###
23
Section Total 0.0
Total Possible 0
Overall Section Rating 0%
Plant Environment / Product Cleanliness:
Cleanliness of component storage: (Contamination= particle/corrosion/moisture) Score Comment
24 Containers are free from contamination. ###
25 Product is protected from contamination and damage. ###
26 Storage rack is clean and well organized. ###
27 Storage rack clearly identified for product location. ###
Cleanliness of product point of use (assembly/finish manufacturing area). Score Comment
28 Containers in staging area clean and well organized. ###
29 Product is protected from contamination to point of use. ###
30 Product is washed immediately prior to assy, or stored in sealed containers between wash and assy. ###
Is there an operator training program for process cleanliness requirements and tracking of certified ###
31 operators?
Product handling during assembly / manufacturing is free of contamination (incl. equipment, clothes, ###
32 gloves).
Assy work benches, tooling and area is clean are well maintained with defined work instructions to reflect ###
33 this.
34 Is lighting adequate for operator to review parts / process? ###
35 Lubrication fluids required for assembly purposes are clean and stored in clean condition. ###
Cleanliness of end product. (handling and storage) Score Comment
Packaging provides protection from damage and contamination during storage and shipment to Hyster- ###
36 Yale Group.
37 All 'open points' of part or assembled are protected by sealing plugs, or properly bagged. ###
38 Sealing plugs used are a good fit and not easily knocked off during shipment and storage. ###
39 Sealing plugs and bags are stored in locations free from contamination. ###
Section Total 0.0
Total Possible 0
Overall Section Rating 0%
15 Test procedure should be controlled, current and reflect fully the complete test procedures
16 If possible review actual test being conducted, or have operator describe test, and compare against procedures
17 The suppliers procedure should define a schedule for oil tests
18 The supplier's test schedule should be consistent with the level of control they have, and based on history of recorded results
19 Test results recorded, stored and available for review
20 K158 notes that test oil must be 2 ISO codes cleaner than assembly drawing requirement, or Q702 table 1a default.
21 Reaction plan must cover correction of root cause of contamination, and include containment of recently manufactured components.
22 Supplier should have means of knowing cleanliness levels of rust preventative oil
23 Rust preventative oil cleanliness levels should be in line with test oil cleanliness requirements.
Tolerance Stack Up Request Design Tolerance Stack Up Calculations when criteria is being challenged
24 Utilize SQE Tolerance Stack Up Calculator when above is not available
25 Key characteristics Missing, appropriate and measurable?
26 Parts list / BOM clear Need matrix to show or # called out
27 Fit and finish criteria Reference HCE-151 for zone cross check to part use
28 Torque specified Confirm torque requirements are clear (Loctite?) Ref. ES-1107 / HC-712
CASTING
Casting: Appearance
29 Surface finish (smoothness) Refer to SQM CQCD
30 Paint /coat HCE-145 & 148
31 No-draft zone
32 No-grinding area (grinding direction)
Identification
(Casting
33 Letterlettering)
size, type, location & part no.
34 Lettering raised or recessed Consider needs of mating parts
35 Foundry symbol Mold in information clear
36 Heat code / lot traceability
Specific dimension requirements for casting
37 Flatness where applicable
38 Datum's from machined surfaces When possible & Ensure dimensions are clear and process is capable
39 Casting datum matches process Supplier check method & fixtures match HYG Welding or Assembly Datum Scheme
40 Specifying std. Tolerance for Casting surface & welding equipment
41 Fillets, corners , drafts, radius Pre-machine surface stock >/= 3mm to ensure complete machining
42 Draft Angle + Tolerance for Weld Surfaces Is Max Draft Angle + Max Tolerance suitable for weld gap & can specified process control
43 Parting line requirements Review for high stress areas and ensure dimensions are clear & tooling is capable
Material
44 Material specification Must clearly specify both Chemical and Mechanical properties (Ref: HC-27 as example)
45 Electroplated Parts HC-404/HC-411 Confirm hardness of individual parts. If >/=34 HRC then negotiate for alternate coating.
46 Baking
Test bartimes in 411 are CTQ
location >/=34 HRDChigh
To consider or 12.9 Hardware
stress = No
area, and electroplating
casting techniques& HC-412 should be specified
47 Hardness reading location Ensure accessibility
48 Metallographic examination location Away from gates & risers
Soundness level vs specified location
49 Soundness level Refer to ASTM E186 / E280, CQCD and HC-49 (example)
Testing method According to material type, casting techniques (proposed gates, riser location, centerline, etc) &
50 part Fit/Function to determine if critical area needs to be specified.
Plastics
Roto molding
51 Process tolerance is 0.5% of dimension Confirm any tolerance requirements on dimensions, notes or title block
52 Flatness tolerance is 1% of dimension
53 Tank Designed for Flushing (K144) Verify tank can gravity drain without components or ledges that prevent flushing
Injection Molding
54 Sink concerns Rib wall thickness is </= to 1/2 of wall
55 Plastic stress / whitening concerns Are attach points supported (gussets) not stand alone
76 HCE-112 electrical cable (GXL) Review HCE-112 for temperature critical (-60 to 270f) cable
77 HCE-130 electrical cable (TXL) Low voltage cable (60 volts or less) must meet SAE J1128 and UL 558/583 requirements
78 Water / dust ingression Consider impact and need for specification (ref IEC 60034-5) IP grade
79 Pin out and labeling of circuit Clear on drawing and able to cross check to schematic
80 Reference information: ES 1353 Electrical Design Guide, ES 1352 symbology, ES 1351 glossary, ES 1356 drawing
81 ESD Protection (Electrostatic Discharge) Example: 8Kv at contact. Consider protection requirements in Mfg. Process & Packaging.
82 EMC (Electromagnetic Compatibility) Input & output filtering specified to prevent electrical (CAN) noise. Ref EN12895
ENGINE
Warrantable Durability Crosscheck PRD Durability Requirements to MSA T&C so team understands Test Expectations vs.
83 Actual Warranty Period
84 HYG Unique Part Design Cross check fit & clearances to mating parts against OEM original part design
85 UL Traceability Confirm UL required components have UL certified source, components, labels, etc…
Fluid Fill & Fluid Drain Confirm what "Full" and "Drained" equal against plant expectations.
86 Example: Oil Full = within top half of hatched area on dipstick window
PERFORMANCE TESTING
Product Requirements Clear on Drawing or PRD.
Development test requirements and Functional part drawings must answer the question - what's it supposed to do, for how long and
87 Operating conditions (e.g. Load, Number of in what conditions?
cycles, pressure range, Temperature range)
noted on Assembly drawing.
Performance requirements, test procedures, P.R.D., or suppliers spec. Is listed on dwg.
88 Emission critical parts or containers Specified as leak free with pressure test (ex: 30KPa pressure)
Leak spec. To be validated to meet des. Requirements - 10CC decay = no leak?
Functional Verification test
89 Production functional test Include details of test / performance requirements to confirm
90 To confirm product quality Function of part or assembly under operating extremes/loaded condition
91 Functional noise
92 Max decibel, vibration, frequency, etc… Electric motors, axles, pumps, etc. Definition and confirmation method
UL REQUIREMENTS
93 Material specification Each component to identify the specified material requirement
94 UL material rating specified Each material specified with the required UL rate (i.e. UL 94 V-0)
95 UL identification marking Specify location of UL marking on part or container/packaging
Note: UL designation may be required if conducting current or When in a high heat area (under
hood) REF. UL 585.
Action list When to create an action Based on experience or audit result create an action when without an action quality is not ensured at a supplier
Item # Give each action a number or subnumber for easy reference
Detailed problem description Describe the issue that requires action and the consequence of no action taken
Owner List relevant problem owners (either at supplier or at Hyster-Yale Group)
Corrective Action Plan Describe a SMART action to resolve the problem
Due date Provide a clear and realistic due date that has been agreed with the supplier, or list as ongoing
Status Status of Corrective action plan (refer to guide above)
Rank Severity of problem (refer to guide above)
Quality System Defined Score how well a certain item is defined or described at a supplier (documented) score each item 9,3,1,0 or n/a based on the guide on top of the sheet.
Assessment
Executed Score how well a certain item is executed or implemented at a supplier (are they actually following the defined processes). Score each item 9,3,1,0 or
n/a based on the guide on top of the sheet.
Comment List any comments relating to each score
Readiness & HVPT Status Score each item based on it's status refer to colour guide above and to the right for each item
Comment List any comments relating to each score
Current status Scored automatically by sheet based on entered scores. Add a comment below on due dates, and outlook based on actions to be taken
SOP Outlook Fill in, based on experience and actions to be taken whether the supplier will be ready for SOP.
Cleanliness Assessment Score Score each item 9,3,1,0 or n/a based on the guide on top of the sheet.
Comment List any comments relating to each score
Final result Scored automatically by sheet based on entered scores.
Technical Assessment Score Score each item 9,3,1,0 or n/a based on the guide on top of the sheet.
Comment List any comments relating to each score
Reaction plan In case of non-conforming scores (must score 9 on applicable items) define a SMART reaction plan. Also list this in the action list
Due date Provide a clear and realistic due date that has been agreed with the supplier.
Hyster-Yale Group Outlook Judge, based on experience whether the reaction plan is acceptable (Green or Red)
Drawing review Result Together with the supplier go through each relevant drawing and judge the completeness, clarity and correctness of the drawing to ensure the
requirements are fully understood with the supplier. If this is not the case, raise this with Engineering at Hyster-Yale Group.
2 If the drawing lists HYG HC and/or HCE specifications record the specification number and revision level of each that you have been issued.
3 Do you have a Process Change or Engineering Change system? If yes please provide document number & copy
Please list the most recent process change you requested from HYG. Process Change is detailed in sub-section 5 of the Supplier Quality Manual.
List the Part number, HYG Process change number, Detail of change and if it has been implemented.
Please list the most recent drawing change (change to Fit, form or function) issued by HYG
List the Part number, Engineering Change Number (ECN), Detail of change and if it has been implemented.
4 Please submit an example of your production work instructions for this part clearly showing that they are revision controlled, identify CTQ's (Critical to
Quality Features) etc.
Checklist questions YES NO
5 Does your production process for this part clearly control all CTQ's (Critical to Quality Features). Please provide examples of how these are controlled,
Poke Yoke, inspection etc. and if a control plan is available please provide a copy. Please also log the number of process steps in your control plan and 1 Was Containment Action taken quickly (within 2 days) to protect the Customer?
the number steps in your control plan that are not being followed.
Did Containment Action check, sort, or rework all local inventory, WIP, finished goods , stock in transit?
6 Are all operators involved in processing this part trained and certified. Please attach a copy of your training matrix showing the status of these 2
operators. Please also record for 4 operators the workstation within the process they work at, their operator number, and confirmation they are 3 Does Containment Action include an interim fix on the direct cause?
trained.
4 Have the interim containment measures been verified to work?
7&8 Are all CTQ's (Critical to Quality Features) identified and documented? Please provide evidence to show how your have identified CTQ's and how you are Does Containment Action give high confidence that the customer will not see the issue, while a long term
measuring and controlling them.
9 Are all the gauges, tools and test equipment used to manufacture this part certified / calibrated, have a unique reference number and logged on
5 action is being developed?
calibration database? Please provide documentation for 3 examples. 6 Has the Containment Action been tested to ensure no additional issues are created?
10 How do you manage reworked parts? Please provide detail for your process to manage rework parts and ensure all CTQ's (Critical to Quality Features),
torques etc. are verified as per certified Production Processes.
Checklist questions YES NO
11 Please review your 2 most recent corrective actions taken for HYG parts and confirm they address why made and why shipped. In each case something Did the Supplier use a formal root cause analysis tool to identity the issue? (Samples of tools above in
must have changed in your process. If you believe the action taken is not effective please state what systemic action you are taking to improve the
corrective action process to ensure robust and effective corrective actions are taken. Please see questions opposite for Containment, Root Cause and 1 red)
Permanent Action as a guideline that you should ask and answer yes to all to ensure you have taken correct steps and actions. 2 Did the root cause identify why the issue happened?
3 Did the root cause identify why the issue was not detected and the parts shipped?
12 Review the CAR's (Corrective Action Report) / ICAM's (Interactive Corrective Action Management) raised by HYG in the last 6 months and record the
quantity that required updates to the Control Plan, the quantity fully implemented, the quantity still outstanding / requiring update and the quantity 4 Has the root cause identified a systemic failure?
that have been updated on the FMEA (Failure Mode & Effect Analysis). 5 Did the investigation reveal a single root cause or were there multiple reasons?
13 Please provide detail of how you monitor equipment / tooling downtime and how this drives improvement. e.g. do you have a Total Preventative
Maintenance (TPM) schedule. Checklist questions YES NO
14 Do you have a 5S program in your production process? If yes please provide details e.g. Audit schedule, audit results and actions, have standards been 1 Does the permanent corrective action eliminate the root cause?
developed. Examples of these 5S steps should be attached. 2 Does the permanent corrective action prevent a recurrence of the issue?
3 Does the permanent corrective action eliminate the root cause?
Incoming Supplied Parts Management 15 Select 4 part numbers you supply HYG and provide Part Approval (PA) information. These 4 parts should be either a part that is used in an HYG assembly
or an individual part you supply HYG. For these parts also provide the current Control Plan (CP) or inspection criteria Initial Sample Inspection Report 4 Can the permanent corrective action be implemented within an acceptable time frame?
(ISIR) as applicable. Also please record if you have rejected any of these 4 part numbers in the last 12 months and if the suppliers corrective action has Has the solution generated new procedures or changed current procedures? If Yes, have these been fully
been adequate.
5 documented, communicated and uploaded into the ICAM?
16 Please provide detail of how you identify parts at your goods receiving that require inspection or rework activity to be conduct prior to being released to 6 Is training required? If yes, have plans been generated?
a stores location. This may be driven by your parts system or a manual process. Please provide examples of how HYG parts have been identified. 7 If a serial number break or date code break is generated has this been captured?
17 Please provide details of how you manage corrective actions with your suppliers. This system should have problem description, root cause, corrective
action at a minimum and also have timelines for each stage. Please also provide detail of how you follow-up on outstanding issues.
18 Do you have a system in place to manage changes with your suppliers? If yes please provide details of how you manage this and a copy of the document
/ clause of your procedure that manages this. Also please log details of the most recent Process change & Engineering change that has been requested
by a supplier and processed by you. If you do not have a recent change for an HYG part please use any part as an example.
Finished Goods Measurement 19 How do you ensure that the product shipped to HYG has been labelled correctly to ensure HYG receive the ordered part and packaged correctly to
ensure the product is preserved during shipping and storage? Have you gained approval for you packaging from HYG? Please log any rejections you have
received from HYG on labelling / packaging of HYG product in the last 6 months.
Follow-up list What requires an action If during the Process Audit you score a question with 0, 1 or 3 then a follow-up action is required
Supplier Name Add the name of your Company
Date Visited Date the Process Audit is being conducted
Item Number Give each action a number or sub number for easy reference
Detailed Problems Identified Describe the issue that requires action and the consequence of no action taken
Assigned to List the action owners (either at supplier or at HYG)
Corrective Action Plan Describe a SMART action to resolve the problem
Agreed Target Implementation Date Provide a clear and realistic due date or list as ongoing
Status Status of Corrective action plan (refer to 'definition of status' guide at top of follow-up list)
Rank Severity of problem (refer to 'Definition of Ranking' guide at top of follow-up list)
Worksheet What is required Please use this worksheet to record all information for each question contained within the Process Audit.
Supporting documentation Any supporting documentation for each question should be converted to pdf and embedded in column T. To embed this documentation into
the worksheet click 'insert', then 'object' and the object box will open. Click 'create from file', 'Browse' and locate the document you wish to
upload. Click on 'Display as icon' and then OK. Ensure you adjust the row height and column width to contain the documents.