The document calculates the lifting requirements for unloading two steel stellings from a truck using a truck mounted crane. It determines that the total erection weight is 0.75 tons based on the weight and number of stellings and lifting gear. It then calculates that the crane's lifting capacity of 1.70 tons at a 7 meter working radius meets the load with a safety factor of 2.27 and an utilization rate of 44.12% which is below the acceptable 75% threshold. Two 5 ton capacity webbing slings and shackles will be used as the lifting devices.
The document calculates the lifting requirements for unloading two steel stellings from a truck using a truck mounted crane. It determines that the total erection weight is 0.75 tons based on the weight and number of stellings and lifting gear. It then calculates that the crane's lifting capacity of 1.70 tons at a 7 meter working radius meets the load with a safety factor of 2.27 and an utilization rate of 44.12% which is below the acceptable 75% threshold. Two 5 ton capacity webbing slings and shackles will be used as the lifting devices.
The document calculates the lifting requirements for unloading two steel stellings from a truck using a truck mounted crane. It determines that the total erection weight is 0.75 tons based on the weight and number of stellings and lifting gear. It then calculates that the crane's lifting capacity of 1.70 tons at a 7 meter working radius meets the load with a safety factor of 2.27 and an utilization rate of 44.12% which is below the acceptable 75% threshold. Two 5 ton capacity webbing slings and shackles will be used as the lifting devices.