ID Task Task Name Duration Start Finish Predecessors

Resource Names
Mode February 11 July 21 January 01 June 11
01/02 03/20 06/05 08/21 11/06 01/22 04/08 06/24
1 KIRKWOOD BULK WATER SUPPLY 218 Mon 23/06/05 Wed 24/04/03
SCHEME; TENDER NO. days?
AW2022/23/23
2 Start 0 days Mon 23/06/05 Mon 23/06/05 06/05
3 Contractual Requirements 5 days Mon 23/06/05 Fri 23/06/09
4 Submission of insurances 1 wk Mon 23/06/05 Fri 23/06/09 2 Khoza Tradings Khoza Tradings
5 Submission and Approval of OHS 1 wk Mon Fri 23/06/09 2 Khoza Tradings Khoza Tradings
File 23/06/05
6 Site handover Meeting 2 days Mon 23/06/12 Tue 23/06/13 5 Client,Engineer Client,Engineer
7 Site Establishment 202 days?Wed 23/06/14 Thu 24/03/21
8 Site camp setup 1 wk Wed 23/06/14Tue 23/06/20 6 Khoza Tradings Khoza Tradings
9 Employment of Labour 6 days Wed 23/06/21Wed 23/06/28 8 Khoza Tradings Khoza Tradings
10 Purchasing of PPE 7 days Thu 23/06/29 Fri 23/07/07 9 Khoza Tradings Khoza Tradings
11 Performing of Medical Tests 5 days Mon 23/07/10 Fri 23/07/14 10 Khoza Tradings Khoza Tradings
12 Signing of Employment Contracts 2 days Mon 23/07/17 Tue 23/07/18 11 Khoza Tradings Khoza Tradings
13 Induction of Employees 2 days Wed 23/07/19Thu 23/07/20 12 Khoza Tradings Khoza Tradings
14 Manufacturing & Erection of 2 wks Fri 23/07/21 Thu 23/08/03 13 Khoza Tradings Khoza Tradings
Project Signboard
15 SECTION 2 192 days?Mon 23/06/26 Tue 24/03/19
16 Construction of 3,0 ml Steel 192 Mon 23/06/26 Tue 24/03/19
Reservoir days?
17 Site Clearance 162 daysMon 23/06/26 Tue 24/02/06
18 Clear & grub of grass, trees1 etc
wk Fri 23/07/21 Thu 23/07/27 2,13 Machines/ Plant Machines/ Plant
19 Earthworks 9 days Fri 23/07/28 Wed 23/08/09
20 Removal of topsoil 1 wk Fri 23/07/28 Thu 23/08/03 18 Machines/ Plant Machines/ Plant
21 Bulk Excavation 1 wk Thu 23/08/03 Wed 23/08/09 20FS-1Machines/
day Plant Machines/ Plant
22 Layerworks 20 days Thu 23/08/10 Wed 23/09/06
23 Importing & laying of G72 material
wks Thu 23/08/10 Wed 23/08/23 2,21 Machines/ Plant,Smooth Roller,Unskilled Labour Machines/ Plant,Smooth Roller,Unskilled Labour
24 Compaction & testing of2G7 wksmaterial
Thu 23/08/24 Wed 23/09/06 23 Laboratory,Push roller Laboratory,Push roller
25 Foundation and / or Ring Beam
50 days Thu 23/09/07 Wed 23/11/15
26 Excavation 2 wks Thu 23/09/07 Wed 23/09/20 24 TLB,Unskilled Labour TLB,Unskilled Labour
27 Casting of blinding 1 wk Thu 23/09/21 Wed 23/09/27 26 Skilled Labour,Unskilled Labour Skilled Labour,Unskilled Labour
28 Fixing of steel reinforcement
2 wks Thu 23/09/28 Wed 23/10/11 27 Skilled Labour,Unskilled Labour Skilled Labour,Unskilled Labour
29 Shuttering of the beam 1 wk Thu 23/10/12 Wed 23/10/18 28 Skilled Labour,Unskilled Labour Skilled Labour,Unskilled Labour
30 Inspection & approval by1 Engineer
wk Thu 23/10/19 Wed 23/10/25 29 Engineer Engineer
31 Casting of concrete 1 wk Thu 23/10/26 Wed 23/11/01 30 Skilled Labour,TLB,Unskilled Labour Skilled Labour,TLB,Unskilled Labour
32 Removal of shuttering 2 wks Thu 23/11/02 Wed 23/11/15 31 Skilled Labour,Unskilled Labour Skilled Labour,Unskilled Labour
33 Erection of Steel Stank 162 daysMon 23/06/26 Tue 24/02/06
34 Allow for ordering, 8 wks Mon 23/06/26 Fri 23/08/18 2
manufacturing and
delivery of the
35 Erection of Steel platform
2 wks Thu 23/11/16 Wed 23/11/29 34,32 Engineer Engineer
36 Erection & Assembling of 3 wks
Steel Tank
Fri 23/11/24 Thu 23/12/14 35FS-4Machines/
days Plant Machines/ Plant

Task Project Summary Inactive Milestone Manual Summary Rollup Deadline

Project: Preliminary Program_ Kir Split External Tasks Inactive Summary Manual Summary Critical
Date: Wed 23/03/01 Milestone External Milestone Manual Task Start-only Critical Split
Summary Inactive Task Duration-only Finish-only Progress

Page 1
ID Task Task Name Duration Start Finish Predecessors
Resource Names
Mode February 11 July 21 January 01 June 11
01/02 03/20 06/05 08/21 11/06 01/22 04/08 06/24
37 Erection of platform & 3 wks Mon 23/12/11 Fri 23/12/29 36FS-4Machines/ Plant Machines/ Plant
External and External days
38 Assembling of inlet & 5 days Mon 24/01/01 Fri 24/01/05 37 Skilled Skilled Labour,Unskilled Labour
Outlet connection Labour,Unskilled
39 Backfilling around the footings
2 wks Mon 24/01/08 Fri 24/01/19 38 Skilled Labour Skilled Labour
40 Installation of External 1 wk Mon 24/01/22 Fri 24/01/26 39
& Internal access
41 Inspection and 7 days Mon 24/01/29 Tue 24/02/06 40 Unskilled Labour Unskilled Labour
approval by Engineer
42 Water Tightness Test & 42 days Mon 24/01/22 Tue 24/03/19
Disinfection
43 Filling of the reservoir with2water
wks Wed 24/02/07 Tue 24/02/20 41 Water Tank Water Tank
44 Testing of water Tightness2 wks Wed 24/02/21 Tue 24/03/05 43 Client,Contractor,Engineer Client,Contractor,Engineer
45 Inspection & approval by 1 wk Wed 24/03/06 Tue 24/03/12 44 Engineer Engineer
Engineer
46 Disinfection of the Tank 3 days Wed 24/03/13 Fri 24/03/15 45 Contractor Contractor
47 Inlet & Outlet Pipework 42 days Mon 24/01/22 Tue 24/03/19
& Appurtances
48 Inlet & outlet pipeline 24 days Mon 24/01/22 Thu 24/02/22
49 Setting out 3 days Mon 24/01/22 Wed 24/01/24 39 Contractor Contractor
50 Excavations for trenches
1 wk Thu 24/01/25 Wed 24/01/31 49 Machines/ Plant Machines/ Plant
51 Trench preparation and 1 wk
shapingMon 24/01/29 Fri 24/02/02 50FS-3Unskilled
days Labour Unskilled Labour
52 Laying of bedding 1 wk Mon 24/02/05 Fri 24/02/09 51 Skilled Labour,Unskilled Labour Skilled Labour,Unskilled Labour
53 Pipelaying 1 wk Mon 24/02/12 Fri 24/02/16 52 Skilled Labour Skilled Labour
54 Backfilling 1 wk Thu 24/02/15 Wed 24/02/21 53FS-2Small
daysMachines,Unskilled Labour Small Machines,Unskilled Labour
55 Density tests 3 days Mon 24/02/19 Wed 24/02/21 54FS-3Laboratory
days Laboratory
56 Approval by Engineer2 days Wed 24/02/21 Thu 24/02/22 55FS-1Engineer
day Engineer
57 Inlet & Outlet Structures 22 days Mon 24/02/19 Tue 24/03/19
58 Inlet Structure 22 days Mon 24/02/19 Tue 24/03/19
59 Excavations 1 wk Mon 24/02/19 Fri 24/02/23 53 Unskilled Labour Unskilled Labour
60 Assembling of valve8 &days
fittings
Mon 24/02/26 Wed 24/03/06 59 Skilled Labour Skilled Labour
61 Brickwork & 1 wk Thu 24/03/07 Wed 24/03/13 60 Skilled Labour Skilled Labour
Placement of
62 Inspection by Engineer
4 days Thu 24/03/14 Tue 24/03/19 61 Engineer Engineer
63 Outlet Structure 15 days Mon 24/02/19 Fri 24/03/08
64 Excavation 3 days Mon 24/02/19 Wed 24/02/21 53 Contractor Contractor
65 Assembling of valve1 &wkfittings
Thu 24/02/22 Wed 24/02/28 64 Skilled Labour,Unskilled Labour Skilled Labour,Unskilled Labour
66 Brickwork & 1 wk Thu 24/02/29 Wed 24/03/06 65 Skilled Labour Skilled Labour
Placement of
67 Approval by Engineer2 days Thu 24/03/07 Fri 24/03/08 66 Engineer Engineer
68 Protection Works 46 days? Mon 24/01/15 Mon 24/03/18
69 Retaining Walls 36 days? Mon 24/01/15 Mon 24/03/04
70 Setting out 6 days Mon 24/01/15 Mon 24/01/22 2 Skilled Labour,Engineer Skilled Labour,Engineer
71 Excavations for foundation6 days Tue 24/01/23 Tue 24/01/30 70 Unskilled Labour Unskilled Labour

Task Project Summary Inactive Milestone Manual Summary Rollup Deadline

Project: Preliminary Program_ Kir Split External Tasks Inactive Summary Manual Summary Critical
Date: Wed 23/03/01 Milestone External Milestone Manual Task Start-only Critical Split
Summary Inactive Task Duration-only Finish-only Progress

Page 2
ID Task Task Name Duration Start Finish Predecessors
Resource Names
Mode February 11 July 21 January 01 June 11
01/02 03/20 06/05 08/21 11/06 01/22 04/08 06/24
72 Steel fixing 6 days Wed 24/01/31 Wed 24/02/07 71 Skilled Labour Skilled Labour
73 Inspection & approval by8 Engineer
days Thu 24/02/08 Mon 24/02/19 72 Skilled Labour,Unskilled Labour Skilled Labour,Unskilled Labour
74 Casting of Concrete 8 days Tue 24/02/20 Thu 24/02/29 73
75 Placing of Geotextile biddim
1 day? Fri 24/03/01 Fri 24/03/01 74
76 Placing of retaining 1 day? Mon 24/03/04 Mon 24/03/04 75
blocks & backfilling
77 Inspection & approval by2 Engineer
days Fri 24/03/01 Mon 24/03/04 74 Engineer Engineer
78 Fencing 17 days Fri 24/02/23 Mon 24/03/18
79 Setting out 3 days Fri 24/02/23 Tue 24/02/27 2 Engineer,Skilled Labour Engineer,Skilled Labour
80 Excavations for poles 5 days Wed 24/02/28 Tue 24/03/05 79 Unskilled Labour Unskilled Labour
81 Erection of Fence and Gates
6 days Wed 24/03/06 Wed 24/03/13 80 Skilled Labour,Unskilled Labour Skilled Labour,Unskilled Labour
82 Approval by Engineer 3 days Thu 24/03/14 Mon 24/03/18 81 Engineer Engineer
83 SECTION 3 175 days?Fri 23/07/21 Thu 24/03/21
84 Construction of 3,0 ml Steel 173 Fri 23/07/21 Tue 24/03/19
Reservoir days
85 Site Clearance 143 daysFri 23/07/21 Tue 24/02/06
86 Clear & grub of grass, trees1 etc
wk Fri 23/07/21 Thu 23/07/27 2,13 Machines/ Plant Machines/ Plant
87 Earthworks 9 days Fri 23/07/28 Wed 23/08/09
88 Removal of topsoil 1 wk Fri 23/07/28 Thu 23/08/03 86 Machines/ Plant Machines/ Plant
89 Bulk Excavation 1 wk Thu 23/08/03 Wed 23/08/09 88FS-1Machines/
day Plant Machines/ Plant
90 Layerworks 20 days Thu 23/08/10 Wed 23/09/06
91 Importing & laying of G72 material
wks Thu 23/08/10 Wed 23/08/23 89,2 Machines/ Plant,Smooth Roller,Unskilled Labour Machines/ Plant,Smooth Roller,Unskilled Labour
92 Compaction & testing of2G7 wksmaterial
Thu 23/08/24 Wed 23/09/06 91 Laboratory,Push roller Laboratory,Push roller
93 Foundation and / or Ring Beam
50 days Thu 23/09/07 Wed 23/11/15
94 Excavation 2 wks Thu 23/09/07 Wed 23/09/20 92 TLB,Unskilled Labour TLB,Unskilled Labour
95 Casting of blinding 1 wk Thu 23/09/21 Wed 23/09/27 94 Skilled Labour,Unskilled Labour Skilled Labour,Unskilled Labour
96 Fixing of steel reinforcement
2 wks Thu 23/09/28 Wed 23/10/11 95 Skilled Labour,Unskilled Labour Skilled Labour,Unskilled Labour
97 Shuttering of the beam 1 wk Thu 23/10/12 Wed 23/10/18 96 Skilled Labour,Unskilled Labour Skilled Labour,Unskilled Labour
98 Inspection & approval by1 Engineer
wk Thu 23/10/19 Wed 23/10/25 97 Engineer Engineer
99 Casting of concrete 1 wk Thu 23/10/26 Wed 23/11/01 98 Skilled Labour,TLB,Unskilled Labour Skilled Labour,TLB,Unskilled Labour
100 Removal of shuttering 2 wks Thu 23/11/02 Wed 23/11/15 99 Skilled Labour,Unskilled Labour Skilled Labour,Unskilled Labour
101 Erection of Steel Stank 117 daysMon 23/08/28 Tue 24/02/06
102 Allow for ordering, 8 wks Mon 23/08/28 Fri 23/10/20 2
manufacturing and
delivery of the
103 Erection of Steel platform
2 wks Thu 23/11/16 Wed 23/11/29 100,102
Engineer Engineer
104 Erection & Assembling of 3 wks
Steel Tank
Fri 23/11/24 Thu 23/12/14 103FS-4
Machines/
days Plant Machines/ Plant
105 Erection of platform & 3 wks Mon 23/12/11 Fri 23/12/29 104FS-4
Machines/ Plant Machines/ Plant
External and External days
106 Assembling of inlet & 5 days Mon 24/01/01 Fri 24/01/05 105 Skilled Skilled Labour,Unskilled Labour
Outlet connection Labour,Unskilled
107 Backfilling around the footings
2 wks Mon 24/01/08 Fri 24/01/19 106 Skilled Labour Skilled Labour
108 Installation of External 1 wk Mon 24/01/22 Fri 24/01/26 107
& Internal access
Task Project Summary Inactive Milestone Manual Summary Rollup Deadline

Project: Preliminary Program_ Kir Split External Tasks Inactive Summary Manual Summary Critical
Date: Wed 23/03/01 Milestone External Milestone Manual Task Start-only Critical Split
Summary Inactive Task Duration-only Finish-only Progress

Page 3
ID Task Task Name Duration Start Finish Predecessors
Resource Names
Mode February 11 July 21 January 01 June 11
01/02 03/20 06/05 08/21 11/06 01/22 04/08 06/24
109 Inspection and 7 days Mon 24/01/29 Tue 24/02/06 108 Unskilled Labour Unskilled Labour
approval by Engineer
110 Water Tightness Test & 42 days Mon 24/01/22 Tue 24/03/19
Disinfection
111 Filling of the reservoir with2water
wks Wed 24/02/07 Tue 24/02/20 109 Water Tank Water Tank
112 Testing of water Tightness2 wks Wed 24/02/21 Tue 24/03/05 111 Client,Contractor,Engineer Client,Contractor,Engineer
113 Inspection & approval by 1 wk Wed 24/03/06 Tue 24/03/12 112 Engineer Engineer
Engineer
114 Disinfection of the Tank 3 days Wed 24/03/13 Fri 24/03/15 113 Contractor Contractor
115 Inlet & Outlet Pipework 42 days Mon 24/01/22 Tue 24/03/19
& Appurtances
116 Inlet & outlet pipeline 24 days Mon 24/01/22 Thu 24/02/22
117 Setting out 3 days Mon 24/01/22 Wed 24/01/24 107 Contractor Contractor
118 Excavations for trenches
1 wk Thu 24/01/25 Wed 24/01/31 117 Machines/ Plant Machines/ Plant
119 Trench preparation and 1 wk
shapingMon 24/01/29 Fri 24/02/02 118FS-3
Unskilled
days Labour Unskilled Labour
120 Laying of bedding 1 wk Mon 24/02/05 Fri 24/02/09 119 Skilled Labour,Unskilled Labour Skilled Labour,Unskilled Labour
121 Pipelaying 1 wk Mon 24/02/12 Fri 24/02/16 120 Skilled Labour Skilled Labour
122 Backfilling 1 wk Thu 24/02/15 Wed 24/02/21 121FS-2
Small
days
Machines,Unskilled Labour Small Machines,Unskilled Labour
123 Density tests 3 days Mon 24/02/19 Wed 24/02/21 122FS-3
Laboratory
days Laboratory
124 Approval by Engineer2 days Wed 24/02/21 Thu 24/02/22 123FS-1
Engineer
day Engineer
125 Inlet & Outlet Structures 22 days Mon 24/02/19 Tue 24/03/19
126 Inlet Structure 22 days Mon 24/02/19 Tue 24/03/19
127 Excavations 1 wk Mon 24/02/19 Fri 24/02/23 121 Unskilled Labour Unskilled Labour
128 Assembling of valve8 &days
fittings
Mon 24/02/26 Wed 24/03/06 127 Skilled Labour Skilled Labour
129 Brickwork & 1 wk Thu 24/03/07 Wed 24/03/13 128 Skilled Labour Skilled Labour
Placement of
130 Inspection by Engineer
4 days Thu 24/03/14 Tue 24/03/19 129 Engineer Engineer
131 Outlet Structure 15 days Mon 24/02/19 Fri 24/03/08
132 Excavation 3 days Mon 24/02/19 Wed 24/02/21 121 Contractor Contractor
133 Assembling of valve1 &wkfittings
Thu 24/02/22 Wed 24/02/28 132 Skilled Labour,Unskilled Labour Skilled Labour,Unskilled Labour
134 Brickwork & 1 wk Thu 24/02/29 Wed 24/03/06 133 Skilled Labour Skilled Labour
Placement of
135 Approval by Engineer2 days Thu 24/03/07 Fri 24/03/08 134 Engineer Engineer
136 Protection Works 46 days? Mon 24/01/15 Mon 24/03/18
137 Retaining Walls 36 days? Mon 24/01/15 Mon 24/03/04
138 Setting out 6 days Mon 24/01/15 Mon 24/01/22 2 Skilled Labour,Engineer Skilled Labour,Engineer
139 Excavations for foundation6 days Tue 24/01/23 Tue 24/01/30 138
Unskilled Labour Unskilled Labour
140 Steel fixing 6 days Wed 24/01/31 Wed 24/02/07 139
Skilled Labour Skilled Labour
141 Inspection & approval by Engineer
8 days Thu 24/02/08 Mon 24/02/19 140
Skilled Labour,Unskilled Labour Skilled Labour,Unskilled Labour
142 Casting of Concrete 8 days Tue 24/02/20 Thu 24/02/29 141
Skilled Labour,Unskilled Labour Skilled Labour,Unskilled Labour
143 Placing of Geotextile biddim 1 day? Fri 24/03/01 Fri 24/03/01 142
Skilled Labour,Unskilled Labour Skilled Labour,Unskilled Labour
144 Placing of retaining 1 day? Mon 24/03/04 Mon 24/03/04 143
Push roller,Skilled Push roller,Skilled Labour,TLB,Unskilled Labour
blocks & backfilling Labour,TLB,Unskilled
145 Inspection & approval by Engineer
2 days Fri 24/03/01 Mon 24/03/04 142 Engineer Engineer

Task Project Summary Inactive Milestone Manual Summary Rollup Deadline

Project: Preliminary Program_ Kir Split External Tasks Inactive Summary Manual Summary Critical
Date: Wed 23/03/01 Milestone External Milestone Manual Task Start-only Critical Split
Summary Inactive Task Duration-only Finish-only Progress

Page 4
ID Task Task Name Duration Start Finish Predecessors
Resource Names
Mode February 11 July 21 January 01 June 11
01/02 03/20 06/05 08/21 11/06 01/22 04/08 06/24
146 Fencing 17 days Fri 24/02/23 Mon 24/03/18
147 Setting out 3 days Fri 24/02/23 Tue 24/02/27 2 Engineer,Skilled Labour Engineer,Skilled Labour
148 Excavations for poles 5 days Wed 24/02/28 Tue 24/03/05 147 Unskilled Labour Unskilled Labour
149 Erection of Fence and Gates 6 days Wed 24/03/06 Wed 24/03/13 148 Skilled Labour,Unskilled Labour Skilled Labour,Unskilled Labour
150 Approval by Engineer 3 days Thu 24/03/14 Mon 24/03/18 149 Engineer Engineer
151 Subsoil Drainage 9 days Mon 24/03/11 Thu 24/03/21
152 Excavation 4 days Mon 24/03/11 Thu 24/03/14 2 Skilled Labour Skilled Labour
153 Placing of biddim, crushed 1 wk Fri 24/03/15 Thu 24/03/21 152 Unskilled Unskilled Labour,TLB
stone & pipeline Labour,TLB
154 Inspection & approval by Engineer
2 days Wed 24/03/20 Thu 24/03/21 153FS-2
Unskilled
days Labour,Skilled Labour Unskilled Labour,Skilled Labour
155 SECTION 4 115 daysMon 23/10/02 Fri 24/03/08
156 RAW WATER PIPELINE 115 daysMon 23/10/02 Fri 24/03/08
157 Site Clearance 15 days Mon 23/10/02 Fri 23/10/20
158 Clear & grub of grass, trees2 etc
wks Mon 23/10/02 Fri 23/10/13 2 Machines/ Plant,Unskilled Labour Machines/ Plant,Unskilled Labour
159 Removal of existing fences,2 walls
wks & Monpaving23/10/09 Fri 23/10/20 2 Unskilled Labour Unskilled Labour
160 Earthworks 22 days Wed 23/10/11 Thu 23/11/09
161 Removal of topsoil 3 wks Wed 23/10/11 Tue 23/10/31 158FS-3
Machines/
days Plant,Unskilled Labour Machines/ Plant,Unskilled Labour
162 Trench Excavation 2 wks Fri 23/10/27 Thu 23/11/09 161FS-3
Machines/
days Plant,Unskilled Labour Machines/ Plant,Unskilled Labour
163 Pipelaying 61 days Thu 23/11/02 Thu 24/01/25
164 Trench preparation & leveling3 wks Thu 23/11/02 Wed 23/11/22 162FS-6
Skilled
daysLabour,Unskilled Labour Skilled Labour,Unskilled Labour
165 Preparation of bedding (selected
3 wks granular
Wed 23/11/08
material)Tue 23/11/28 164FS-11
Skilled
days
Labour,Unskilled Labour Skilled Labour,Unskilled Labour
166 Pipelaying 3 wks Mon 23/11/20 Fri 23/12/08 165FS-7
Skilled
daysLabour Skilled Labour
167 Inspection & Approval by Engineer
2 wks Thu 23/11/30 Wed 23/12/13 166FS-7
Engineer
days Engineer
168 Blanketing (selected granular3 wks
material)
Thu 23/12/07 Wed 23/12/27 167FS-5
Skilled
daysLabour,Unskilled Labour Skilled Labour,Unskilled Labour
169 Backfilling (selected fill material)
3 wks Tue 23/12/19 Mon 24/01/08 168FS-7
Unskilled
days Labour Unskilled Labour
170 Backfilling of trench & compaction
2 wks Mon 24/01/01 Fri 24/01/12 169FS-6
Unskilled
days Labour Unskilled Labour
171 Topsoiling & re-instatement 2 wks
of grassFri 24/01/05 Thu 24/01/18 170FS-6
Unskilled
days Labour Unskilled Labour
172 Inspection & by Environmentalist
1 wk Fri 24/01/19 Thu 24/01/25 171 Environmentalist Environmentalist
173 Pipeline Appurtances 22 days Mon 23/12/25 Tue 24/01/23
174 Construction of Manholes22 fordays
Air, Scour
Mon 23/12/25
& IsolationTue
Valves
24/01/23
175 Excavations 1 wk Mon 23/12/25 Fri 23/12/29 166 Unskilled Labour Unskilled Labour
176 Assembling of pipework1 wk Mon 24/01/01 Fri 24/01/05 175 Skilled Labour Skilled Labour
177 Installation of valves 1 wk Mon 24/01/08 Fri 24/01/12 176 Skilled Labour Skilled Labour
178 Construction of chambers 1 wk Mon 24/01/15 Fri 24/01/19 177 Skilled Labour Skilled Labour
179 Inspection & Approval by 2 days
Engineer Mon 24/01/22 Tue 24/01/23 178 Skilled Labour,Engineer Skilled Labour,Engineer
180 Pipeline Pressure Testing 35 days Mon 24/01/22 Fri 24/03/08
181 In-house Testing 18 days Mon 24/01/22 Wed 24/02/14
182 Pipeline testing 2 wks Mon 24/01/22 Fri 24/02/02 178 Khoza Tradings Khoza Tradings
183 Identifying & repairing of2 wks
leakages Thu 24/02/01 Wed 24/02/14 182FS-2
Machines/
days Plant,Khoza Tradings Machines/ Plant,Khoza Tradings
184 Engineer's Approval 17 days Thu 24/02/15 Fri 24/03/08
185 Request for the Engineer1 towkwitnessThutests
24/02/15 Wed 24/02/21 183 Khoza Tradings Khoza Tradings
186 Pressure Testing 2 wks Thu 24/02/22 Wed 24/03/06 185 Khoza Tradings Khoza Tradings
187 Approval by Engineer 4 days Tue 24/03/05 Fri 24/03/08 186FS-2
Engineer
days Engineer

Task Project Summary Inactive Milestone Manual Summary Rollup Deadline

Project: Preliminary Program_ Kir Split External Tasks Inactive Summary Manual Summary Critical
Date: Wed 23/03/01 Milestone External Milestone Manual Task Start-only Critical Split
Summary Inactive Task Duration-only Finish-only Progress

Page 5
ID Task Task Name Duration Start Finish Predecessors
Resource Names
Mode February 11 July 21 January 01 June 11
01/02 03/20 06/05 08/21 11/06 01/22 04/08 06/24
188 Storage Dam Lining 109 daysMon 23/10/23 Thu 24/03/21
189 Laying of Class 2 Geotextile lining
6 wks Mon 23/10/23 Fri 23/12/01 2 Khoza Tradings Khoza Tradings
190 Laying of Geomembrane lining 6 wks Tue 23/11/28 Mon 24/01/08 189FS-4 Unskilled
days Labour,Machines/ Plant Unskilled Labour,Machines/ Plant
191 Placing of mesh wire 3 wks Tue 24/01/02 Mon 24/01/22 190FS-5Skilled
daysLabour,Unskilled Labour Skilled Labour,Unskilled Labour
192 Stacking of concrete panels 5 wks Fri 24/01/19 Thu 24/02/22 191FS-2Skilled
daysLabour Skilled Labour
193 Inspection & Approval by Engineer2 wks Fri 24/02/23 Thu 24/03/07 192FS-2Engineer
days Engineer
194 Fencing 17 days Fri 24/02/23 Mon 24/03/18
195 Setting out 3 days Fri 24/02/23 Tue 24/02/27 2 Engineer,Skilled Labour Engineer,Skilled Labour
196 Excavations for poles 5 days Wed 24/02/28 Tue 24/03/05 195 Unskilled Labour Unskilled Labour
197 Erection of Fence and Gates 6 days Wed 24/03/06 Wed 24/03/13 196 Skilled Labour,Unskilled Labour Skilled Labour,Unskilled Labour
198 Approval by Engineer 3 days Thu 24/03/14 Mon 24/03/18 197 Engineer Engineer
199 Subsoil Drainage 9 days Mon 24/03/11 Thu 24/03/21
200 Excavation 4 days Mon 24/03/11 Thu 24/03/14 2 Skilled Labour Skilled Labour
201 Placing of biddim, crushed 1 wk Fri 24/03/15 Thu 24/03/21 200 Unskilled Unskilled Labour,TLB
stone & pipeline Labour,TLB
202 Inspection & approval by Engineer
2 days Wed 24/03/20 Thu 24/03/21 201FS-2
Unskilled
days Labour,Skilled Labour Unskilled Labour,Skilled Labour
203 General Cleaning, Top-soiling, 2 wks Mon Fri 24/03/29 2 Machines/
Re-vegitation & Rehabilitation of 24/03/18 Plant,Small
pipeline route Machines,Unskilled
204 Snagging 1 wk Fri 24/03/22 Thu 24/03/28 62,67,145,150,154,130,135,77,82,198,202
Small Machines,Unskilled Labour Small Machines,Unskilled Labour
205 Practical Completion & Commissioning2 days Mon 24/04/01 Tue 24/04/02 204,203,41,109
Client,Engineer,Khoza Tradings
206 De-Establishment 1 day Wed 24/04/03 Wed 24/04/03 205 Khoza Tradings
207 Finish 0 days Wed 24/04/03Wed 24/04/03 206,14,46,114,159,172,187 04/03

Task Project Summary Inactive Milestone Manual Summary Rollup Deadline

Project: Preliminary Program_ Kir Split External Tasks Inactive Summary Manual Summary Critical
Date: Wed 23/03/01 Milestone External Milestone Manual Task Start-only Critical Split
Summary Inactive Task Duration-only Finish-only Progress